HomeMy WebLinkAboutFile Documents.33 MINING STOCK PKWY.0093-2020-BRES (49)burlingame
phase III
community
outreach report
January 8th, 2020
08/26/2020
970.925.2855
info@bendonadams.com
www.bendonadams.com
300 South Spring Street, Aspen Colorado 81611 08/26/2020
This report has been commissioned by the City of Aspen as the conclusion to the community
outreach efforts conducted during the development of the Burlingame Ranch Phase III project,
which began in April 2019.
Community outreach initiatives were led by BendonAdams LLC, and supported by 359 Design,
Bluegreen, Sopris Engineering, and BG Buildingworks, the results of which are summarized
herein. BendonAdams would like to thank the following individuals and organizations for their
contributions and partnerships throughout the community outreach process:
Mayor
Torre
City of Aspen Council Members
Ann Mullins
Ward Hauenstein
Skippy Mesirow
Communications Director
Tracy Trulove
Affordable Housing Project Manager
Asset Department
Chris Everson
City Manager
Sarah Ott
APCHA Staff and Board
City of Aspen
Burlingame Ranch HOAs and Residents
Burlingame Ranch Property Management
Aspen Young Professional Association
NextGen Board
American Planning Association
Colorado Chapter
Aspen Saturday Market
Basalt Sunday Market
Aspen Community Members
Community + Partners
Aspen Chamber Resort Association
08/26/2020
10
15
16
Outreach Schedule
Key Findings
22 Next Steps
Outreach Approach and
Activities
TABLEOFCONTENTS
05
06
07
09
Executive Summary
Introduction
Inform, Verify, Refine
Property Background
08/26/2020
55
Executive
Summary
The Burlingame Ranch Phase III project was
previously approved in Ordinance 22 of 2011.
Under the existing approvals and recorded
Planned Unit Development (PUD) documents,
the City had the ability to go directly to the
building permit application process to build the
next phase of affordable housing at Burlingame
Ranch.
Instead, the City of Aspen committed to perform
voluntary community outreach to check in
with the Aspen community and ensure that
the approvals still reflect its needs. An RFP was
released in spring 2019, and the primary project
team, consisting of 359 Design (architecture and
design), BendonAdams (community outreach
and entitlements), BlueGreen (landscape
architecture), and Sopris Engineering (civil
engineering), was selected in May 2019.
Community outreach planning began in June,
with activities beginning in July, and concluding
at the end of September. During this time, the
the project team hosted twelve public events, in
addition to online engagement opportunities
and formal updates to City Council, to provide
the Aspen community with project information
for Burlingame Ranch Phase III.
A suite of tools and techniques were identified
to provide opportunities for varying levels of
engagement across different stakeholder
groups. These included press releases, market
booths, questionnaires, pop-ups, open houses,
field trips and tours, live polling sessions,
site planning exercises, design charrettes,
stakeholder meetings, HOA meetings, a
dedicated website and online surveys, board
presentations, and infographic reporting.
Many of these events were held in conjunction
with the Framing the Future initiative - which
served as the overarching theme for community
engagement across the Lumberyard, Water
Place II, and Burlingame Ranch Phase III
projects. This initiative, was created in response
to Aspen City Council setting a priority to build
more affordable housing in Aspen and conduct
extensive outreach with the Aspen community
to best understand housing needs.
Given the varying stages of each project, this
collaboration allowed for all three project teams
to successfully balance discussions of higher-
level affordable housing policies with fine-grain
examples of areas for improvement in the design,
construction, and delivery of affordable housing
developments. In total, there were over 500 event
participants who received information about
the Burlingame Ranch Phase III project, and
319 online participants who provided housing
and demographic information pertinent to the
development of Phase III.
Survey respondents gave the project team
clear direction to implement incremental
improvements and improve finishes, key site
and building functions, and construction
methodologies. These changes will be
memorialized through an amendment to the
original Planned Unit Development (PUD)
approvals with construction anticipated to
begin in 2021.
