Construction Mitigation Plan for Minor Projects
Full Construction Management Plan (CMP) requirements can be found in the Construction Management Plan
Requirements Manual available here. The following document can be utilized for interior remodels and/or soil
disturbance less than 1,000 SF with no excavation stabilization or single-family roofing permits outside the
CRA. The “Construction Mitigation Plan for Medium Projects” document can be utilized for interior remodels
and/or soil disturbance greater than 1,000 SF and less than 2,000 SF or roofing permits within the CRA or
roofing permits on multifamily dwellings regardless of location. For large projects or at the discretion of the
CMP staff a full CMP written by the project contractor is required.
The purpose of this form is for small projects to acknowledge the applicant is aware of all CMP requirements
and will abide by all requirements.
1.0 General
The project contractor has completed the City of Aspen online CMP certification class. The online training
course is available at cmpaspen.com. A copy of the CMP certificate is provided with this submission.
2.0 Project Location
Project Address:
Project Disturbance Area:
Project Description:
Contact Information:
Name:
Phone:
Email:
3.0 Project Documentation
Prior to the start of permit activity, the contractor will properly notify all
neighbors and the general public.
Prior to the start of permit activity, a project sign will be posted at the
site.
4.0 Project Implementation
936 W Francis St
16.03
Replacing 3 windows like for like
Matthew Seiler
303-945-1519
mseiler@renewalcolorado.com
07/14/2023
2
Hours of Construction: Construction hours shall be limited to 7:30am – 5:30pm Monday through Friday
and 9:00am – 5:00pm on Saturday. No construction is permitted on Sundays or holidays as identified by
the CMP Manual.
Prior to the start of permit activity the project will provide fencing six feet (6') in height and constructed
out of chain-link fence with mesh windscreens (visual barriers) for all exterior work.
The contractor is aware of all trees within the work area and will provide tree protection in coordination
with, and as directed by the City Parks Department.
5.0 Site and Right of Way Management
By signing this document, the contractor ensures that there is adequate staging area onsite for all
construction trailers, job materials storage, portable restrooms, waste management and recycling
containers. If a portion of the ROW is needed the contractor will submit for a temporary encroachment
permit. Loose job material storage is not allowed in ROW under any circumstances.
The project will maintain continuous emergency vehicle access, on and around site, including but not
limited to police, fire, and ambulance services.
All required construction parking shall be provided onsite or the contractor will properly lease parking
spaces from the COA Parking Department.
Contractor will provide recycling onsite for both conventional and construction related materials.
6.0 Traffic Control
By signing this document the contractor ensures that the project does not impact roadways or pedestrian
walkways. No traffic control plan is needed.
The project requires no special circumstances for deliveries. Traffic control required for deliveries must be
fully coordinated with the City of Aspen Engineering Department. Roads will not be closed under any
circumstances, unless granted permission from the City of Aspen Engineering Department.
7.0 Pedestrian Protection
The project maintains all pedestrian walkways including all ADA requirements.
8.0 Sediment and Erosion Control
Best Management Practices will be installed which will prevent any erosion and sediment transport offsite.
If the project is located in the Smuggler Mountain Superfund Site a Superfund Site soil removal permit has
been submitted.
9.0 FUGITIVE DUST CONTROL
07/14/2023
3
A Fugitive Dust Control Plan is in place if applicable.
10.0 EMISSIONS
All vehicles and equipment used on site will be properly maintained such that the engines will function
within manufacture’s standards or parameters.
11.0 NOISE SUPPRESSION
The project will adhere to all noise requirements.
Noise limits are 70 decibels (dB) at the property line during the summer on season. Projects located on the
Mall will be limited to 70 decibels (dB) at the property line during the winter on season. All other times
projects will be limited to 80 decibels (80dB) at the property line.
If the project requires a sound fence to stay within the noise limits this form is not applicable and the
project shall submit a full CMP with a Noise Suppression Plan. The minimum requirements for a non-
modeled noise suppression plan are a 14-foot tall fence of noise dampening material surrounding the
construction site.
12.0 ENFORCEMENT
A City Construction Mitigation Officer will complete random site visits to determine if the project is
following approved Plan and City requirements.
SIGNATURE
I acknowledge that all requirements listed above as well as within the COA Construction Management Plan
Requirements Manual will be met on the project site. Contractor acknowledges that failure to abide by this
affidavit will result in red tags on the project and loss of participation in the program
Signature:
Printed Name:
Date: