Loading...
HomeMy WebLinkAboutFile Documents.688 Spruce St.0119-2020-BRES (43) The Mozingo Code Group, LLC 261 W 79th Ct Denver, CO 80221 sdmozingo@mozingocodegroup.com PLAN REVIEW REPORT PROJECT 688 Spruce Street PROJECT LOCATION Aspen, CO DATE OF REVIEW December 21, 2020 REVIEW BASED ON PLANS DATED 10/16/2020 Architectural 08/20/2020 Structural REVIEW CONTACT Shaunna Mozingo, President The Mozingo Code Group LLC sdmozingo@mozingocodegroup.com 12/28/2020 688 Spruce Street, Aspen First Review 2 | P a g e Mozingo Code Group, LLC PROJECT INFORMATION ARCHITECT: CCY Architects STRUCTURAL ENGINEER: KL&A Engineers MECHANICAL ENGINEER: Resource Engineering Group ELECTRICAL ENGINEER: Resource Engineering Group CODES USED FOR REVIEW (as amended by Aspen) 2015 International Building Code 2015 International Mechanical Code 2015 International Plumbing Code 2015 International Energy Conservation Code 2020 National Electrical Code BUILDING INFORMATION New SFD Total Floor Area: 4930 Notice This cursory plan review is based on the codes noted herein and represents a list of corrections necessary to comply with the requirements contained within them. This review is not a building permit. The local jurisdiction is responsible for issuing the appropriate permits based on this review. The approval of plans and specifications does not permit the violation of any section of any federal, state or local regulations. All comments in this report are based on the information provided on the drawings and supporting documentation provided for review. The Mozingo Code Group, LLC does not accept any responsibility for any condition that was not known at the time of this report. We reserve the right to amend this report if additional information is received. This report does not purport to review, interpret, apply, or certify compliance with the accessibility requirements set forth within the Americans with Disabilities Act (ADA). The application, interpretation and enforcement of the ADA are vested with the Federal Department of Justice. Applicants are encouraged to seek professional review to ensure compliance with the ADA. 12/28/2020 688 Spruce Street, Aspen First Review 3 | P a g e Mozingo Code Group, LLC REVIEW COMMENTS The items noted below with a comment number (B-1, B-2 etc.) are items that need to be corrected to show compliance with the applicable codes. Please provide a written response indicating where the corrections are made on the plans. This will speed up the review process. Additional plan review comments may be added once revised plans are received for review. BUILDING CODE COMMENTS B-1 Refer to Sheets A202: Please specify how the glass guard behind the moveable screen meets the requirements of IRC Section R308.1 and its subsections, as amended by the City of Aspen. Please also provide construction details and specifications for the glass guard. B-2 Please specify where on the plans the provisions for IRC Section R309.6 Electric Vehicle Charging, as adopted by the City of Aspen, can be found. Sheet E-102 mentions an EV charging station in the garage but that is the only thing provided. B-3 Refer to Electric plans, Sheet E102: Plans contain a note that there will be pre-wiring for a future elevator. Separate permit required for future installation of an elevator per IRC Section R321.4 as amended by the City of Aspen. B-4 Refer to Sheet A502: Please specify how all of the exterior wall coverings will meet the wall covering requirements of Table R703.3(1). There are no details in the architectural or structural plans. Please also specify how the anchored stone veneer will meet the requirements for anchorage, air spaces, weepholes, etc of Section R703.8. The details say to refer to the structural plans, but the structural plans say it is per the architectural plans. B-5 Refer to Architectural Sheet A-500: Please specify how any enclosed rafter spaces meet the roof ventilation requirements of IRC Section R806.1 as amended by the City of Aspen. B-6 Refer to architectural, mechanical, electrical, and structural plans: Please specify how the 23.41 KW solar array meets the requirements of IRC Sections R902.4, R907 or R909, and R324. Sheet A-112 says to reference the mechanical plans but there are no specifications located within