3.16.2023 332 Main Street FP Budget Notes
CODE CATEGORY As per drawings dated 3.15.2023
DIV 01:GENERAL CONDITIONS
1-101 Project Management/Supervision 41,500 Allowance
1-110 Blueprints/Copies 350 Allowance
1-295 Permits/Fees 0 By Owner
1-301 Jobsite Office/Equipment 800 Allowance
1-315 Survey/Layout Allowance 0 N/A-By Owner If Any Changes
1-380 Protection of Finished Work 4,300 Includes Finished Floor Protection
1-390 Winter Conditions 0 N/A
1-452 Soils and Materials Testing 0 N/A
1-510 Temporary Electric 0 N/A
1-512 Temporary Heat 0 N/A
1-514 Temporary Phone 0 N/A
1-516 Temporary Toilet 600 Allowance
1-542 Equipment/Crane Rental 5,000 Includes Jack Hammer
1-560 Temporary Site Fencing 0 N/A
1-585 Utility Fees 0 By Owner
1-705 Trash Removal/Dumpster 7,200 Excluding Asbestos Removal
1-800 Construction/Final Window Clean 2,300 Includes Window Cleaning,Interior Walls/Floors/Fixtures
1-815 Site Maintenance 1,500 Includes Street Cleaning(If Needed)
Division 1 Total 63,550
DIV 02:SITE MAINTENANCE
2-900 Landscaping/Irrigation 5,300 Includes Grading/Gravel For Exterior ADA Ramp As Per Required By COA
Division 2 Total 5,300
RECEIVED
09/17/2023
ASPEN
BUILDING DEPARTMENT
3.16.2023 332 Main Street FP Budget Notes
CODE CATEGORY As per drawings dated 3.15.2023
DIV 03:CONCRETE
3-100 Foundation/Footings 0 N/A
3-720 Exterior Slabs 6,400 Allowance For New Exterior ADA Ramp
3-730 Interior Slabs on Grade 1,500 Includes Misc Floor Repairs
Division 3 Total 7,900
DIV 04:MASONRY
Division 4 Total 0
DIV 05:METALS
Division 5 Total 0
ti
DIV 06:WOOD&PLASTICS
6-075 General Labor 7,500 Includes General Daily Clean Up
6-080 Demolition Labor 26,500 Inludes Flooring,Millwork,Trim,Drywall
6-100 Framing Labor 3,800 Includes Minor Wall Framing.Excluding Front Porch Revisions/Renovations
6-101 Framing Materials _ 2,100 Includes Wall Materials
6-200 Interior Trim Labor _ 24,300 Includes Casing/Base.Excluding Large Repairs At Exterior Window Openings
6-201 Interior Trim Materials _ 7,900 Includes Casing/Base
6-300 Exterior Siding/Trim Labor 0 N/A
6-301 Exterior Siding/Trim Materials 0 N/A
Division 6 Total 72,100
NEW—
DIV 07:THERMAL&MOISTURE PROTECTION _
7-110 Foundation Waterproofing _ 0 N/A
7-210 Building Insulation/Vapor Barrier 1,500 Allowance Misc Small Batt Repairs
7-220 Roofing 0 N/A
Division 7 Total 1,500
DIV 08:DOORS&WINDOWS
8-310 Interior Doors 4,800 Allowance For Six Replacement Assemblies
8-325 Entry Door 0 N/A
8-360 Overhead Doors 0 N/A
8-370 Door Hardware 350 Allowance For Six Assemblies
8-550 Exterior Door/Window Package 0 N/A
8-555 Exterior Door/Window Installation 0 N/A
Division 8 Total 5,150
RECEIVED
09/17/2023
ASPEN
BUILDING DEPARTMENT
3.16.2023 332 Main Street FP Budget Notes
CODE CATEGORY As per drawings dated 3.15.2023
DIV 09:FINISHES
