HomeMy WebLinkAboutFile Documents.134 E Bleeker St.0064-2022-BCHO (13)SMOKE ALARMS AND
CARBON MONOXIDE
DETECTORS REQUIRED
THROUGHOUT DWELLING
UNIT PER CITY OF ASPEN
MUNICIPAL CODE 8.15
These plans must be kept at the
building site or inspection
delays may occur. Construction
shall conform to these plans. All
changes shall be approved by
the building official.
Field Plan Set Must Be Printed In Color
SEPARATE PERMITS ARE
REQUIRED FOR ELECTRICAL,
PLUMBING, MECHANICAL, OR
FIRE SPRINKLER WORK
SEE NOTES #1 PLANS
It should be known that this review shall
not relieve the applicant of their
responsibility to comply with the
requirements of the City of Aspen
Municipal Code. Pursuant to
Sec.26.104.050, any permit or approval
issued in error or otherwise not in
conformity with the requirements of this
Title, shall be void. Similarly, any permit
or approval issued in reliance upon or
as a result of, a materially false
statement or representation made in
the process of obtaining the permit or
development approval shall, likewise,
be void. Any person having received a
void or voidable permit or approval
shall not be relieved from having to
comply with all applicable terms and
conditions of this Title and the City shall
not be estopped from fully enforcing
same.
bobn
10/12/2022ZONING
REVIEWED BY ZONING
10/12/2022 bobn
It should be known that this review shall
not relieve the applicant of their
responsibility to comply with the
requirements of the City of Aspen. The
review and approval by the City is
offered only to assist the applicant's
understanding of the applicable Land
Use Code requirements. The issuance
of a permit based on construction
documents and other data shall not
prevent the City of Aspen from
requiring the correction of errors in the
construction documents and other
data.
ALL OUTDOOR LIGHTING
MUST COMPLY WITH
THE CITY OF ASPEN LIGHTING CODE
SECTION 26.575.150
Reviewed by Engineering
10/19/2023 3:52:44 PM
"It should be known that this review shall not
relieve the applicant of their responsibility to
comply with the requirements of the City of
Aspen. The review and approval by the City is
offered only to assist the applicant's
understanding of the applicable Engineering
requirements." The issuance of a permit based
on construction documents and other data shall
not prevent the City of Aspen from requiring the
correction of errors in the construction
documents and other data.
City Development Engineer's Comments
1. Encroachments: Any existing or planned encroachments into the public
right-of-way, including temporary construction trailers and dumpsters, must be
applied for licensing at City Engineering (920- 5080). Five davs advance
notice is required to obtain a temporary encroachment license.
2. Right-of-way Permits: Approval of these plans by the City Building Dept. is
for work on private property only. Design approvals for proposed work
(including landscaping) in the public right-of-way (ROW) must be obtained
from City Engineering Dept. (920-5080) and Parks Dept. (920-5120) . A
permit for work in the public right-of-way must be obtained from the City
Engineering Dept. five days in advance of when the permit is needed.
3. Mud, dirt and debris may not be tracked onto the adjacent public ROW,
and the adjacent ROW must be clean at the end of eachworkday. Construct
mud rack if needed. Trucks hauling demolished materialsmust becovered.
4. Utilities in ROW: No utility pedestals, meters, or electric transformers can
be installed in the public right-of-way. Provide utility easements on private
property as needed.
5. Certificate of Occupancy (CO) Inspection: Engineering CO Inspection
includes but is not limited to: (a) witnessing that all property corners
havemonuments, (b) drainage improvements were installed as approved, (c)
easements are documented, (d) no unapproved ROW encroachments exist,
and (e) the ROW has been restored. Call 429-2750 to arrange CO inspection.
6. Snowmelt Driveways : (i) Snowmelt runoff from driveway cannot flow into
street . A grate or swale must intercept runoff before street. (ii) Snowmelt
installation in the public ROW requires an encroach- ment permit.
7. Drainage Issues: (i) Foundation drains cannot go to a dry well receiving
other drainage flows. (ii) City must be notified of drainage plan changes. (iii)
Plan approval assumes no ground water. If ground water is encountered, call
the Senior Dev. Engineer at 920-5080. Call for an open hole inspection prior
to placement of the drywell.
8. No Loose Material Storage allowed in R.O.W.
9. Neighbor Notification: For all excavation, the Contractor must comply with
neighbor notification requirements per Section 3307 of the 2003 International
Building Code (IBC)
REFERENCES FROM 2015 IRC
CV/A = crawl space ventilation required, sec. R408.1 Access required, R408.4
EE = emergency escape required sec R310.1
EU = enclosed usable space under stairs shall be ½” Gyp, sec R302.7
G/D = garage/dwelling separation, sec R302.5 and R302.6
STC = Sound transmission class not less than 45 at dwelling separations, app
K
RV = roof and rafter ventilation required, R806.1
A = attic access 22” x 30”, 30” headroom above, R807.1
SA = smoke alarms installed to NFPA 72 requirements, sec R314
CO = carbon monoxide detector per City Ordinance 41 series 2008
SG = safety glazing required, sec R308.4
GR = guardrails, 36” min ht, 4” max opening; req at 30” drop any point w/in 36”
horizontally, sec R312
WFP = window fall protection- operable window <24” AFF & >72” above
grade: use opening control device listed to ASTM F2090, sec R312.2
HR = handrails 34”-38” ht, sec R311.7.8
SI = stairway illumination, sec R303.7
PD = protect against decay, sec R317
REFERENCES FROM 2015 IMC
V = bathroom and balanced whole house mechanical ventilation req.
