HomeMy WebLinkAboutFile Documents.175 Paepcke Dr.0088-2020-BRES (3)Generated by REScheck-Web Software
Compliance Certificate
Project Burlingame Phase III - BLDG 09
Energy Code:2015 IECC
Location:Aspen, Colorado
Construction Type:Multi-family
Project Type:New Construction
Conditioned Floor Area:13,355 ft2
Glazing Area 13%
Climate Zone:7 (9922 HDD)
Permit Date:
Construction Site:
9A 173 Paepcke Dr & 9B 175
Paepcke Dr
Aspen, CO 81611
Owner/Agent:
Chris Everson
City of Aspen
130 S Galena St
Aspen, CO 81611
(970) 920-5000
Designer/Contractor:
Will Hentschel
359 Design
3630 Osage St
Denver, CO 80211
whentschel@359design.co
Permit Number:
Compliance: Passes using UA trade-off
21.2% Better Than Code Maximum UA:1512 Your UA:1191
The % Better or Worse Than Code Index reflects how close to compliance the house is based on code trade-off rules.
It DOES NOT provide an estimate of energy use or cost relative to a minimum-code home.
Compliance:
Envelope Assemblies
Assembly
Gross Area
or
Perimeter
Cavity
R-Value
Cont.
R-Value U-Factor UA
Ceiling: Flat Ceiling or Scissor Truss 4,988 30.0 30.0 0.017 85
EAST WALLS: Wood Frame, 16" o.c.5,229 34.0 6.0 0.033 128
Door: Solid Door (under 50% glazing)21 0.280 6
Door 1: Glass Door (over 50% glazing)288 0.280 81
Window: Metal Frame w/ Thermal Break 1,035 0.240 248
WEST WALLS: Wood Frame, 16" o.c.3,423 34.0 6.0 0.033 103
Door 2: Solid Door (under 50% glazing)120 0.280 34
Window 1: Metal Frame w/ Thermal Break 196 0.240 47
NORTH WALLS: Wood Frame, 16" o.c.1,830 34.0 6.0 0.033 59
Window 2: Metal Frame w/ Thermal Break 52 0.240 12
SOUTH WALLS: Wood Frame, 16" o.c.2,584 34.0 6.0 0.033 82
Window 3: Metal Frame w/ Thermal Break 96 0.240 23
Floor: All-Wood Joist/Truss 4,988 30.0 0.0 0.033 165
Basement: Solid Concrete or Masonry
Wall height: 11.0'
Depth below grade: 5.5'
Insulation depth: 11.0'
2,775 34.0 6.0 0.038 103
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 1 of 10
07/02/20Report date:08/26/2020
03/09/2021
State CO Housing Div
Assembly
Gross Area
or
Perimeter
Cavity
R-Value
Cont.
R-Value U-Factor UA
Window: Metal Frame w/ Thermal Break 63 0.240 15
Name - Title Signature Date
Compliance Statement: The proposed building design described here is consistent with the building plans, specifications, and other
calculations submitted with the permit application. The proposed building has been designed to meet the 2015 IECC requirements in
REScheck Version : REScheck-Web and to comply with the mandatory requirements listed in the REScheck Inspection Checklist.
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 2 of 10
07/02/20Report date:
Bruce Ivins 07/02/20
08/26/2020
Inspection Checklist
Requirements: 0.0% were addressed directly in the REScheck software
REScheck Software Version : REScheck-Web
Text in the "Comments/Assumptions" column is provided by the user in the REScheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Energy Code: 2015 IECC
Section
#
& Req.ID
Pre-Inspection/Plan Review Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
103.1,
103.2
[PR1]1
Construction drawings and
documentation demonstrate
energy code compliance for the
building envelope. Thermal
envelope represented on
construction documents.
Complies
Does Not
Not Observable
Not Applicable
103.1,
103.2,
403.7
[PR3]1
Construction drawings and
documentation demonstrate
energy code compliance for
lighting and mechanical systems.
Systems serving multiple
dwelling units must demonstrate
compliance with the IECC
Commercial Provisions.
Complies
Does Not
Not Observable
Not Applicable
302.1,
403.7
[PR2]2
Heating and cooling equipment is
sized per ACCA Manual S based
on loads calculated per ACCA
Manual J or other methods
approved by the code official.
Heating:
Btu/hr_____
Cooling:
Btu/hr_____
Heating:
Btu/hr_____
Cooling:
Btu/hr_____
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 3 of 10
07/02/20Report date:08/26/2020
Section
#
& Req.ID
Foundation Inspection Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
402.1.1
[FO4]1
Conditioned basement wall
insulation R-value. Where interior
insulation is used, verification
may need to occur during
Insulation Inspection. Not
required in warm-humid locations
in Climate Zone 3.
R-_____
R-_____
R-_____
R-_____
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
303.2
[FO5]1
Conditioned basement wall
insulation installed per
manufacturer’s instructions.
Complies
Does Not
Not Observable
Not Applicable
402.2.9
[FO6]1
Conditioned basement wall
insulation depth of burial or
distance from top of wall.
