HomeMy WebLinkAboutFile Documents.503 N 4th St.0074-2021-BRES (8) 2021
Construction
Management Plan
508 W. SMUGGLER STREET, ASPEN COLORADO 81611
HENDRICKSON CONSTRUCTION INC
RECEIVED
05/9.8/2021
ASPEN
BUILDING DEPARTMENT
Construction Management Plan
508 W. Smuggler Street, Aspen CO 81611
1.0 General
Total square feet of soil disturbed is zero (0.00 sf)
Total square feet of Building Footprint is Three Thousand Fifty(3050.00 sf)
2.0 Project Introduction
2.1 Disturbance Area: Total Project disturbance area is 4000 sf.
2.2 Location: 508 W. Smuggler Street, CO 81611 Vicinity Map Attached Page 6
2.3 Description/Background Information : Full Interior Remodel of a Duplex Located at
the Corner of 4th Street and W. Smuggler Street. The unit effected will be located at the
address mentioned within this CMP.
Construction Type V Can you provide more information on the scope? The
Occupancy Group R-6 permit description is only for siding, roof, and window
replacement, not a full interior remodel. Also, is the
work on both sides of the duplex, or just one?
3.0 Project Documentation.
3.1 Permit Types, Permit#s. Will be attached when issued.
3.2 Public/Project Notification. The project specific Construction Management Plan will
be presented at the preconstruction meeting. The CPM will address the project
representative,project schedule and estimated impact to applicable parties. All parties
within 300 ft will be notified a minimum 10 days prior to commencement of work.
3.3 Project Sign. Project sign shall be posted according to City Municipal Code 26.510.030B4
3.4 Contact List:
Owner— 508 West Smuggler St LLC
508 W. Smuggler Street
Aspen, CO 81611
Contractor: Hendrickson Construction Inc
130 Primrose Path
Aspen, CO 81611
Contact: Chris Hendrickson 970-274-6324
Project Manager: Ben Fierstein
Site Supervisor: Shaun Kennedy 970-948-4424
Architect: Alius Design Corps
Contact 719.331.9211
Michael@aliusdc.com
4.0 Project Implementation.
4.1 Dates of Construction: Date of permit issue plus two weeks to mobilize and 300 days to
construct.
4.2 Hours of Construction:
7:30 am- 5:30 pm Daily M-F and 9:00 am— 5:00 pm Saturday wh E C E IVE D
05/118/2021
ASPEN
BUILDING DEPARTMENT
necessary. Holidays and various Non Working days set
forth by the City of Aspen will be followed.
4.3 Construction Sequence-Schedule: Schedule includes 30 days of interior demolition 170
days to completion of roughs and interior framing. 100 days for finishing and completion.
4.4 Adjacent Property Owners: Adjacent Properties will be notified of the construction.
4.5 Construction Fencing. The perimeter of the lot will be fenced with a temporary six foot
tall chain link fence with green screen. Other fencing will include tree protection per the
documents.
4.6 Public Health and Welfare. All care will be taken by project proponents to protect the
public health and welfare, including dust control, noise control, and site maintenance.
4.7 Natural Environment. All tree and natural resource protection measures is identified in
the Plan and will be in place prior to the commencement of any construction or
demolition activities. Fencing will be installed outside the drip line of trees.
5.0 Site and ROW management plan
5.1 ROW Management Plan—See attached Plan
5.2 Emergency Vehicle Access and Ordinance 35. Ordinance 35 will be adhered to,
emergency access at the property will be maintained at all times.
5.3 Construction Parking Details. Critically important construction vehicles will utilize the
existing parking Driveways on Property and streetside parking. Small trucks and personel
vehicles will utilize street parking along the west end. Overflow vehicles will be required
to park at the Galena Street parking structure and shuttle over to the jobsite.
5.4 Staging Areas. Staging of materials will occur on site within the fenced in backyard.
Absolutely no staging will occur within the City ROW.