08/26/2020
66
The Burlingame Ranch affordable housing
project, located just outside downtown Aspen
on Highway 82, was initially approved in 2004
via Ordinance 120, Series 2004.
This ordinance granted conceptual approval
to a three-phase development plan which was
developed through intensive discussion and
work with a task force of community members
- formally known as the Burlingame Affordable
Housing COWOP Task Force Team. Both Phase
I and Phase II brought additional community
outreach endeavors, guiding the look and feel
of what we see today.
In 2011, Aspen City Council approved the third
and final phase of development at Burlingame
Ranch - consisting of 79 condominium units
in eight multi-family buildings. Approvals also
detailed foundations, excavations, stormwater
facilities, roadways, landscape and irrigation
systems, grading, utilities, parking, and
accessory structures on-site to incorporate
this phase into the existing Burlingame Ranch
community. The approval granted a 10-year
vesting on development entitlements.
In April 2019, the City of Aspen released an
RFP (request for proposals) for community
outreach, design, engineering, and modular
facilitation for the delivery of Burlingame Ranch
Phase III. The scope of work was to first focus on
community outreach, followed by design work,
and concluding with construction and delivery.
The primary project team, consisting of 359
Design (architecture and design), BendonAdams
(community outreach and entitlements),
BlueGreen (landscape architecture), and Sopris
Engineering (civil engineering), was selected
in May 2019 and began community outreach
efforts in July - which concluded at the end of
September with clear direction to implement
incremental improvements and improve
finishes, key site and building functions, and
construction methodologies.
The following pages summarize the community
outreach process: project information, project
planning, approach, stakeholders, outreach
activities, key findings, direction from Aspen
City Council, and a summary of the design
changes resulting from the feedback that the
project team received.
Introduction
08/26/2020
7
LOCATION
ASPEN
AIRPORT
DOWNTOWN
ASPEN
BG
III
PROJECT SCHEDULE
2018 2019 2020 2021 2022
COMMUNITY OUTREACH
CONCEPTUAL
DESIGN
COUNCIL
DIRECTION
CONSTRUCTION DOCS
+ BDG
PERMIT
OCCUPANCYCONSTRUCTION
Project
Background
Burlingame Ranch is located outside Aspen on
Highway 82, near the Aspen Airport Business
Center. The property consists of approximately
35 acres of developable area surrounded by open
space, the Roaring Fork River, and the Double
Bar X Ranch. As stated in the introduction,
Burlingame Ranch was approved as a three-
part phased affordable housing development
where Phases I and II are already completed and
occupied (see callout in map).
Burlingame Ranch Phase III, is one of three
concurrent projects being undertaken by the
City of Aspen in its commitment to supporting
affordable workforce housing and opportunities
for people to live in the community where they
work. These affordable housing projects: the
Lumberyard project, Water Place Phase II, and
Burlingame Phase III, comprise the Framing the
Future initiative - a community-wide discussion
on affordable housing development in Aspen
under the direction of Aspen City Council. The
initiative will create an additional 200+ housing
units in Aspen.
Burlingame Ranch Phase III is uniquely placed
within the initiative due to it being the final
phase of an existing vibrant affordable housing
development. Its development and occupancy is
estimated to be on a much shorter timeline than
the development of the Lumberyard and Water
Place Phase II which are in initial discussions
with the community regarding programming.
City of Aspen GIS Mapping
08/26/2020
8
Project
Background
Burlingame Ranch Phase III, with existing
approvals in place, is able to move forward into
building permit and construction. However,
Aspen City Council requested community
outreach prior to moving forward with design to
ensure that the final housing product is reflective
of today’s community needs.
Phases I and II consist of single family, duplex,
and multi-family buildings totaling 179 units.
The remaining 79 condominium units will be
provided through the development of Phase III
consisting of buildings 8 through 15, 28 carports
with integrated storage, and 10 surface parking
spaces.