_____ ft _____ ft Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
303.2.1
[FO11]2
A protective covering is installed
to protect exposed exterior
insulation and extends a
minimum of 6 in. below grade.
Complies
Does Not
Not Observable
Not Applicable
403.9
[FO12]2
Snow- and ice-melting system
controls installed.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 4 of 10
07/02/20Report date:08/26/2020
Section
#
& Req.ID
Framing / Rough-In Inspection Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
402.1.1,
402.3.4
[FR1]1
Door U-factor.U-_____U-_____Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
402.1.1,
402.3.1,
402.3.3,
402.5
[FR2]1
Glazing U-factor (area-weighted
average).
U-_____U-_____Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
303.1.3
[FR4]1
U-factors of fenestration products
are determined in accordance
with the NFRC test procedure or
taken from the default table.
Complies
Does Not
Not Observable
Not Applicable
402.4.1.1
[FR23]1
Air barrier and thermal barrier
installed per manufacturer’s
instructions.
Complies
Does Not
Not Observable
Not Applicable
402.4.3
[FR20]1
Fenestration that is not site built
is listed and labeled as meeting
AAMA /WDMA/CSA 101/I.S.2/A440
or has infiltration rates per NFRC
400 that do not exceed code
limits.
Complies
Does Not
Not Observable
Not Applicable
402.4.5
[FR16]2
IC-rated recessed lighting fixtures
sealed at housing/interior finish
and labeled to indicate ≤2.0 cfm
leakage at 75 Pa.
Complies
Does Not
Not Observable
Not Applicable
403.3.1
[FR12]1
Supply and return ducts in attics
insulated >= R-8 where duct is
>= 3 inches in diameter and >=
R-6 where < 3 inches. Supply and
return ducts in other portions of
the building insulated >= R-6 for
diameter >= 3 inches and R-4.2
for < 3 inches in diameter.
Complies
Does Not
Not Observable
Not Applicable
403.3.5
[FR15]3
Building cavities are not used as
ducts or plenums.
Complies
Does Not
Not Observable
Not Applicable
403.4
[FR17]2
HVAC piping conveying fluids
above 105 ºF or chilled fluids
below 55 ºF are insulated to ≥R-
3.
R-_____R-_____Complies
Does Not
Not Observable
Not Applicable
403.4.1
[FR24]1
Protection of insulation on HVAC
piping.
Complies
Does Not
Not Observable
Not Applicable
403.5.3
[FR18]2
Hot water pipes are insulated to
≥R-3.
R-_____R-_____Complies
Does Not
Not Observable
Not Applicable
403.6
[FR19]2
Automatic or gravity dampers are
installed on all outdoor air
intakes and exhausts.
Complies
Does Not
Not Observable
Not Applicable
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 5 of 10
07/02/20Report date:08/26/2020
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 6 of 10
07/02/20Report date:08/26/2020
Section
#
& Req.ID
Insulation Inspection Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
303.1
[IN13]2
All installed insulation is labeled
or the installed R-values
provided.
Complies
Does Not
Not Observable
Not Applicable
402.1.1,
402.2.6
[IN1]1
Floor insulation R-value.R-_____
Wood
Steel
R-_____
Wood
Steel
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
303.2,
402.2.7
[IN2]1
Floor insulation installed per
manufacturer’s instructions and
in substantial contact with the
underside of the subfloor, or floor
framing cavity insulation is in
contact with the top side of
sheathing, or continuous
insulation is installed on the
underside of floor framing and
extends from the bottom to the
top of all perimeter floor framing
members.
Complies
Does Not
Not Observable
Not Applicable
402.1.1,
402.2.5,
402.2.6
[IN3]1
Wall insulation R-value. If this is a
mass wall with at least ½ of the
wall insulation on the wall
exterior, the exterior insulation
requirement applies (FR10).
R-_____
Wood
Mass
Steel
R-_____
Wood
Mass
Steel
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
303.2
[IN4]1
Wall insulation is installed per
manufacturer’s instructions.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 7 of 10
07/02/20Report date:08/26/2020
Section
#
& Req.ID
Final Inspection Provisions Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
402.1.1,
402.2.1,
402.2.2,
402.2.6
[FI1]1
Ceiling insulation R-value.R-_____
Wood
Steel
R-_____
Wood
Steel
Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
303.1.1.1,
303.2
[FI2]1
Ceiling insulation installed per
manufacturer’s instructions.
Blown insulation marked every
300 ft².
Complies
Does Not
Not Observable
Not Applicable
402.2.3
[FI22]2
Vented attics with air permeable
insulation include baffle adjacent
to soffit and eave vents that
extends over insulation.
Complies
Does Not
Not Observable
Not Applicable
402.2.4
[FI3]1
Attic access hatch and door
insulation ≥R-value of the
adjacent assembly.
R-_____R-_____Complies
Does Not
Not Observable
Not Applicable
402.4.1.2
[FI17]1
Blower door test @ 50 Pa. <=5
ach in Climate Zones 1-2, and
<=3 ach in Climate Zones 3-8.
