MEMORANDUM
TO: Mayor Torre and Aspen City Council
THROUGH: Phillip Supino, Community Development Director
FROM: Amy Simon, Interim Planning Director/Historic Preservation Officer
MEMO DATE: April 20, 2020
MEETING DATE: April 28, 2020
RE: Notice of Call Up, HPC approval for 227 E. Main Street- Conceptual Major
Development Review, Relocation, Setback Variations
APPLICANT/OWNER:
227 East Main LLC
REPRESENTATIVE:
Kim Raymond Architecture +
Interiors
LOCATION:
Street Address:
227 E. Main Street
Legal Description:
Lot F, Block 74, City and Townsite
of Aspen, Colorado
Parcel Identification Number:
PID# 2737-073-28-003
CURRENT ZONING AND USE:
MU, Mixed Use. Currently in
Commercial Use
PROPOSED ZONING AND USE:
MU, Mixed Use. Converting to a
Single-family home
PROCESS SUMMARY: Certain land use approvals granted by
HPC or P&Z require that Council be notified of the decision through
a brief staff summary. The notification is not a public hearing and
no applicant presentation or public comment has been accepted in
the past. During the Call Up Notice, City Council may uphold the
HPC or P&Z decision. Alternatively, Council may request more
detailed information be provided through a presentation by staff
and the applicant at a future meeting. After hearing the additional
project description, Council may uphold the boards’ decision or
may remand it to require reconsideration of specific issues at a new
public hearing. HPC’s or P&Z’s decision on remand shall be final.
BACKGROUND: On April 8th, by a 7-0 vote, HPC approved a
proposal to restore and expand the miner’s cottage at 227 E. Main
Street. The approval included setback variations to accommodate
the original position of the historic house, and to allow appropriate
placement of the addition on this 3,000 square foot lot.
Site Locator Map – 227 E. Main Street
227
Page 2 of 2
130 South Galena Street Aspen, CO 81611-1975 | P: 970.920.5197 | cityofaspen.com
FINANCIAL IMPACTS: N/A
ENVIRONMENTAL IMPACTS: N/A
ALTERNATIVES: N/A
RECOMMENDATION:
HPC conducted two hearings on the project,
initially continuing the review for a restudy of the
location and roof form of the addition. Staff and
HPC supported approval of the redesign that the
architects produced, with a condition to re-
evaluate windows on the new construction as
part of the upcoming Final review application.
The historic resource is in a very deteriorated
condition, a circumstance that will be corrected
by this project. Staff recommends Council
uphold HPC’s decision.
Recommended Motion
“I move to uphold HPC’s approval for 227 E. Main Street- Conceptual Major Development Review,
Relocation, and Setback Variations.”
CITY MANAGER COMMENTS:
___________________________________________________________________________________
___________________________________________________________________________________.
EXHIBITS:
A – Staff memo to HPC
B – Approved Plans
C – Draft HPC meeting minutes, April 8, 2020
D – Draft HPC Resolution