The dimensional requirements and buildout
of Phase III are predetermined via Ordinance
22, Series 2011, where material changes to
the “number of residences, the deletion of
common amenities, change by more than 1%
to approved parking, substantial changes to
the transportation/mobility plan, or changes
to the uses, intensity, character, or nature of
the development shall require approval by City
Council.”
Amendments to “unit layouts, changes to the
mix of units, affordable housing categories,
insubstantial changes to building locations
and configurations, location of carports, surface
parking, or common amenities, architectural
detailing or roof profiles, or changes to the
transportation/mobility plan may be approved
by the Community Development Director.”
As with other phased projects, Burlingame Ranch
has presented an opportunity for the project
team to learn from Phases I and II - to understand
what works and where improvements can be
made to increase the quality and functionality of
Phase III. With this in mind, project work kicked
off with a two-day intensive ‘Lessons Learned’
charrette focusing on documenting areas for
improvement based upon maintenance records,
issues identified by current residents, and quality
control information from on-site construction.
The charrette was also an opportunity to conduct
a deep-dive into the approvals and ascertain a
baseline for anticipated improvements, what
questions needed to be posed to the public and
current Burlingame residents, and potential
implications for project timeline and delivery if
‘material changes’ were necessitated through
the outreach process.
The images to the right illustrate what was
approved in 2011, specifically the look and feel
of Phase III - site and building character and
location of buildings, accessory structures, site
infrastructure, roadways, and open spaces. These
renderings were utilized throughout the initial
stages of the community outreach as a guide
for the public to provide feedback for potential
improvements.
Oz Architecture, 2011 PUD Approvals
Oz Architecture, 2011 PUD Approvals
Oz Architecture, 2011 PUD Approvals
08/26/2020
9
Inform. Verify. Refine.
The ‘Lessons Learned’ charrette provided
the project team with three project pillars:
inform, verify, refine. These ideas were
utilized to support the outreach approach,
project schedule, and tools and techniques
employed to reach stakeholders and
community members.
08/26/2020
10
OUTREACH APPROACH
Burlingame Ranch Phase III - Community Outreach Report
Outreach planning was conducted with the Burlingame Ranch project team to define
project scope, decision points, decision makers, stakeholders, and the most relevant tools
and techniques to reach community members and encourage participation. The team also
worked through a visioning exercise to create project outreach goals, the result of which
were team driven narrative statements - identifying their approach to process, approach to
community engagement, and putting feedback in action.
In similar fashion to previous phases of Burlingame Ranch, the City of Aspen identified
‘collaboration’ as a key principle in the outreach program; again, integrating input from
community members and current residents to help guide the look, feel, and program of
Phase III to ensure that it reflects the values and needs of our community and allows for
necessary improvements to building design and site functionality.
The outreach methodology is based upon international best practice from the International
Association for Public Participation, IAP2, which utilizes tried and true project management
techniques to ensure a complete and equitable process with attention to detail. Outreach and
communication plans were derived from these exercises, and were utilized as a benchmark
throughout the community outreach process to ensure that the project team and the tools
and techniques employed were successful.
A variety of tools and techniques were identified to provide a spectrum of opportunities for
varying levels of engagement across different stakeholder groups. These included but were
not limited to: press releases, market booths, questionnaires, pop-ups, open houses, field
trips and tours, live polling sessions, site planning exercises, design charrettes, stakeholder
meetings, HOA meetings, dedicated website and online surveys, board presentations, and
infographic reporting - all supporting the team’s work to inform the community about the
project, verify issues and opportunities, and refine the 2011 approvals where necessary.
08/26/2020
11
OUTREACH ACTIVITIES
MARKET DAYS X 31
Purpose: The project team hosted booths at the
Aspen Saturday Market, and Basalt Sunday Market,
in July, August, and September, in order to provide
history and background on the Burlingame Ranch
approvals and project schedule. Participants were
encouraged to sign up for Aspen Community Voice
to stay updated on project scheduling and events.
