HomeMy WebLinkAbout07_1175 Doolittle Cir Proposal Description
715 W. Main Street, Suite 104 Aspen, Colorado 81611 voice: 970.544.4851 email:LAM@MenendezArchitects.com
March 25, 2021
Re: Castle Ridge Apartments Sidewalk Replacement Project (1175 Doolittle Circle, Aspen)
Project Description
Castle Ridge Apartments is an employee-housing complex consisting of eight, 2-story,
residential buildings and one, 1-story, maintenance equipment storage shed. The project was
originally approved as the Waterhouse Housing project and developed by the city of Aspen
in 1980-1981.
Excluding decks and exterior on-grade stairs, the total area of existing enclosed space is
64,251 square fee, consisting of eight residential buildings totaling approximately 63,928
square feet plus a maintenance shed of 988 square feet.
The proposed project consists of removing the on-grade concrete walkways and stairs serving
the 600 & 700 Buildings, that were constructed without a permit, and replacing them with
new code-compliant on-grade concrete walkways and stairs as mandated by order of the
Building Department. The replacement on-grade stairs count toward the deck area of the lot.
Per the attached Pre-Application Conference Summary the proposed improvement project is
subject to 8040 Greenline Review Exemption and Insubstantial PD Amendment review.
8040 Greenline Exemption
Per Land Use Code Section 26.435.030.B projects are exempt from 8040 Greenline and may
be reviewed administratively if all of the following standards are met:
1. The development does not add more than ten percent (10%) to the floor area of
the existing structure or increase the total amount of square footage of areas of
the structure that are exempt from floor area calculations by more than twenty-
five percent (25%).
Project meets the standard - the replacement walkway stairs total 425 square feet,
which represents less than one percent of the existing floor area.
2. The development does not require the removal of any tree for which a permit
would be required pursuant to Section 15.04.450 or the applicant received a
permit pursuant to said Section.
Project meets the standard - the project is designed to leave all existing trees in place.
In the event that any of the existing trees require removal a tree removal permit will
be obtained.
3. The development is located such that it is not affected by any geologic hazard
and will not result in increased erosion and sedimentation.
Project meets the standard - the replacement walkways are to be located in the same
general location as the existing walkways. There are no geologic hazards in these
locations and the replacement walkways should not result increased erosion and
sedimentation since these are already developed and disturbed areas.
4. All exemptions are cumulative. Once a development reaches the totals specified
in Subsection 26.435.030.B.1, and 8040 Greenline review must be obtained
pursuant to Subsection 26.435.030.C.
Project meets the standard – the only previous 8040 Greenline exemption for this
property was for the 988 square foot shed that replaced previously existing sheds.
8040 Greenline Review Standards
In addition to meeting the 8040 Greenline review exemption standards, the project meets all
8040 Greenline review standards listed in Section 26.435.030.C as follows:
1. The parcel on which the proposed development is to be located is suitable for
development considering its slope, ground stability characteristics, including
mine subsidence and the possibility of mudflow, rock falls and avalanche
dangers. If the parcel is found to contain hazardous or toxic soils, the applicant
shall stabilize and revegetate the soils or, where necessary, cause them to be
removed from the site to a location acceptable to the City.
Project complies with requirement – the parcel is already developed with 8 multi-
family residential buildings, a shed and a significant amount of hardscape areas
dedicated to walkways, road and parking. The replacement walkways are to be
located where the existing walkways currently exist that serve the 600 and 700
buildings. There is no evidence of previous mudflows or rock falls and avalanche
dangers in this location. The walkways are proposed to be located on a gently sloping
part of the site.
2. The proposed development does not have a significant adverse effect on the
natural watershed, runoff, drainage, soil erosion or have consequent effects of
water pollution.
Project complies with requirement – the project will not change the existing course of
drainage. All drainage from the replacement walkways will continue to flow similarly
to the existing walkways. The water will be conducted via grassy areas to the existing
drainage.
3. The proposed development does not have a significant adverse affect on the air
quality in the City.
Project complies with requirement – the replacement walkways will not have any
equipment that would contribute to air pollution and will not have a snowmelt system.
4. The design and location of any proposed development, road or trail is
compatible with the terrain on the parcel on which the proposed development is
to be located.
Project complies with requirement – the replacement walkways follow the slope of
the terrain and create a gentler and safer approach to the buildings than the walkways
they will replace.
5. Any grading will minimize, to the extent practicable, disturbance to the terrain,
vegetation and natural land features.
Project complies with requirement – grading will be minimized to what is required to
construct the proposed project. The project has been designed to preserve the existing
trees. All disturbed soils will be reseeded.
6. The placement and clustering of structures will minimize the need for roads,
limit cutting and grading, maintain open space and preserve the mountain as a
scenic resource.
Project complies with requirement – the proposed building will be located where the
site already contains development. Grading will be limited to what is needed for the
replacement walkways. No new roads or driveways will be necessary to access the
walkways.
7. Building height and bulk will be minimized.
Project complies with requirement – the proposed replacement walkways are on-
grade.
8. Sufficient water pressure and other utilities are available to service the proposed
development.
Project complies with requirement – the replacement walkways do not require
utilities or water.
9. Adequate roads are available to serve the proposed development and said roads
can be properly maintained.
Project complies with requirement – the proposed project will be located in an
existing development that is served by Castle Creek Road. The walkways will be
served by Doolittle Circle, which is the private road within the existing development
and is maintained by the property owner.
10. Adequate ingress and egress is available to the proposed development so as to
ensure adequate access for fire protection and snow removal equipment.
Project complies with requirement – there is already adequate ingress and egress to
the site, and to the location of the replacement walkways via Doolittle Circle for fire
protection and snow removal.
11. The adopted regulatory plans of the Open Space and Trails Board are
implemented in the proposed development, to the greatest extent practical.
Project complies with requirement – not applicable.
Insubstantial Amendments
Per Section 26.445.110.A of the Land Use Code, the proposed project falls under the
category of Insubstantial Amendment to a PD by meeting the required criteria as follows:
1. The request does not change the use or character of the development.
Project meets the criteria – the replacement walkways will serve existing
development without changing its use or character. The proposed work does not
include any work to the existing buildings, only to the walkways.
2. The request is consistent with the conditions and representations in the project’s
original approval, or otherwise represents an insubstantial change.
Project meets the criteria – the original approval is not very detailed but the
replacement walkways replace existing walkways. This is an insubstantial change to
what has existed since the project was originally built.
3. The request does not require granting a variation from the project’s allowed
use(s) and does not request an increase in the allowed height or floor area.
Project meets the criteria – the replacement walkways do not change the allowed use
and does not impac height. The original approval does not define a specific maximum
floor area but the walkways replace existing stair floor area and only increases it, if at
all, by an amount equal to less than one percent (1%) of the existing floor area.
4. Any proposed changes to the approved dimensional requirements are limited to
a technical nature, respond to a design parameter that could not have been
foreseen during the Project Review approval, are within dimensional tolerances
stated in the Project Review, or otherwise represents an insubstantial change.
Project meets the criteria – the original approval is not detailed with respect to
dimensional requirements and the proposed improvement should be considered an
insubstantial change that is necessary to safely and properly access the building they
serve. This suggests that precise total floor area was not of concern and that certain
flexibility in floor area was allowed for the project. Thus, further supporting that the
proposed increase in area is insubstantial to the original approval.
Given the type and the insubstantial nature of the proposed project we feel that it is a good
candidate for an administrative review and that the added costs and time that would be
required for a Planning and Zoning Commission and City Council review would represent an
unnecessary hardship to the Owner of this employee housing project.