ACH 50 =_____ACH 50 =_____Complies
Does Not
Not Observable
Not Applicable
403.3.4
[FI4]1
Duct tightness test result of <=4
cfm/100 ft2 across the system or
<=3 cfm/100 ft2 without air
handler @ 25 Pa. For rough-in
tests, verification may need to
occur during Framing Inspection.
_____ cfm/100
ft2
_____ cfm/100
ft2
Complies
Does Not
Not Observable
Not Applicable
403.3.3
[FI27]1
Ducts are pressure tested to
determine air leakage with
either: Rough-in test: Total
leakage measured with a
pressure differential of 0.1 inch
w.g. across the system including
the manufacturer’s air handler
enclosure if installed at time of
test. Postconstruction test: Total
leakage measured with a
pressure differential of 0.1 inch
w.g. across the entire system
including the manufacturer’s air
handler enclosure.
_____ cfm/100
ft2
_____ cfm/100
ft2
Complies
Does Not
Not Observable
Not Applicable
403.3.2.1
[FI24]1
Air handler leakage designated
by manufacturer at <=2% of
design air flow.
Complies
Does Not
Not Observable
Not Applicable
403.1.1
[FI9]2
Programmable thermostats
installed for control of primary
heating and cooling systems and
initially set by manufacturer to
code specifications.
Complies
Does Not
Not Observable
Not Applicable
403.1.2
[FI10]2
Heat pump thermostat installed
on heat pumps.
Complies
Does Not
Not Observable
Not Applicable
403.5.1
[FI11]2
Circulating service hot water
systems have automatic or
accessible manual controls.
Complies
Does Not
Not Observable
Not Applicable
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 8 of 10
07/02/20Report date:08/26/2020
Section
#
& Req.ID
Final Inspection Provisions Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
403.6.1
[FI25]2
All mechanical ventilation system
fans not part of tested and listed
HVAC equipment meet efficacy
and air flow limits.
Complies
Does Not
Not Observable
Not Applicable
403.2
[FI26]2
Hot water boilers supplying heat
through one- or two-pipe heating
systems have outdoor setback
control to lower boiler water
temperature based on outdoor
temperature.
Complies
Does Not
Not Observable
Not Applicable
403.5.1.1
[FI28]2
Heated water circulation systems
have a circulation pump. The
system return pipe is a dedicated
return pipe or a cold water supply
pipe. Gravity and thermos-
syphon circulation systems are
not present. Controls for
circulating hot water system
pumps start the pump with signal
for hot water demand within the
occupancy. Controls
automatically turn off the pump
when water is in circulation loop
is at set-point temperature and
no demand for hot water exists.
Complies
Does Not
Not Observable
Not Applicable
403.5.1.2
[FI29]2
Electric heat trace systems
comply with IEEE 515.1 or UL
515. Controls automatically
adjust the energy input to the
heat tracing to maintain the
desired water temperature in the
piping.
Complies
Does Not
Not Observable
Not Applicable
403.5.2
[FI30]2
Water distribution systems that
have recirculation pumps that
pump water from a heated water
supply pipe back to the heated
water source through a cold
water supply pipe have a
demand recirculation water
system. Pumps have controls
that manage operation of the
pump and limit the temperature
of the water entering the cold
water piping to 104ºF.
Complies
Does Not
Not Observable
Not Applicable
403.5.4
[FI31]2
Drain water heat recovery units
tested in accordance with CSA
B55.1. Potable water-side
pressure loss of drain water heat
recovery units < 3 psi for
individual units connected to one
or two showers. Potable water-
side pressure loss of drain water
heat recovery units < 2 psi for
individual units connected to
three or more showers.
Complies
Does Not
Not Observable
Not Applicable
404.1
[FI6]1
75% of lamps in permanent
fixtures or 75% of permanent
fixtures have high efficacy lamps.
Does not apply to low-voltage
lighting.
Complies
Does Not
Not Observable
Not Applicable
404.1.1
[FI23]3
Fuel gas lighting systems have
no continuous pilot light.
Complies
Does Not
Not Observable
Not Applicable
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 9 of 10
07/02/20Report date:08/26/2020
Section
#
& Req.ID
Final Inspection Provisions Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
401.3
[FI7]2
Compliance certificate posted.Complies
Does Not
Not Observable
Not Applicable
303.3
[FI18]3
Manufacturer manuals for
mechanical and water heating
systems have been provided.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: Burlingame Phase III - BLDG 09
Data filename:Page 10 of 10
07/02/20Report date:08/26/2020
2015 IECC Energy
Efficiency Certificate
Insulation Rating R-Value
40.00Above-Grade Wall
40.00Below-Grade Wall
30.00Floor
60.00Ceiling / Roof
_______Ductwork (unconditioned spaces):
Glass & Door Rating SHGCU-Factor
0.24Window
0.28Door
Heating & Cooling Equipment Efficiency
_______Heating System:_________________________
_______Cooling System:_________________________
_______Water Heater:___________________________
Name:Date:
Comments
08/26/2020