Participants: 65 Participants
ASPEN COMMUNITY VOICE / SURVEY
MONKEY
2
Purpose: Multiple online surveys were hosted
through the City’s online engagement platform,
Aspen Community Voice (ACV), and Survey
Monkey in order to provide multiple channels for
participants to engage online. ACV also hosted the
project schedule, background documents, contact
information, and timeline.
Participants: 319 Participants across 3 surveys
in
f
o
r
m
Between July and the end of September the project team hosted twelve public events, in
addition to online engagement opportunities and formal updates to City Council, to provide
the Aspen community with project information for Burlingame Ranch Phase III. Many of these
events were held in conjunction with the Framing the Future initiative and Lumberyard and
Water Place II projects. Given the varying stages of each project, this collaboration allowed for
all three project teams to successfully balance discussions of higher-level affordable housing
policies with fine-grain examples of areas for improvement in the design, construction, and
delivery of affordable housing developments.
In total, there were over 500 event participants who received information about the
Burlingame Ranch Phase III project, and 319 online participants who provided housing and
demographic information pertinent to the development of Phase III.
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
1212
OUTREACH ACTIVITIES
ON-SITE ASSESSMENTS4
Purpose: The project team worked with property
management and maintenance staff to verify existing
conditions on-site and attain a comprehensive list
of items that had potential to be improved in the
design and construction of Phase III.
Participants: ~15 Participants
COMMUNITY PICNIC @ RED BRICK5
Purpose: The project team hosted a booth at the
Community Picnic to officially launch outreach
initiatives for the Burlingame Phase III and Framing
the Future projects. Online surveys were available
for participants in addition to the ability to register
on Aspen Community Voice for project updates and
events.
Participants: ~100 Participants
ve
r
i
f
y
+
r
e
f
i
n
e
LISTENING POSTS3
Purpose: In order to reach as many community
members as possible, the team conducted three
pop-ups at strategic locations around Aspen in order
to share project information and the outreach events
schedule. Locations included the Aspen Pedestrian
Mall, Burlingame Phase II, and Castle Ridge bus stop.
Participants: 72 Participants
in
f
o
r
m
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
13
OUTREACH ACTIVITIES
BURLINGAME NEIGHBORHOOD
MEETING + SURVEY
7
Purpose: The project team provided a survey for
Burlingame HOA members and existing residents
which was utilized as a ‘report card’ on existing
conditions such as landscape, noise, unit layouts,
storage and parking. Results were used to provide
‘improvement options’ that were then presented
back to the Burlingame community.
Participants: ~40 Meeting Participants / 96 Surveys
ve
r
i
f
y
+
r
e
f
i
n
e
ACRA PRESENTATION + SURVEY8
Purpose: Engaging with local employers was
considered to be a priority for the project team to
better understand housing demand and challenges
facing employers / employees in Aspen. The project
team presented to the Aspen Chamber Resort
Association Board and provided a survey specifically
for ACRA members.
Participants: ~25 Meeting Participants / 92 Surveys
CITY STAFF BBQ6
Purpose: The project team hosted an event
specifically for City staff in order to provide them with
project information and Framing the Future project
timelines. Surveys were available for participants,
in addition to poster displays, and registration for
Aspen Community Voice.
Participants: 162 Participants
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
1414
OUTREACH ACTIVITIES
LUNCH AND LEARN10
Purpose: The project team hosted an open house
style luncheon in order to present the iterations of
‘improvement options’ that resulted from community,
ACRA, and Burlingame resident feedback. Posters
were displayed and discussions were focused on
ensuring that the options were supported and that
additional improvement opportunities had not been
missed.
Participants: ~75 Meeting Participants
COMMUNITY OPEN HOUSE11
Purpose: In collaboration with the American
Planning Association, Aspen Young Professionals,
and the NextGen Board, the project team hosted a
joint event to present information on all Framing the
Future projects, providing detailed information on
the ‘improvement options’ for event participants to
discuss and indicate their level of support.
