HomeMy WebLinkAboutFile Documents.215 N Garmisch St.0019-2023-BREP (8) 215 N GARMISCH
YELLOW BRICK STAIR
REPLACEMENT PROJECT
CONSTRUCTION MANAGEMENT PLAN
February 3rd, 2023
Project is a removal and replacement (with like) of the East and West Stairs and adding a
railing to the South ramp of the Yellow Brick School Work will occur outdoors. The total
area of ground disturbance is approximately 550sqft.
TABLE of CONTENTS
Overview and Table of Contents 1
Vicinity 2
Project Introduction, Dates of Construction, Hours of Construction 3
Contact Designation 4
Sequence of Construction, Adjoining Properties, Project Fencing,
Public Health&Welfare,Natural Environment,Parking Management,
Emergency Vehicles &Ordinance 35,Staging Areas,Traffic Control 5
Pedestrian Protection, Sediment & Erosion Control, Fugitive Dust Control,
Emissions,Noise Suppression, Site Plan 6
Heavy Haul Route Map 7
Site Plan 8
RECEIVED
04/18/2023
ASPEN
BUILDING DEPARTMENT
VICINITY MAP
Address
215 N Garmisch
Aspen CO, 81611
AA, . . • �� ts ,t . � c . I ; ,— I
„..,,,„ ,., —... , _=�-
' + �
r 'A.. ti x Vie+x !� _ >..�6r s �)
•:3� JJJ 1 `�� .• 4•:'� .. .l 4 F� •' '
---4 n A {, a t ° ` g�N'Garmisc ��. ' -1 I \, , �;
: :
,ik.o I 5, \4%,_.,0. , ..,... .1i, 'W. . '.,.' ',-,: '• 7 1'.i
t 'yy` 44 1 t •,Zvi }0 _• ` ' { r 1 f
zi t ` ' ..91 • mil 11
r.
r'• ra
f . 'A A r! y FSiCy-'fC ox ni bus 7 E� t `� .
ti
RECEIVED
04/18/2023
ASPEN
BUILDING DEPARTMENT
PROJECT INTRODUCTION
Project disturbance will be limited to approximately 450sqft of concrete removal and
replacement to the West Stair, 350sgft of concrete removal and replacement to the East
Stair, and 100sgft of coring and grouting to install the railing on the South ramp. About
900sqft of ground disturbance will occur.
• The project is located at the Yellow Brick School, 215 N Garmisch. The building is
a preschool. The building and unit are currently connected to public utilities
including water and sewer and the project is not expected to have any effect on
these utilities.
Permits Applied For:
Building Permit: #TBD
• Project Notification will be performed by the general contractor as required.
• A project sign will be posted on the window of the unit so that it is visible from the
parking/drivewayin front of the unit.
DATES OF CONSTRUCTION
• The window for construction will be 4/01/23- 10/1/23. Construction is expected to take
two months total within the construction window.
• Any work being performed within City ROW shall be completed as per the City of
Aspen Right of Way permit requirements.
HOURS OF CONTRUCTION
• Construction hours will be limited to 7:30am - 5:30pm Monday through Friday and
9am- 5pm on Saturday. No construction work will be performed on Sundays, 4th of
July day and/or weekend if it falls on a Friday or Monday, Memorial Day and Labor
Day weekends, Thanksgiving Day, Christmas Day,New Years Day.
• All activity that generates noise in excess of 80 decibels requires a noise suppression
plan and is restricted to operating between the hours of 9am and 5pm Monday
through Friday.
RECEIVED
04/18/2023
ASPEN
BUILDING DEPARTMENT
CONTACT DESIGNATION
Owner- City of Aspen-evan.pletcher@cityofaspen.com
General Contractor Office—City of Aspen
General Contractor Site Supervisor—Evan Pletcher 970-987-0208
Safety Officer—Evan Pletcher
Traffic Control Officer—Trevor Brown
Erosion Control Representative- Evan Pletcher
City of Aspen Community Development Department- (970)920-5090
City of Aspen Fire Department - (970)925-5532
City of Aspen Police Depai tiuent - (970) 920-5400
Emergency Fire & Police- 911
Aspen Valley Hospital- (970) 925-1120
Roaring Fork Transit Authority (RFTA)-(970) 925-8484
Aspen School District- (970) 925-3760
Holy Cross Energy Electrical- (970) 945-5491
Xcel Energy Natural Gas - (800) 895-2999
Century Link Telephone- (800) 603-6000
Comcast Xfinity Cable - (800) 266.2278
RECEIVED
04/18/2023
ASPEN
BUILDING DEPARTMENT
SEQUENCE (PHASING) OFCONSTRUCTION
• Construction will be performed on one stair system at a time to ensure that one main
entrance will be maintained at all times. Additional alternate egress routes from the
building are available and will be utilized while the stair system under construction is
out of order.
ADJOINING PROPERTIES
• The Yellow Brick school is an entire city block in size with no directly adjoining
properties. Neighboring properties are largely residential. Sound, dust, traffic, and
safety measures will be implemented to minimize the impact to adjoining properties.
Work will also only occur during designated City working hours.
PROJECT FENCING
• Construction areas shall have a non-removable construction fence or other
approved device securely placed around the areas to be protected. The fence
shall be six feet (6') in height and constructed out of chain-link fence with
mesh windscreens (visual barriers). Construction is expected to stay within the allowable
noise limits and the need for noise suppression fencing additions is not anticipated.