9-250 Drywall/Plaster 31,600 Includes Drywall Repairs/Light Skip Trowel Throughout
9-300 Tile Materials 7,300 Includes Upper Level Bathroom Floor
9-310 Tile Prep/Installation 6,200 Includes Floor Prep/Tile Install Upper Level Bathroom Floor _
9-400 _Marble/Granite Slabs 7,300 Inludes Living Fireplace Slab/Install.Excluding Kitchen Slabs _
9-500 _Bath Vanities 0 Purchased By FP _
9-640 Wood Flooring/Installation _ 54,550 Includes Minimal Floor Prep,Tube Adhesive,Install.Does Not Include Full Floor Spread Adhesive
9-901 Interior/Exterior Paint/Stain _ 42,600 Inludes Walls/Ceilings/Casing/Base/Interior Doors
Division 9 Total 149,550
I
DIV 10:SPECIALTIES
10-300 Gas Fireplaces -Appliances/Flues 0 N/A
10-400 Blinds/Motorized Shades 0 By Owner
10-650 Shower Doors/Glass 0 Includes Upper Level Bath
10-825 Bath Accessories 750 Includes Install Only.Accessories Provided By FP
10-826 Mirrors 0 N/A
Division 10 Total 750
DIV 11:EQUIPMENT
11-200 AudioNisual/Security 0 By Owner
11-400 Telephone System 0 N/A
11-500 Appliance Package 0 Allowance As Per Spec Provided By FP.One Fridge,One Dishawasher.(FP Purchased)
11-600 Fire Pit 0 N/A
11-700 Hot Tub 0 N/A
Division 11 Total 0
DIV 12:FURNISHINGS
12-315 Closet Systems/Installation 6,500 Allowance As Needed.Does Not include Lower Level
12-320 Cabinetry 8,900 Allowance Only For Breakroom
12-325 Cabinetry Installation 3,900 Includes Kitchen&Bath Vanities
12-335 Cabinet Hardware 0 By Owner
Division 12 Total 19,300
DIV 15:MECHANICAL
15-100 Plumbing/Gas-Rough-in/Trim 13,500 Allowance Includes Rough-In Labor/Materials
15-300 Plumbing Fixtures and Hardware 3,100 Allowance As Per Spec Provided By FP
15-400 _Radiant Heat 4,200 Allowance For Base Board Heat Repairs(If Needed)
15-450 Snow Melt 0 N/A
15-500 Fire Suppression 0 N/A
15-800 HVAC 1,100 Allowance For Main Bath Exhaust Fan
15-835 Radon Mitigation 0 N/A
Division 15 Total 21,900
DIV 16:ELECTRICAL
16-100 Service/Wiring/Rough-In 17,800 Allowance Includes Labor/Material
16-300 Fixed Lighting Package 0 By Owner
16-400 Deco Lighting Package 0 By Owner
16-500 Permit 500 Allowance
16-700 Fire/Security/Alarm Systems 0 By Owner
16-750 A V,Tel,Communication Prewire 0 By Owner
Division 16 Total 18,300
RECEIVED
09/17/2023
ASPEN
BUILDING DEPARTMENT
3.16.2023 332 Main Street FP Budget Notes
CODE CATEGORY As per drawings dated 3.15.2023
DIV SUMMARY
1 GENERAL CONDITIONS 63,550
2 SITE CONSTRUCTION 5,300
3 CONCRETE 7,900
4 MASONRY 0
5 METALS 0
6 WOOD&PLASTICS 72,100
7 THERMAL&MOISTURE 1,500
8 DOORS&WINDOWS 5,150
9 FINISHES 149,550
10 SPECIALTIES 750
11 EQUIPMENT 0
12 FURNISHINGS 19,300
15 MECHANICAL 21,900
16 ELECTRICAL 18,300
CONSTRUCTION COSTS
PROJECT SUBTOTAL 365,300
BUILDER FEE 12% 43,836
SUBTOTAL CONSTRUCTION COSTS 409,136
OTHER COSTS
GENERAL LIABILITY INSURANCE 2,454
SUBTOTAL OTHER COSTS 2,454
TOTAL COST OF PROJECT 411,590