RE: HPC Referral Project: 110 Neale Ave.
Wednesday, June 3, 2020 11:07:32 AM
Sarah,
One item that needs to be addressed with the HPC review.
1.Adjacent to the house on Queen St there is 2 hour Park use parking. This head in parking
needs to remain. Head in parking is supported instead of parallel parking because cars need
the space to turn around. The applicant needs to propose a street section that allows head in
parking, curb and gutter, a 5’ landscape buffer, and a 5’ sidewalk. If there is not available
width to meet the standards the applicant will need to work with the Engineering Department
on the street section.
Below is a list of items that will need to be worked through prior to building permit submittal.
1.Engineering Standards require a detached sidewalk. Due to the existing vegetation the
sidewalk on Neale Ave will be permitted to remain attached. On Queen St the sidewalk needs
to be detached.
2.The condition of the sidewalk and curb and gutter adjacent to the property will be
determined at building permit if it needs to be replaced.
3.All drywells need to be modified in some way to provide pretreatment to meet today’s
standard. The two chamber standard drywell is an example of pretreatment. At building
permit either the two chamber approach or some other pretreatment retrofit will need to be
proposed.
4.The existing utilities show multiple water service lines. Maybe one to the main house and one
to the ADU? As shown on the plans. At building permit all lines will need to be abandoned and
just one service line will supply the building.
5.An easement will need to be put in place for the new transformer prior to building permit
approval. There must be 3’ clear on the sides and back of the transformer.
Thanks.
Hailey Guglielmo, PE
Development Engineer
Engineering Department
201 N Mill St. Ste 203
Aspen, CO 81611
p: 970.429.2751
www.cityofaspen.com