Ordinance 40, 2016
DE = clothes dryer exhaust, sec 504. Makeup air req’d if over 200 CFM
AS = access and service space for maintenance req’d, sec 306
MA = make up air required if hood exhausts greater than 400 CFM, sec 505.2
ET = exhausts terminate 3’ from prop line and openings, 10’ from intakes,
501.3.1
IT= intake openings 10’ from lot line & contaminant sources (vents, streets),
401.4
D = fasten and seal all ductwork per 603.9
REFERENCES FROM 2015 IFGC
DV = direct vent req’d, sec 303.3
CA = combustion air not taken from bedrooms, bathrooms or
storage sec 303.3
OD = outdoor appliances must be listed for outdoor use, sec 303.6
REFERENCES FROM 2015 IECC
F = new or replacement glazing shall not exceed 0.28 U-Value, NFRC label
required, Ordinance 40, 2016
L = 75% of lamps in permanently installed lights must be high efficacy, sec
R404.1
SE = Continuous air barrier required; all exterior joints, cracks, and holes to be
caulked, gasketed, sealed, table R402.4.1.1
REFERENCES FROM 2014 NEC
EP = electric panel 'happy space' 30"x36"x78", not in storage, sec 110.26
SPECIAL INSPECTION REQUIRED:
-Structural steel welding: Field & Shop
-High strength bolting
-Epoxy anchors
-Intumescent paint
-Spray applied fire resistive materials
-Permanent micropiles
Special inspection is required per 2015 IBC
section 1704. Inspector to verify that copy of
agreement for inspection program to be on
the job site prior to performing any
inspections. A copy of all Special Inspector
field reports to be on the job site for
inspectors' review if requested. Failure to
comply may result in denial of inspection.
GAS LOG
2015 IFGC Section 602:
Install per manufacturer’s instructions
Sec 634:
Permanently open damper
Sec 501.15:
Flue passageway, 1 sq in per 2000 btu/hr
input
Sec 409.1:
Shutoff valve req’d
2015 IRC Section R1001.5, R1004:
Firebox walls of masonry construction or
factory built.
Sec R1001.9, R1001.10:
Hearth and Extension supported by
non-combustible construction. Minimum
dimensions:
<6 sqft opening: 16” deep, 8” each side.
>=6 sqft opening: 20” deep, 12” each side.
Sec R1006:
Exterior air supply req’d. Intake no higher
than firebox
2015 IECC Section R402.4.2:
Flue sentinel or tight fitting door req’d
External Energy Use Approved
RREMP CREMP
PERMIT #:_______________DATE:________
SNOWMELT:_____________________________
POOL: _____________________________
SPA: _____________________________
OFFSET:________________________________
REMP SHEET: __________________________
REVIEWED BY: _________________________
SNOWMELT SYSTEM AND EQUIPMENT MANDATORY REQ’S.
All snowmelt systems shall meet the following:
-Any portions in the Right of Way must be on a separate zone. A ROW
permit and Permanent Encroachment License are required.
-R10 insulation shall be installed under the area to be snow melted or R5
insulation shall be installed under and at the slab edges. (Ordinance 11
Series 2011)
-Automatic controls installed for system shut off when pavement
temperature is above 50°F and no precipitation is falling. (2009 IECC
Sec. 403.8 & 503.2.4.5)
-Automatic or manual controls installed for system shut off when outdoor
temperature is above 40°F. (2009 IECC Sec. 403.8 & 503.2.4.5)
-Inspection by testing hydrostatically at 1½ times max system design
pressure, but not less than 100psi, for 15minutes. (2009 IMC Sec.
1208.1)
MINIMUM BOILER AFUE: _________________
0064-2022-BCHO
443.41 total= 175 #1 + 268.41 Changer order
1/11/24
X
98%
no
Jim Pomeroy
L0-01
01/12/2024
jimp
SEE NOTES #1 PLANS
1
APPLICATION ACCEPTED DATE: 2022-08-25 PERMIT NUMBER: 0064-2022-BCHO
COMMUNITY DEVELOPMENT DEPARTMENT
BUILDING PERMIT COVERSHEET
PROPERTY INFORMATION
ADDRESS: 134 E BLEEKER ST UNIT:
PARCEL ID: 273707315002 LEGAL DESCRIPTION: CITY AND TOWNSITE OF ASPEN
OWNER: 134 E BLEEKER LLC
PERMIT CONTRACTOR: STEEPLECHASE CONSTRUCTION
DESCRIPTION OF WORK No change to building footprint; no change to gross SF; no change to allowable SF. All fenestration changes
approved by HP Monitor as noted in elevations. See 10.Narrative Summary of Changes.
USE OF BUILDING Single Family FIRE SPRINKLER REQUIRED? Yes
CLASS OF WORK Residential FIRE SPRINKLER TYPE NFPA 13 D
BUILDING TYPE (IRC) One family REQUIRED SPECIAL
INSPECTIONS
High-Strength Bolting;Structural
Steel Welding
CONSTRUCTION TYPE ENERGY CODE COMPLIANCE Prescriptive Table
OCCUPANCY GROUP (IBC) R-3 WORK CHANGES BUILDING
FOOTPRINT? No
CODE EDITIONS 2015 IRC TOTAL SPA SQ.FT.
OTHER CODE EDITIONS TOTAL SNOWMELT SQ.FT. 443
HISTORIC PROPERTY? Yes TOTAL POOL SQ.FT.
FIRE SPRINKLER EXISTING?