Participants: ~350-400 Participants
ci
r
c
l
e
b
a
c
k
CITY COUNCIL PRESENTATIONS9
Purpose: The project team checked in with City
Council three times throughout the outreach
process in order to provide updates on community
feedback, potential upgrades, and changes within
the insubstantial amendment language from the
PUD.
Participants: NA
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
15
OUTREACH SCHEDULE
1
2
4 On-site
Assessments
August
7-17th
Burlingame property management, property
maintenance staff
5 Community Picnic
@ Red Brick
August
14th
Greater public, visitors, local residents, APCHA tenants,
current homeowners, future homeowners, elderly,
families, community groups
6 City BBQ August
6-8th
City Departments: Water, Engineering, Community
Development, Parks Department, CMO
Communications, Fire Department
8 ACRA
Presentation
August
27th ACRA membership, business owners, employers
7 BG Neighborhood
Meeting
August
27th
Burlingame HOA, all Burlingame residents, property
management, property maintenance staff, interested
future homeowners
10 Lunch and
Learn
September
12th
Greater public, young families, commuters, Burlingame
residents, Burlingame HOA, future home owners, APCHA
board members, APCHA staff, city staff
9
City Council
Presentations
Aug 20th +
Sept 24th City Council, Planning Staff, greater public
11 Community Open
House
September
19th
Greater public, young families, commuters, Burlingame
residents, Burlingame HOA, future home owners, APCHA
board members, APCHA staff, city staff
sequence targeted stakeholdersdateactivity
in
f
o
r
m
ve
r
i
f
y
+
r
e
f
i
n
e
ci
r
c
l
e
b
a
c
k
Market Days x 3
July 27th
Sept 8th
Sept 21st
Greater public, visitors, local residents, APCHA tenants,
current homeowners, future homeowners, elderly,
families, community groups
Aspen Community
Voice Launch
August
8th
Greater public, young families, commuters, Burlingame
residents, Burlingame HOA, Maroon Creek Club, future
homeowners, APCHA board members, APCHA staff, city
staff and department heads
3 Listening
Posts x 3
August
6-8th
Commuters, families, Burlingame residents, Burlingame
HOA, city staff and department heads, future tenants /
homeowners
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
KEY
FINDINGS
16
In total, the project team aggregated information from twelve public events, over 300 surveys, and
City Council direction to specifically inform the ‘improvement options’ for Burlingame Phase III.
The three surveys that contributed to the ‘improvement options’ at Burlingame were the
Burlingame Affordable Housing Information Gathering Survey, Aspen Affordable Housing
Information Gathering Survey, and the ACRA Affordable Housing Survey; all of which were available
on Survey Monkey or Aspen Community Voice. Data was compiled and reviewed by the project
team throughout the community outreach which allowed for options to be fine-tuned through
an iterative process.
The range of feedback allowed for the project team to understand the demand for fine-grain
changes to the project’s previous approvals to landscape, green spaces, layouts, finishes, parks,
transit, storage and parking and contextualize them with demographic and household information,
local housing demand, and overarching City of Aspen sustainability goals.
Average Respondent
Profile
Of respondents
have families of
four or more
42%
Of respondents
were between ages
30-49
65%
Of respondents
need 3 or more
bedrooms
53%
The majority of participants across surveys lived in Aspen, were
females between the ages of 30 and 49, and had households with
three (general housing survey) to four plus (Burlingame survey)
members.
A large number of survey respondents from the general community
and ACRA live in free market housing; however, many of these
respondents would be interested in renting or purchasing a unit
through APCHA if it were to become available.
A predominant portion of all survey respondents supported the
Burlingame Ranch Phase III project moving forward as approved
with incremental improvements identified through the community
outreach process.
Data Analysis
Of respondents
were female
60%
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
17
KEY
FINDINGS
Aspen General Housing
Information Gathering Survey
The general housing survey was utilized across
several events for community members who do
not reside in Burlingame, or who weren’t familiar
enough with the property to provide detailed
information on potential improvements for
Phase III.
