HomeMy WebLinkAboutFile Documents.332 W Main St.0031-2023-BCOM (9) 9/7/23,3:13 PM Forum Phi Mail-Re:332 W Main sprinkler requirements
PiGmail Mark Hardeman <mhardeman@forumphi.com>
Re: 332 W Main sprinkler requirements
1 message
Jan Legersky <Jan.Legersky@aspenfire.com> Tue, Sep 5, 2023 at 11:58 AM
To: Mark Hardeman <mhardeman@forumphi.com>
Hi Mark,
Thanks to you and Ryan for the site visit. It helped very much to see what has been done and review your plans for this
space.
Based on the current scope of work, I would not require the addition of sprinklers at this time. Aspen Fire requires the
sprinklers in remodels when approximately 50% of the drywall has been removed from ceiling and/or walls. This project
falls far short of that 50%threshold.
If the scope of work changes, and more drywall ends up being removed, I would request that we review the project again
to review sprinkler coverage.
Please let me know if you have any questions, or need any other information. Feel free to share or forward this email with
the building department.
Jan
Jan Legersky
Fire Marshal
Aspen Fire Prot Dist
420 E.Hopkins Ave.
Aspen,CO 81611
970-925-2690(w),970-379-1522(c),970-920-4451 (fax)
email: jan.legersky@aspenfire.com