HomeMy WebLinkAboutFile Documents.285 Pfister Dr.0028-2020-BRES (13)1/20/2020
Division 1 GENERAL REQUIREMENTS $83,250.00 4.12%
01-100 Architectural Drawings By Others 0.00
01-140 Engineers By Others 0.00
01-150 Final Cleanup
Labor Allowance for Construction
Clean and Window Cleaning 8,500.00
01-190 General Laborers Labor Allowance 5,250.00
01-200 Insurance
Allowance for Prorated GL &
Umbrella 15,000.00
01-230 Permits & Fees By Others 0.00
01-240 Photographic/Reprographic Documentation 500.00
01-280 Project Manager No Charge 0.00
01-340 Temporary Toilet Allowance 1,500.00
01-370 Superintendent Labor Allowance 52,500.00
Division 2 SITEWORK $111,100.00 5.50%
02-140 Selective Demolition
Labor Alowance to remove cabinets &
walls at Kitchen/Pantry/Mudroom, (7)
fireplaces and surrounds, Great Room
ceiling, Entry & East wall window
units, half wall at upper level, all Bath
finishes per plan, Laundry Room
flooring & cabinets, etc. 75,000.00
02-220 Moving & Storage By Others. Empty site assumed.0.00
02-250 Radon Mitigation Existing system?0.00
02-290 Site Protection Labor and Material Allowance 25,000.00
02-330 Testing & Inspections Asbestos Test for Permit Application 1,100.00
02-340 Trash Removal Allowance 10,000.00
Division 3 CONCRETE $8,500.00 0.42%
03-180 Gypcrete / Light Weight Concrete
Labor and Material Allowance for new
skinny slabs in Kitchen, Pantry, and
Mud Room areas.8,500.00
Division 4 MASONRY $150,000.00 7.43%
04-120 Fireplace Masonry / Surrounds
Labor and Material Allowance - All
designs, material specifications, and
details TBD.150,000.00
Schedule of Values for:
Smith Residence: 285 Pfister Drive - Interior Remodel
Page 1 of 4
03/30/2020
Division 5 METALS $59,500.00 2.95%
05-165 Railings - Interior
Labor and Material Allowance for
approximately 85 LF of glass rail with
steel frames A $700.00/LF. All details,
metal finishes, etc. TBD 59,500.00
Division 6 WOOD & PLASTICS $259,250.00 12.84%
06-110 Disposable Tools Material Allowance 5,000.00
06-140 Fasteners & Adhesives Material Allowance 7,500.00
06-150 Finish Carpentry
Labor allowance for wood ceilings,
column wraps, trim at East windows
and doors, misc case & base, etc.75,000.00
06-160 Finish Lumber
Material Allowance for items listed in
06-150.22,000.00
06-200 Foreman / Lead Carpenter Labor Allowance 85,000.00
06-210 Labor Rough Carpentry
Labor Allowance to install Entry &
East window and door units, interior
partitions as drawn, fireplace surrounds
and misc. interior framing.56,250.00
06-240 Rough Lumber Material Allowance 8,500.00
Division 7 THERMAL/MOIST. PROTECTION $7,500.00 0.37%
07-100 Batt Insulation
Labor and Material allowance for new
foam and batt assemblies at Great
Room ceiling, new interior partitions,
and misc. infill as needed.7,500.00
07-200 Snow Retention Reflected in 07-180 0.00
Division 8 DOORS & WINDOWS $97,500.00 4.83%
08-100 Door Hardware
Material Allowance for new interior
door and cabinet hardware throughout.17,500.00
08-120 Entrance Doors Material Allowance 5,000.00
08-200 Windows
Material Allowance for East Windows
and Doors, & Office Door. Reveal or
equivalent. Verify Spec & Locations 75,000.00
Division 9 FINISHES $476,700.00 23.60%
09-100 Carpeting
Material and Labor allowance. No
specification provided.15,000.00
09-110 Drywall
Labor and material allowance for patch
and repair as necessary, Integral Plaster
in Kitchen and Great Room, retexturing
in areas of relocated doors, etc.100,000.00
09-130 Interior Painting
Labor and material allowance to
refinish interior
doors/casing/baseboard, prefinish new
wood ceilings & refinish trusses, paint
over existing skip trowel finish in
secondary spaces, etc.150,000.00
Page 2 of 4
03/30/2020
09-140 Mirrors
Allowance for plate glass mirrors at
new baths.1,200.00
09-150 Plaster Reflected in 09-110.0.00
09-170 Shower & Tub Enclosures
Labor and material Allowance for 1/2"
Starphire frameless glass enclosures at
new baths.18,000.00
09-180 Slabwork
Labor and Material Allowance for
Kitchen, Wet Bars and New Baths.75,000.00
09-230 Tile
Labor and Material Allowance for all
areas listed in 09-180 + additional
allowance for new floor in
Kitchen/Mudroom/Pantry area.100,000.00
09-240 Wood Flooring
Labor and Material Allowance to sand
and refinish existing hardwood floors
and stair treads & risers.17,500.00
Division 10 SPECIALTIES $61,500.00 3.04%
10-100 Fireplace & Stoves
Labor and Material allowance for (5)
new inserts with associated flueing.60,000.00
10-140 Toilet & Bath Accessories
Material Allowance for towel bars, TP
holders, etc.1,500.00
Division 11 EQUIPMENT $66,980.00 3.32%
11-100 Appliances
Mountain High Appliance Bid #143556
dated 1/9/2010.66,980.00
11-110 Appliance Installation Reflected in 11-110 0.00
11-120 Audio-Visual By Others 0.00
Division 12 FURNISHINGS $258,000.00 12.77%
12-100 Blinds & Curtains
Labor and Material Allowance - All
fabric selections and locations TBD.75,000.00
12-110 Cabinetry
Labor and Material Allowance for
Kitchen/Pantry/Mudroom areas, New
Baths, Wet Bars, Office and
miscellaneous cabinetry. 175,000.00
12-170 Shelving
Labor and Material Allowance for
glass and steel shelving at Great Room
Wet Bar. All other shelving reflected
in 12-110.8,000.00
Division 13 SPECIAL CONSTRUCTION $5,000.00 0.25%
13-100 Fire Suppression
Labor and Material Allowance to
relocate heads for updated
lighting/wood ceilings in Great Room
and miscellaneous changes due to
revised floorplans.5,000.00
Division 14 CONVEYING SYSTEMS $0.00 0.00%
Page 3 of 4
03/30/2020
Division 15 MECHANICAL $225,000.00 11.14%
15-100 Fixtures
Material Allowance for Kitchen, Wet
Bars, and All Baths.60,000.00
15-130 HVAC
Labor and Material Allowance for
forced air in Kitchen and Great Room
areas. Mini-split in Master Bedroom.65,000.00
15-150 Plumbing
Labor and Material Allowance for
rough-in changes at Kitchen, New
Baths and Wet Bars. New radiant heat
tubing assumed in Kitchen / Mud
Room / Pantry, and New Baths.100,000.00
Division 16 ELECTRICAL $150,000.00 7.43%
16-100 Electrical-120/240 Volt
Labor and Material Allowance for
updated lighting and controls in
Kitchen, Great Room, Master
Bedoom/Bathroom, and Family Room.
Secondary spaces assumed to be
relamped with LED and new trims
installed with new devices throughout.150,000.00
$2,019,780.00
Contractor's Fee @ 12%$242,373.60
$2,262,153.60
P.M. / Owner @ $125.00 Per Hour $0.00
Total:$2,262,153.60
Subtotal:
Subtotal:
Page 4 of 4
03/30/2020