HomeMy WebLinkAboutFile Documents.300 S Spring St.0054-2020-BCOM (2)Construction Management Plan_______________________________________ To: City of Aspen Building Department 130 South Galena Aspen, Co 81611 From: Adrian A Gomez, OwnerFeralli Construction LLC 6968 HWY 82 #19 Glenwood Springs CO 81601 Construction Management Plan 300 Spring St. Suite 200 1. Project Introduction 1.1. Hanover Offices is located on the 2nd floor of 300 S. Spring St. unit 200. This space is 838SF of floor area. Material staging will be located on the south side of the building within the alley access and long-term storage will be in the space itself. 1.2. Vicinity Map: QuickTime™ and a decompressorare needed to see this picture. QuickTime™ and a decompressorare needed to see this picture. 1.3. The property contains a mixed-use building located in downtown Aspen on the SW corner of Spring St.and Hyman Ave. There are multiple existing occupied tenant spaces in this building. The scope of this construction consists of an interior office space remodel and will be completed in 1 phase. We anticipate starting the project in the beginning of March with the expectation of total project buildout taking no more than six weeks. Scope of work includes demolition of the existing interior of the office space and the reconstruction of the new office including minor MEP rework. This building is serviced by public utilities. There are no plans for upgrading any of the utility services. 2. Project Documentation 2.1. Adjacent tenants and properties will be notified of work and provided contact information via the posting of the project sign the immediate neighbor will be notified of this construction and informed on an as need basis of possible construction impacts. This sign will include a brief scope of work and list contractor’s contact information. Because impacts beyond the licensed ROW area are not anticipated, specific notification and on-site meeting should not be necessary. 2.2. A project sign will be posted on the entry door of the building with the contractor's contact information. See exhibit A 2.3. Contact List: Owner: Hanover Offices General Contractor: Feralli Construction LLC, Adrian Gomez (970) 309-4720 Site Supervisor: Larry Flores (970) 319-6029 Safety Officer: Larry Flores (970) 319-6029 Traffic Officer: Larry Flores (970) 319-6029 3. Project Implementation 3.1. Dates of Construction: Construction is expected to last 10 weeks (Feb 14, 2022 – May 15, 2022) and will only occur on approved dates Monday through Saturday. 3.2. Hours of Construction: Construction activity will only occur during the allowed hours of 7:30AM and 5:30PM Mon - Friday and 9AM to 5PM on Saturdays. 3.3. Excavation will not occur or encroach within 5’ of the property line. 3.4. Project is all interior scope so no job site fencing will be installed. 4. Project Management 4.1. Parking for subcontractors and Feralli Construction LLC employees will be limited to street parking within the 2hr zone. Temporary material staging will be located on to the south side of the building in the alley as well. 4.2. Parking at the site is limited and is all metered. Public transit will be encouraged and utilized to the greatest extent practicable. 4.3. Map of Construction Management Plan is attached as Exhibit B. 4.4. Feralli Construction will maintain continuous emergency vehicle access on and around the site, including but not limited to police, fire and ambulance services See attachment C; Ordinance # 35 5. Traffic Control 5.1. Traffic Control Supervisor will manage operations, if and when necessary. 