the mechanical plans. There is a small mention of the electric requirements in the electric plans but no specifications or details. The structural plans do mention in a comment that the roof load did take into consideration the PV array. Please also see electric comments below. STRUCTURAL COMMENTS S-1 Refer to Structural plans Sheet S-001: Please clarify why Seismic Design Category B was used instead of C, IRC Table R301.2(1) as amended by Aspen. Please also clarify 12/28/2020 688 Spruce Street, Aspen First Review 4 | P a g e Mozingo Code Group, LLC why an elevation of 5280 was used instead of 7400, or if it has any bearing on the calculations. Also please complete the notes in the Design Criteria table as they are incomplete or reference wrong codes and standards. S-2 Refer to Structural Sheet S-122: Please specify the proper description for Keyed note <1> as it is missing. The note applies at Grids C and D. S-3 Refer to Architectural Sheet A130: The plans call for a pulldown stair to access storage in the garage attic. Please clarify whether the attic has been designed for loads associated with storage and provide details for pulldown stair framing. S-4 Refer to Architectural Plans, Sheet A-425: Please provide details for the west outdoor room screen wall that is shown on the plans. MECHANICAL CODE COMMENTS M-1 Refer to Mechanical Plans: Please provide heating and cooling load calculations in accordance with IMC Section 312.1. There is a “total zone heat loss” summary but nothing to show how those losses were calculated. Also, Sheet M001 lists design conditions with a winter outdoor temperature of -20 and summer outdoor temperature of 95. Aspen’s design temperatures are -15 and 82. Please be sure that the load calculations submitted use these design temperatures and revise Sheet M001 accordingly. M-2 Refer to Mechanical Plans: Please provide ventilation calculations per IMC 403.3.2.1 through 403.3.2.3, as amended by the City of Aspen. Also, please specify the combination mechanical ventilation strategy used to meet the requirements of IMC 403.1, as amended by the City of Aspen. The plans show ERVs and exhaust fans in the controls sequence on Sheet M204 and a “max cfm” of 120 on Sheet M201 equipment schedule. Ventilation calculations are needed to show that the 120cfm is needed. M-3 Refer to Mechanical and Plumbing Plans: Please provide water heating and space heating sizing calculations in accordance with IMC 1002.2.1 to ensure the combined systems will each be met. 12/28/2020 688 Spruce Street, Aspen First Review 5 | P a g e Mozingo Code Group, LLC M-4 Refer to Mechanical Sheets: Exhaust fans are required in bathrooms and toilet compartments, not just the toilet compartments. Please provide exhaust fans in all rooms containing showers and/or tubs in accordance with M403, as amended by the City of Aspen. M-5 Refer to Electric Sheet E102: Please provide details and/or specifications for the patio heaters referenced in the electric sheets. PLUMBING CODE COMMENTS P-1 No plumbing sheets submitted. Refer to Architectural Sheet A-110 and Mechanical Sheet M101, project note #19: Plans show a hot tub (by others) but no other information has been submitted for the plumbing, electric, mechanical or energy efficiency of the hot tub. Please provide additional information in order to verify compliance. P-2 Refer to Sheet A110 and mechanical plans: Please provide gas pipe sizing calculations with your design in accordance with IFGC Section 402. Please note that the mechanical plans show boilers for both the home heating/water heating as well as for the snow melt. The gas pipe sizing needs to include all appliances. There is an outdoor bbq, outdoor heating and fireplace as well as multiple gas appliances within the home. On Sheet M001, there is a comment that the lines have been sized for a capacity of 1090 MBH. This may not be accurate with all appliances included in the calculation. ENERGY CODE COMMENTS EN-1 Refer to Mechanical and Architectural plans: The plans specify prescriptive Energy Code compliance. Please specify how the plans will comply with the following thermal envelope requirements: a. Slab Edge Insulation: There is a requirement for R10 insulation (R15 for heated slabs) for a depth of 4 feet at all