5.5 ROW Limitations. No construction trailer will be required, all materials will be
delivered at time of use, and small materials will be stored in the unit or within the
backyard. No loose material will be stored in any public right-of-way. Trucks will be able
to utilize the alleyway to the North of the Property. Necessary ROW and Encroachment
permits will be pulled for activities requiring staging within the ROW or Alleyway and
coordination with the neighbors will occur.
5.6 CONSTRUCTION TRAILER, MATERIALS STORAGE,AND WASTE
MANAGEMENT
Waste management will be handled by bear proof waste carts placed on site.
Construction related materials will be sorted on site and placed in appropriate containers.
See ROW plan for details
6.0 Traffic Control.
6.1 General. All traffic control operations shall be managed by the designated certified
traffic control supervisor
6.2 Haul Routes. See attached plan.
6.3 Onsite Vehicle Limitations. All vehicles proposed to be used will qualify for road
vehicle weight and height limitations.
6.4 Delivery requirements. Trips will be coordinated to ensure that only one large truck will
be onsite at any given time. Delivery vehicles will not be allowed to idle for moregEt EIVED
05/18/2021
ASPEN
BUILDING DEPARTMENT
mins per City of Aspen Vehicle Idling regulations
6.5 Traffic Control Plan. There are no bus stops or school bus stops that will be impacted.
No traffic disruptions are planned or proposed. If any activities needing to interfere with
the Public ROW a Traffic Control Plan will be prepared by a state certified Traffic
Control Supervisor.
7.0 Pedestrian Protection. The project will comply with pedestrian safety per City code
21.04.060,MUTCD Chapter 6D, the Americans with Disability Act, and IBC Chapter 33.
8.0 Sediment Control.
8.1 General. All necessary Best Management Practices (BMP's)will be in place and
maintained in order to minimize sediment leaving the perimeter of our jobsite. Primary
strategies include:
• Avoid unnecessary site disturbance
• Maintain Grading; install silt fences and seditment traps prior to any soil
disturbance
• Due to the limited space available on site, a tracking pad will be
impractical. Screened rock and geotextile fabric will be lined along our
excavation ramp.
• Concrete washout will be done back into the concrete trucks due to lack of
space.
• Spills will be captured into hard plastic "kiddie"pools and allowed to dry,
then placed in a site trash receptacle.
• All pathways into site will be lined with screened rock over geotextile
fabric.
8.2 Smuggler Mountain Restrictions. Do not apply.
8.3 Stormwater Control Plan. Project is interior only. All deliveries and material storage
will comply with City Code.
9.0 Fugitive Dust Control Plan
The project will avoid unnecessary site disturbance and keep a hose and spray nozzle
available to mitigate born dust.
10.0 Emissions.
10.1 General. The project intends to comply with City Code.
10.2 Emissions for Diesel Powered Engines. The project intends to comply with City Code.
11.0 Noise Suppression.
11.1 General. The project intends to comply with City Code.
11.2 Noise Suppression Plan. Contractor will follow City Code.
11.3 Requirements for activities exceeding 70 decibels. The Project intends to comply with
City Code. Notices will be posted to advise workers and sub-contractors of noise
requirements.
11.4 Specific restrictions related to manufacturing on site. It is not proposed that any
manufacturing will occur on site.
12.0 Enforcement. RECEIVED
05/18/2021
ASPEN
BUILDING DEPARTMENT
12.1 City Construction Mitigation Officer. The project intends to comply with City Code.
12.2 Corrective Action. The project intends to comply with City Code.
12.3 Inspection Reports. The project intends to comply with City Code.
13.0 CONSTRUCTION MITIGATION COMMITTEE - The project is not applying for
any exemptions
Please provide a site plan. Include the following information:
1. site plan with property line
2. location of construction fence and access points
3. location of onsite parking
4. location of porta john
5. location of dumpster
6. material staging locations
7. location of trees with drip line protection zones shown
RECEIVED
05/18/2021
ASPEN
BUILDING DEPARTMENT