Of those who participated, there was a relatively
even split in household size, ranging from single
to three or more (37%). 52% of respondents were
female, with 63% of respondents aged 30-49.
Many of the survey participants lived in Aspen,
but 52% were living down valley in Woody Creek,
Snowmass and Old Snowmass, Basalt, El Jebel,
Carbondale, and Glenwood.
Almost 95% of participants were full-time
working residents in Pitkin County, with only
33% living in affordable housing, either provided
through the City of Aspen of through APCHA.
Of those living in affordable housing, most were in
a Category 3 unit (26%). 78% of participants were
interested in purchasing (65%) or renting (13%)
an affordable housing unit if it were to become
available with a 25%-30%-33% split between a
need for one, two, and threee-bedoom units.
Most participants were interested in all three
Framing the Future projects - which reflects the
high level of interest of those currently living
in free-market housing wanting to enter the
affordable housing system.
The majority of participants were supportive of
the City of Aspen developing more affordable
housing and for Burlingame Phase III to
move forward as approved with incremental
improvements.
Overall, the general housing survey provided the
project team with an understanding of the type
of housing demand that is being experienced
in the local Aspen market, and reflects trends
that were discussed in the Greater Roaring Fork
Regional Housing Study, 2019.
Participants: 133
Age: Majority of respondents are aged 30-49
Family Size: 37% of respondents have 3 or more family members
Zip Code: 48% live in Aspen
Employment: 94% of respondents are full-time employees of Pitkin County
Housing: 50% of respondents live in free-market housing
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
18
KEY
FINDINGS
ACRA Affordable
Housing Survey
The survey provided to ACRA members
focused on understanding the biggest housing
challenges facing employers in Aspen.
Generally, the majority of businesses who
participated have been established for at least
ten years with many employing ten people or
less.
There was an array of industries represented
including, business services, arts and culture,
lodging, non-profits, real estate, restaurants,
retail, and transportation.
The majority of respondents cited cost and
availability as the two biggest challenges in
housing their employees, with a significant
number of respondents stating that the
availability of housing has a significant impact
on their business or place of work.
When asked whether they had specific
comments or concerns about the planning and
design of Burlingame Phase III, the project team
received comments that focused on creating
appropriate spaces for families, affordability, and
project timeline.
Many respondents provided us with their ‘big
idea’ for housing in Aspen, ranging from location
of development, to adjustments to the affordable
housing program, and quality of design.
Respondents supported the City of Aspen
building more affordable housing, (7.7/10),
with an almost equal level of support for the
Burlingame Phase III project moving forward as
approved assuming there will be refinements.
Interestingly, employers showed slightly less
support for the City of Aspen constructing
affordable housing for its own employees at the
Water Place Phase II project, (5.2/10).
Participants: 92
Age: 50% of respondents are aged 30-49, 33% of respondents were aged 50-64
Business Tenure: 61% of respondents have worked/owned a business in Aspen for 10+ years
Employees: 44% of respondents indicated there were 10 or less employees at their business or place of
work
Housing assistance: Only 18% of respondents employers offer housing assistance to employees
Commuting: 46% of employees commute into Aspen for work
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
19
While multiple surveys were used to aggregate
demographic and household housing needs, the
survey created for Burlingame residents most
directly influenced the creation of ‘improvement
options’ for Phase III. Almost 100 residents
participated in the survey, answering report-card
style questions and providing open comments.
Overall, Burlingame Phase I and II residents were
happy with the existing conditions on site, but
there were some key site functions that were
highlighted as needing to be improved; with
further detail provided through open comments.
Residents were asked about accessibility,
transportation and parking, drainage and
irrigation, existing green spaces, parks, and play
areas, storage, outdoor living areas, and lighting.
Residents highlighted snow removal, parking,
drainage, community gardens, ‘gear’ storage,
private outdoor spaces, and private patio spaces
as items to improve.
