26.435.040.E, Special Review Standards
No development shall be permitted within the stream margin of the Roaring Fork River unless
the Community Development Director makes a determination that the proposed development
complies with all requirements set forth below:
An application requesting a variance from the stream margin review standards or an appeal of
the Stream Margin Map's Top of Slope determination, shall be processed as a Special Review
in accordance with common development review procedure set forth in Chapter 26.304. The
Special Review shall be considered at a public hearing for which notice has been published,
posted and mailed, pursuant to Subsection 26.304.060.e.3. Review is by the Planning and
Zoning Commission.
A Special Review from the stream margin review determination may be approved, approved
with conditions or denied based on conformance with the following review criteria:
1. An authorized survey from a Colorado professionally licensed surveyor shows a different
determination in regard to the Top of Slope and 100-year flood plain than the Stream
Margin Map located in the Community Development Department and filed in the City
Engineering Department.
Staff findings: A survey has been submitted from a Colorado professionally licensed
surveyor depicting the proposed location of the alternative Top of Slope. A report was
also submitted by SGM Engineering which speaks to the locations of floodplain Zone X
and AE, as well as the existing slope and topography of the parcel. A site visit with the
Engineering Department and the applicant confirmed the location of existing riparian
zones. The culmination of these documents and the site visit helped to inform the
proposed location of the alternative Top-of-Slope. An official wetland delineation will be
required to confirm the locations of all floodplains. Any development proposed in the
future that is located within the Stream Margin Review area is subject to all Stream Margin
Review standards. A subsequent alternative Top-of-Slope may be required pending any
new findings that were not clear as part of this review. Staff finds this criterion to be
met.
2. The proposed development meets the Stream Margin review standard(s) upon which the
Community Development Director had based the finding of denial.
Staff findings: This land use application complies with the applicable Stream Margin
Review standards. Any new development proposed within the Stream Margin Review
area will be subject to another Stream Margin Review process. An analysis that brings
forth new findings not discussed within this review may require a subsequent Top-of-
Slope to be established. Staff finds this criterion to be met.