5.2. Designated haul routes will be followed. Exhibit D 5.3. Maximum vehicle weight shall not exceed 10,000lbs. 5.4. Any traffic control required for deliveries will be coordinated with the City of Aspen Engineering Department. Deliveries will not be scheduled outside of the approved hours of construction. No more than one delivery truck can be accommodated at any time. Deliveries will be unloaded via the entry doors on S Spring St. in early morning hours or off loaded with-in the alleyway to the south of the building. 5.5. A Traffic Control Plan is not included as road blockages or traffic stoppages are not scheduled or anticipated due to the limited scope and nature of the project. 6. Pedestrian Protection 6.1. Pedestrian safety will be maintained per City Code Section 21.04.060, MUTCD Chapter 6D, the Americans with Disability Act, and IBC Chapter 33. 7. Sediment and Erosion Control – NA 8. Fugitive Dust Control – N/A. 9. Emissions – All construction vehicles will be maintained and in good running order. 10. Noise Suppression 10.1. Construction noise will be limited to 80 decibels at the property line whenever possible. And are not expected to be a concern with all construction activity contained indoors. 10.2. Loud or obtrusive work will be completed during the approved hours of 9AM to 5PM (Monday through Friday only). Neighbors will be notified 3 days advance. Hanover Offices ADDRESS: 300 Spring St. Suite 200 Aspen, CO 81611 Building Permit #: 0054-2020-BCOM 24 Hr Emergency Contact: Larry Flores 970.319.6029 FERALLI CONSTRUCTION GENERAL CONTRACTOR - CONSTRUCTION MANAGEMENT ROLL-IN ANSI SHOWER AND GRAB BARS FREE STANDING ANSI SHOWER BENCH COMMON WORKSPACE 200 OFFICE 201 OFFICE 202 OFFICE 203 OFFICE 204 OFFICE 205 ANSI RESTROOM 206 B OCCUPANCY 838 SF / 100 = 9 OCCUPANTS EXIT ACCESS AND COMMON PATH OF EGRESS TRAVEL = 21'-6" TOILET GRAB BARS EXISTING BUILDING, NOT IN SCOPE EXISTING SHELL, WINDOWS AND DOORS TO REMAIN DEAD END 8' - 10" 4 A0.2 4 A0.2 EXISTING BUSINESS OCCUPANY EXISTING ELEVATOR EXISTING NON-RATED FLOOR/CEILING ASSEMBLIES TO REMAIN 1/4" = 1'-0"2 LIFE SAFETY / UNIT ADJACENCIES PLAN 782.59 sf E. Hyman Ave S. S p r i n g S t . temporary staging and material deliver to be located in alleyway Main access stair and elevator from Spring St.t Exhibit B E MAI N S T W MAI N S T E DUR A N T A V E E HOP K I N S A V E GI B S O N A V E E COO P E R A V E W HAL L A M S T W BLE E K E R S T N T H I R D S T S A S P E N S T W FRA N C I S S T N F I F T H S T W HO P K I N S A V E N M I L L S T NORTH S T N S I X T H S T W SM U G G L E R S T N F O U R T H S T S M O N A R C H S T P A R K A V E S M I L L S T R E D M T N R D N F I R S T S T S O R I G I N A L S T LA K E A V E N S E C O N D S T S G A R M I S C H S T LO N E P I N E R D O A K L N S H U N T E R S T S W E S T E N D S T E BLE E K E R S T N S P R I N G S T NEA L E A V E VINE ST S F I R S T S T S H A D Y L N MI D L A N D A V E E HYM A N A V E S G A L E N A S T GILLESPIE AVE W HY M A N A V E DEAN S T KIN G S T RI O G R A N D E P L N E I G H T H S T S S P R U C E S T M A P L E L N PAR K C I R N G A R M I S C H S T RA C E S T E HAL L A M S T WATE R S A V E N A S P E N S T S T H I R D S T N SPRUCE ST T E A L C T A J A X A V E N I C H O L A S L N W CO O P E R A V E JUAN S T WI L L I A M S W Y ASPEN MTN R D P U P P Y S M I T H S T QUEEN ST CL E V E L A N D S T L A C E T L N FOUN D E R S P L A C E C O T T O N W O O D L N S R I V E R S I D E A V E N S E V E N T H S T PEARL CT SOUTH AVE SUMM I T S T GILB E R T S T S F I F T H S T S S I X T H S T W NO R T H S T S F O U R T H S T S S P R I N G S T N R I V E R S I D E A V E S S P R I N G S T DEAN S T S G A L E N A S T N S E V E N T H S T P A R K C I R DEAN S T S M I L L S T AS P E N M T N R D Map prepared by Engineering and GIS Department City of Aspen, CO 81611 May 4,2007 0 600300 Feet Legend Designated Heavy Haul Route Roads Parcels City Boundary OFFICIAL HEAVY HAUL ROUTE MAP 300 Spring st. suite200 ATTACHMENT C - HAUL ROUTE MAP ATTACHMENT D - ORDINANCE 35