They were also asked to prioritize improvement
areas and construction concerns, and to provide
the project team with detail on how to improve:
living spaces, mechanical systems, floorplans,
finishes, bathrooms, decks, and privacy.
The project team was able to set up the survey so
that respondents answers could be filtered based
upon what unit type they lived in - providing a
detailed analysis of what has been working well
and what needs refinement, allowing the team
to match issues and opportunities to specific
unit types and layouts.
This analysis was completed in August, and
in conjunction with the report card and open
comments provided the basis for the proposed
‘improvement options’ that are outlined on the
next page.
Burlingame Affordable Housing
Information Gathering Survey
Participants: 96
Family size: 49% of respondents had families of 4+
Age: 78% of respondents are aged 30-49
Category: 22% Category 2 owners / 36%Category 3 owners / 21% Category 4 owners
Unit size: 63% of respondents indicated they needed three bedrooms or more
Unit type: Respondents lived in 1-3 bedroom flats, 2-3 bedroom townhomes, single family homes
KEY
FINDINGS
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
2
3
20
Burlingame Affordable Housing
Information Gathering Survey
1
4 More bike storage Seek opportunities to provide additional bike storage including potential for more covered bike storage.
5 Unit layout improvements
In order to facilitate meeting the design parameters for modular construction, there are no major modifications to the
units needed. The design team is instead making a few slight modifications where suggestions have been made for small
matters related to day-to-day livability.
6 Simplify mechanical systems
The prior phase utilized natural gas fueled high-efficiency boilers for both hot water and space heating. This dual-
purposing of the boilers ended up causing complexities which were initially unforeseen. The team is examining
opportunities for simplified, high efficiency, all-electric mechanical systems.
8
Provide two sinks in the bathroom vanity In the prior phase, one sink was provided, but the vanity had space to accommodate a second sink.
7
Utilize modular construction
The prior phases are site-built construction. Cost savings may be achieved with factory built modular construction, but
even if there is no cost savings, sound and vibration improvements, construction quality improvements and decreased on-
site construction impacts make factory-built modular construction highly beneficial.
10
Use residential fire alarm systems, not commercial which are
more costly to maintain
Simplified fire alarm systems can be explored to the extent allowed by code.
9
Provide better quality finishes In the prior phase, the “upgrade package” was included in about half of the units. This should be the baseline finish
package in the next phase.11
st
o
r
a
g
e
fu
n
c
t
i
o
n
a
l
i
t
y
fi
n
i
s
h
e
s
Increase storage by moving “water entry” mechanical rooms out
of space which could be used as in-unit storage.
Some of the buildings in the prior phase have “water entry closets” with the main water meter for each building located
within the building envelope and using up valuable floor area which was otherwise part of a larger storage closet in some of
the units. It will be highly beneficial to move these “water entry closets” outside the building envelope so they are no longer
located above livable area thus reducing the risk of damage from flooding and adding back the otherwise lost storage in
the affected units.
Add storage closet near entry of lower level units In the prior phase, the lower level units do not have a coat/storage closet near the entry. The door can be moved slightly to
improve circulation and provide a storage opportunity.
Add linen closet / storage There is an opportunity to add a linen closet by rearranging the storage space in the hallway outside the bathroom door.
Increase unit-to-unit sound insulation
In the prior phase, high STC and IIC wall and ceiling assemblies were designed, but were still limited by site-built construction.
This will be an inherent improvement with factory-built modular construction due to separate floor and ceiling framing and
separate demising wall framing that is inherent in factory-built modular construction.
Provide better quality appliances In the prior phase, the “upgrade package” was included in about half of the units. This should be the baseline finish
package in the next phase.12
Burlingame Ranch Phase III - Community Outreach Report
theme 359 Design responserequesttopic area
08/26/2020
21
Burlingame Affordable Housing
Information Gathering Survey
14
15
13
16 Provide vertical railing balusters, not horizontal which allow
children to climb
Cobble stone areas around patios can be replaced with pavers under covered decks to increase usable patio space
adjacent to unit.