slabs less than 12” below grade. Please specify how the slabs that are less than 12” below grade will meet the requirements of R402.2.10. (this requirement is in addition to the under slab insulation required for radiant slabs). b. Please clarify if the R13 insulation in Wall 6 and Wall 7 is truly continuous or cavity insulation. The plans say “ci” but the wall is a framed wall and this is closed cell sprayed being used. Will it be sprayed between the framing members 12/28/2020 688 Spruce Street, Aspen First Review 6 | P a g e Mozingo Code Group, LLC or continuously over the top of the framing members? If it is continuous, the detail is incorrect on Sheet A505. EN-2 Please specify how the hot water piping will meet the pipe insulation requirements of IECC Section R403.5.3 EN-3 Please specify how the fans used for the whole house mechanical ventilation system meet the efficiency requirements of IECC Section R403.6.1 as amended by the City of Aspen. EN-4 Please specify how the balanced ventilation system meets the requirements as set forth in IECC Section R403.6.2, as added by the City of Aspen. EN-5 Please specify how the snow melt system controls will meet the requirements of IECC R403.9. ELECTRICAL CODE COMMENTS Sheet E001 Project Information – Per Sec. 8.24.010 of city Amendments, correct to 2020 NEC as adopted by state October 1, 2020, most current edition. Electrical Specifications – C.1 – …per NECA 1. What is the reason for this reference? Sheet E002 One-Line Diagram – Anticipated 75kVA transformer – Justify size. Max 312.5 amps. Too small for calculated load from Load Calculation; CT Meter and Disconnect – Article 230.85 requires an Emergency Disconnect. Provide confirmation that the Disconnect will meet one of the design provisions from 230.82 (1) – (3) or an additional EM disconnect is required; Main Distribution Panel – Future Elevator in question. It has been included in the load calculation and is not noted as future; Tesla Gateway – Is there a current solar system in for review? Need product specifications for all Tesla Gateway, Generation Panel, Tesla Powerwall, AC Combiner, Solar Panels, Array disconnects, and associated OCPD’s for the system. Where is the Rapid Shutdown for PV as required per 690.12? General notes for this page – 2. Verify all loads have been included in Load Calculation. List of additional equipment is not reflected in the Load Calculation. Detail notes for this page – 11. - …to be rated 220A – This rating conflicts with one-line. Load Calculation – Area 5,756 SF differs from Architectural Plans Cover Sheet G-000 at 4,930 SF; Use of Art. 220.82 is based on known nameplate values. Load for Future Steam Showers and Assumed Patio Heaters in question; From Sheet M201 ASHP-1 & ASHP-2 are 31 amps at 230 volts. This value is only 14,880 VA as applied. Load calculation shows 19,215 VA; Only pumps 3, 8, and 9 are shown. From Sheet M204 Pumps 4, 5, 6, and 7 should be added based on use; Architectural Sheet A-10 show a Self-Contained Hot Tub. This load is not reflected; Where are the product specification sheets for all known values of equipment used? 12/28/2020 688 Spruce Street, Aspen First Review 7 | P a g e Mozingo Code Group, LLC Feeder Schedule – Feeder Note 2 – Ground to increase per 250.102 (C)(1) as this is a Supply- Side Bonding Jumper and not an Equipment Ground. Feeder Notes 6 & 7 – Feeders to be provided pending receipt/ review of PV Tesla system. Load Calculation EM-1 – Range at 1,750 VA while Range in Load Calculation is 1,725 VA. Why are these different?; Why are Pumps 4 & 7 accounted for when not on Load Calculation? Sheet E101 Provide General Note for page to require all 125-volt to 250-volt receptacles located on the lower level to be GFCI protected per 2020 NEC 210.8 (A)(5). Outdoor Kitchen/BBQ – AG receptacles are also required to be weatherproof per NEC 406.9 (A) & (B). PDR near Wet Bar – Missing EF-1? Sheet E102 Kitchen – Appears to have a built in Island from Sheet A-111. Provide general note to provide island receptacles as calculated from 2020 NEC 210.52 (C)(2). Garage – Garage Door receptacles to be GFCI protected per 210.8 (A)(2). Master Bath – Heated towel bars not included in Load Calculation. Sheet E103 Not reviewed. Pending PV submittal/ review. 12/28/2020