931 Gibson — Change Order 1
PROJECT: 931 GIBSON AVE,ASPEN CO 81611
PPERMIT NUMBER: 0036-2019-BRES
DATE: Monday,December 5,2022
To City of Aspen:
The following is a list of requested changes to building permit 0036-2019-BRES.The bulk of the
changes are a result of two factors. First,the Historic Asset's foundation was poured incorrectly.This resulted in
a shift of building footprint location,but not in size.Second,ownership of the project and property changed in
June of 2021.The programmatic design changes are listed below.
Site:
1. Footprint:
Due to surveyor and previous contractor error,the foundation for the historic structures was poured
1'9"East and 1 1/4"South of where it was originally drawn.This change order includes the updated
plans showing how the whole footprint shifted slightly and modified the driveway and auto court to
still fit within our building envelope.
a. A1.1 Site Plan
b. All Civil Plans
c. All Landscape Plans
2. Electrical Service:
Existing electrical service was improperly scabbed together, and insufficient for new construction.
Holy Cross Energy requested a new service originating from southern existing transformer,and
accessible via Gibson Ave.
- Please reference Sheet A1.1.and C600.
3. Landscape and Irrigation Design
a. Added Spa and Spa Patio
i. See new Landscape Sheets—and new PL Sheets
b. Corresponding Changes to Adjusted Driveway and Auto court
c. New Planting plans for new owner
d. New Irrigation plans coordinated with new Landscape Plans
4. Civil Design:
a. New Electrical Service
b. New Water Service
c. New Sewer connection design
d. Adjusted Driveway and Auto court corresponding to building footprint shift
e. Added Drywell for Condenser drainage
f. Corresponding Changes due to Added Spa
g. Coordinated Drainage design and report
Architectural Sheets:
RECEIVED
Initial F & M ARCH I T E C T S 1 2/12/2 0 2 2
Enduring Architecture. Lasting Relationships 1 o 4
ASPEN
BUILDING DEPARTMENT
1. A1.3 REMP Plan
a. Added/modified snowmelt to patio and driveway areas of the project
2. A2.1 Basement/Foundation Plan
a. Theater 001 was changed to SPA 001: 1 shower, 1 recirculating water feature, 1 steam room, 1
sauna and 1 sink were added.
b. Bath 003 flipped shower and WC rooms
c. Revised Stair 020 with storage space underneath
d. Added Wine Room 007
e. Added Bar in Entertainment 008: 1 sink added
f. Larger Laundry 005 and Framing/Doorway changes to Therapy 011-No fixture changes
g. Detailed Mechanical Chase South of Mech 006
h. Revised Closet framing in Bed 015/Bath 013
i. Radon Vent locations
3. A2.2 Main Level Plan
a. Powder 107 has moved locations
b. Added Bar 102-1 Sink Added
c. Changed Fireplace Appliance in Speakeasy 101
d. Kitchen 105 fixtures and appliance location changes-No Fixture Changes
e. Replaced hood vent with Downdraft ventilation for Range
f. Patio Bar 111 framing changes for Mechanical ventilation
g. Living 110 South wall framing changes
h. Living 110 fireplace manufacturer and design change
i. Added Powder Room 112 adjacent to Mudroom—1 sink, 1 toilet added
j. Garage 106 shows lower-level spa mechanical equipment in cabinetry
4. A2.3 Upper Level Plan
a. Master bath 205 plumbing and framing changes.
i. Added 1 shower head,and 1 drain
ii. Removed 1 bathtub
iii. Added 1 Clothes Washer and 1 Electric Dryer
b. Roof Deck 204 framing and plumbing changes
i. Move stairs behind parapet wall
ii. Change to perimeter slot drains
iii. Add 1 Fire pit
iv. Add outdoor kitchenette: 1 Sink
c. Remove Skylight in Master Bed 208
d. Guest Suite 201 and Bath 202
i. Changed Fireplace Appliance
ii. Nonbearing Closet wall changes
iii. Bath Plumbing location and framing changes-No fixtures added
5. A2.4 Roof Plan
a. Added PV Array
b. Radon Exhaust Vent Locations
c. Removed Skylight W-35
d. Revised Drainage for Roof Deck 204 RECEIVED Initial F & M ARCH I T E C T S 12/12/2 0 2 2
Enduring Architecture. Lasting Relationships 2 o 4
ASPEN
BUILDING DEPARTMENT
6. A2.5-2.7 RCPs vs EL Sheets
a. Lighting Design has been removed from RCPs and now exists on EL Sheets by Kevin
White Lighting
7. A3.1-3.4 and A4.1&2 Exterior Elevations—Building Sections
a. Removed Skylight W-35
b. W-13 and 23 openings are shorter,Widths remain the same
c. Thermally treated wood replaced with Metal panel siding
d. Metal paneling for Garage Door.Match other exterior metal paneling
e. Exterior aluminum louvers Over W-24,mechanically operated
f. Top of Roof Deck Ply changed to 108'-1 1/4"
g. Top of Deck changed to 108'-9 1/2"
h. W-22 and D-18 openings are shorter,Widths remain the same
8. A5.1&2 Wall Sections/Details
a. Structural and waterproofing details have been refined
9. A5.17&18 Fireplace Details
a. Fireplace Appliance Manufacturer Changes and Details
10. A6.1 Roof Assemblies
a. Modified Roof Deck Assembly with tapered insulation and snowmelt
11. A6.2 Wall Assemblies
a. Modified Historic wall assembly with sheathing,WRB and cavity rockwool
b. Modified Brick wall Assembly with AWB behind 1"rigid
12. A10.1 & 10.2
a. Clouded windows with minor dimensional and operational changes to work with
detailing
b. Clouded entire Door Schedule as all Doors have changed slightly with added details.
Structural Design:
1. New Structural sheets have been clouded to show revisions with requested changes and rectifying
previous errors.
MEP Design:
1. New Mechanical plans have been provided.Previously we had no plans,just a letter from engineer
stating that the project would be properly heated,cooled ventilated,and specified an ERV
2. New Electrical plans have been provided,which were not originally in permit set
3. New EL sheets with lighting design have been provided which replace the original lighting design
4. New Plumbing plans have been provided,which were not originally in permit set.
End of Document
RECEIVED
Initial F & M ARCHITECTS 12/12/2022
Enduring Architecture. Lasting Relationships 30.14
ASPEN
BUILDING DEPARTMENT
By: Patrick Westfeldt,Project Architect
F&M Architects LLC
Project:931 Gibson
Project No.:21040