17 Provide expanded patio space In the prior phase, not much screening was provided at the unit entries and at adjacent patio areas. Wing walls and screening
can be strategically added to provide an increased sense of privacy between these areas.
20
Traffic-calming such as raised, shortened crosswalks In the prior phase, the crosswalks are painted on the pavement. The possibility of raised crosswalks or speed humps can be
explored with City Engineering.
19
Better anticipate site and landscape maintenance requirements,
including irrigation and planting
Simplify irrigation system details and refine plant palette to reduce amount of non-native species and species that require
regular maintenance or are considered nuisances.
22
Use native landscape for steeper areas or areas that are otherwise
more difficult to mow
Landscape variation will be considered to provide appropriate plantings for ease of maintenance and improved hierarchy
of
21
Carport parking columns interfere with opening car doors Make columns narrower.23
ex
t
e
r
i
o
r
s
ou
t
d
o
o
r
s
Provide more in-ceiling overhead lighting In the prior phase, some ceiling light fixtures were included, but in some of the rooms, a switched plug was provided for use
of lamps in lieu of in-ceiling lighting. More in-ceiling lighting can be provided.
Provide ceiling fan with light In the prior phase, a switched junction box was provided for owner-installed ceiling fans. The fixtures can be added.
Timber look and feel is preferred to tube steel
The prior phase used wood timbers and glulaminated beams at the exterior of the buildings. The team proposed to
replace with steel, but there is a desire to maintain the look and feel of wood. The team is looking at providing some more
articulated ideas for providing the functionality of steel with a texture that works with the existing style.
Lawns should be flat for active use Further opportunities to create flat lawn areas can be sought and grade transitions can be softened.
fi
n
i
s
h
e
s
18 Improved integration of grading, stormwater devices and
planting design
Reduce soggy lawn areas, exposed inlets and other box covers, abrupt grade transitions that are difficult to maintain,
stormwater to supplement and reduce need for irrigation, and other improvements.
theme 359 Design responserequesttopic area
Burlingame Ranch Phase III - Community Outreach Report
08/26/2020
2222
NEXT
STEPS
The project team provided the Aspen City Council
with several updates throughout the summer
and fall, starting August 20th - outlining the
project schedule and outreach opportunities for
all three Framing the Future projects.
A second update was provided September 24th -
at which time the community outreach had almost
concluded. This meeting focused on outlining key
findings to date from the three surveys discussed
within this report, and to confirm with City
Council that the scope of changes discussed still
were within an administrative amendment. City
Council directed the project team to continue
moving forward with the ‘improvement options’.
In late September, early October, the design team
commenced Schematic Design incorporating
the community feedback into the updated
designs for Buildings 8-15.
On November 18th, the project team returned
to Council to get guidance on some of the more
material changes to the design which have
budgetary impacts. Specifically, the project team
asked City Council to choose between options for
upgraded exterior steel beams, exterior materials,
energy systems, levels of sound attenuation, and
energy efficiency options.
Council members requested the project team
move forward with incorporating these elements
into the design and to come back with a detailed
budget update so that they could give final
direction on what level of improvements to
pursue.
The project team is currently working through
design development and anticipates 100%
completion by early March 2020. At that time, the
project team will submit a land use application
for an Insubstantial Planned Development
Amendment, which will be reviewed by the City
of Aspen Planning Department and Community
Development Director.
The project team will check in with City Council in
March 2020, providing a pricing model and more
detailed information on modular construction
estimates and delivery. With approval from City
Council, the project team will move forward with
releasing an RFP for modular construction and
contractors.
It is expected, with the current schedule, that
a building permit will be submitted in the
beginning of summer 2020.
08/26/2020
23
970.925.2855
info@bendonadams.com
www.bendonadams.com
300 South Spring Street, Aspen Colorado 81611
08/26/2020