If after implementation,the project fails to stay within City noise regulations, additional
measures will be implemented.
PUBLIC HEALTH AND WELFARE
• The general contractor shall uphold utmost respect to public health and welfare.
NATURAL ENVIRONMENT
• Special care will be given to ensure that trees and vegetation are protected
from abrasions and trampling. No vehicles will be driving on the ground
coverings.
PARKING MANAGEMENT
• All parking to be contained to the existing available on-site parking.
EMERGENCY VEHICLE ACCESS AND ORDINANCE 35
• See attached Site Plan for emergency vehicle access,parking and staging areas.
STAGING AREAS
• Materials storage will be contained within the existing available on-site parking.
• A construction dumpster will be implemented as necessary and be contained within the
existing available on-site parking. Recyclable materials will be collected and recycled
properly.
• A construction office trailer will not be necessary.
TRAFFIC CONTROL
• All traffic control operations shall be managed by a designated, certified
traffic control supervisor.
• Construction vehicles will be a medium sized excavator for concrete removal, a E IVE D
sized dump truck for concrete hauling, and a cement truck and cement pump c r'new
concrete pouring. 0 4/18/2 0 2 3
ASPEN
BUILDING DEPARTMENT
• Heavy hauls will be limited to equipment staging and concrete removal and
replacement. The haul route will be down HWY82
• The heaviest construction related vehicle anticipated at this time will be a dump
truck hauling a trailed with medium sized excavator for site
mobilization/demobilization.
• Deliveries to the job site are expected to consist of trailers containing items such as
concrete rebar and forms. One delivery truck at a time will be scheduled. The most
impactful delivery will be of concrete and a concrete dump truck. This will require
less than two days over the entire project duration.
PEDESTRIAN PROTECTION
• Construction supervisors will act as spotters for all deliveries to ensure pedestrians are
safe.
SEDIMENT AND EROSION CONTROL
• As the disturbance area is less than 1000 sf, an SMP is not required. However, sediment
and erosion control measures will be deployed as necessary to contain disturbed areas.
FUGITIVE DUST CONTROL
• As the disturbance area is less than 1000 sf, a fugitive dust control plan is not
required. However, work area dust control measures and street cleaning will occur to
mitigate fugitive dust emissions to the surrounding areas.
EMISSIONS
• All vehicles and equipment used on site will be properly maintained such that the
engines will function within manufacture's standards or parameters.
• Emissions from diesel engines operated within the City of Aspen shall be of a shade
or density no darker than 40% opacity, except for starting motion no longer than 10
seconds or for stationary operation not exceeding 10 seconds.
NOISE SUPRESSION
• Only standard construction equipment(nail guns, compressors, saws, drills) with a
sound rating of below 80db is anticipated to be used outdoors. Outdoor noises
construction will be completed between the hours of 9am and 5pm Monday
through Friday.
SITE PLAN
• A portable restroom will be utilized for construction workers. Materials will be
neatly stored in the available, reserved, on-site parking.
RECEIVED
04/18/2023
ASPEN
BUILDING DEPARTMENT
HAUL ROUTE
M e
ii.
• e , ••ilo ''Parks Be earl en: - <- o f 5t ' - _• v - .. nl„ N
-t ' r i ^ .; y- .t I +� .71ami`g91 p r�W
�• t t �..i t .-.., v.''t ' •,-0 ?,1,, [ ,' F'rl t "' . 7 n't11
y - 1 ti ) '4 t '•. '. y ,•;:y .. . �- z215: Garrrii•
- • '•, , ., ', '.%!,''''I s .:'1- x'; • •• •!:,
,-,'':';'-,' , ..-'x..*1<l./j,T,i iI jiil-'l1f%:.
1.-
,Aspen Hickory] ®use p.,
`deer+ `v,a,` tt1 .;`, 1_if "a if .#,tr„ iA . t r • ,Paepcke
,' /xrz;Gi 4ffno M ' .1 �� iYw S Mo tl Lodge`�
RECEIVED
04/18/2023
ASPEN
BUILDING DEPARTMENT
RECEIVED
04/18/2023
ASPEN
BUILDING DEPARTMENT
RECEIVED
04/18/2023
ASPEN
BUILDING DEPARTMENT
SITE PLAN
• '�r`
AI e-#: ' 4Str � r�1Riaals Storage +_ _ _ „; kot
''
� F �'; T`__ : -K ARE ..
` _
e -4411k A
----.• -• 2415 N Gad Fsc St - --- r - 4., .:, _
4 , .,;
‘. ilk 'I , .
7 IkIS . .'. -- : -t'' Z i.4 ' - ..._- , , t 11-.
, .,1 . 4 ' 4:- Ve 1101111P *
�. 3 . � ,
oil., t
,141011r ' AL, . ., . . „.. _. .\ -.- 1 . 4,, .- .
4 . ... .• ..-.. .,, , ,, ...4,4,. .., k\ , .1, . .,* ,
3 .,.,,,, • 4 .. P -
0 N •'''' .111: :I'A . i M. . 't . .r 24 • I ' ^ %.
1 :au _ .' - „�
" ,. S%4:i1 1,-
,. • t 164P .1-40001100 sw,
`�r f ` : ` =tom _ .- :_1:- , ...`.
f 5.
. ramkil �ii !0ikJid ` •- - 7t .
RECEIVED
0 4/1 8/2 0 2 3
ASPEN
BUILDING DEPARTMENT