26.445.050. Project Review Standards.
The Project Review shall focus on the general concept for the development and shall outline any
dimensional requirements that vary from those allowed in the underlying zone district. The burden
shall rest upon an applicant to show the reasonableness of the development application and its
conformity to the standards and procedures of this Chapter and this Title. The underlying zone
district designation shall be used as a guide, but not an absolute limitation, to the dimensions which
may be considered during the development review process. Any dimensional variations allowed
shall be specified in the ordinance granting Project Approval. In the review of a development
application for a Project Review, the Planning and Zoning Commission or the Historic
Preservation Commission, as applicable, and City Council shall consider the following:
A. Compliance with Adopted Regulatory Plans. The proposed development complies with
applicable adopted regulatory plans.
Staff Findings: The proposed development is not subject to a regulatory city document. Staff finds
this criterion is met.
B. Development Suitability. The proposed Planned Development prohibits development on
land unsuitable for development because of natural or man-made hazards affecting the property,
including flooding, mudflow, debris flow, fault ruptures, landslides, rock or soil creep, rock falls,
rock slides, mining activity including mine waste deposit, avalanche or snowslide areas, slopes in
excess of 30%, and any other natural or man-made hazard or condition that could harm the health,
safety, or welfare of the community. Affected areas may be accepted as suitable for development
if adequate mitigation techniques acceptable to the City Engineer are proposed in compliance with
Title 29 – Engineering Design Standards. Conceptual plans for mitigation techniques may be
accepted for this standard. The City Engineer may require specific designs, mitigation techniques,
and implementation timelines be defined as part of the Detailed Review and documented within a
Development Agreement.
Staff Findings: The lot currently contains development. The property currently contains Lift 1A
and a ski operations building. The Engineering Department outlined specific information needed
to comply with the Engineering Design Standards and provide adequate mitigation for natural
hazards such as mudflow. With appropriate conditions of approval, staff finds this criterion
conditionally met.
C. Site Planning. The site plan is compatible with the context and visual character of the
area. In meeting this standard, the following criteria shall be used:
1. The site plan responds to the site’s natural characteristics and physical constraints such as
steep slopes, vegetation, waterways, and any natural or man-made hazards and allows
development to blend in with or enhance said features.
Staff Findings: The proposed development mimics the natural changes in topography by
stepping the design in modules. However, the proposed building is very large and although
the modules assist in breaking up the mass, additional consideration needs to be given to
reducing the mass, as it does not blend in or enhance the ski mountain. Staff finds this
criterion to not be met.
Exhibit A
Planned Development – Project Review
2
2. The project preserves important geologic features, mature vegetation, and structures or
features of the site that have historic, cultural, visual, or ecological importance or contribute
to the identity of the town.
Staff Findings: The applicant is proposing the removal of mature trees along the property’s
east service road. The Parks Department has reviewed this application and would like to
see these trees preserved. Parks has instructed the applicant to provide a more detailed
grading plan showing why these trees require removal, and the amount of fill or cut
required up against the trunk of the trees. Parks is also requiring an alternative to preserve
the spruce trees adjacent to the Caribou Condominiums. Staff finds this criterion to not be
met.
3. Buildings are oriented to public streets and are sited to reflect the neighborhood context.
Buildings and access ways are arranged to allow effective emergency, maintenance, and
service vehicle access.
Staff Findings: The proposed development is oriented with its front entrance towards South
Aspen St., which is the only public street that accesses the site. The site is constructed with
one large building that contains no access ways through the site, rather, there is just one
walkway that starts at the front of the property and wraps the building to the east. The
front of this walkway could be particularly problematic for emergency service as this area
also serves pedestrians, skiers and ski co when needed. Staff recommends the applicant
study the design and provide additional access ways through the site to allow for more
effective pedestrian, skier, emergency, maintenance and service vehicle access. Staff finds
this criterion to not be met.
D. Dimensions. All dimensions, including density, mass, and height shall be established
during the Project Review. A development application may request variations to any dimensional
requirement of this Title. In meeting this standard, consideration shall be given to the following
criteria:
1. There exists a significant community goal to be achieved through such variations.
Staff Findings: As part of this proposal the applicant is requesting a rezoning of the
property to Ski Base Area (SKI). The dimensions of this zone district are set by the adoption
of a final development plan, as there are not underlying dimensional standards for this
zone district. Therefore the applicant is not requesting any variations from underlying
zoning with this PD request. Staff finds this criterion to be not applicable.
2. The proposed dimensions represent a character suitable for and indicative of the primary
uses of the project.
Staff Findings: The project proposes approximately 70,000 sq. ft. of floor area. The site’s
current zoning is Conservation (C) which permits the development of a single-family home
on the site. With the requested rezoning to Ski Area Base (SKI) the applicant is requesting
a much larger development that includes lodge, commercial space, underground parking,
and residential housing. Staff finds the overall size to be too large for the neighborhood
in which it is being proposed, Staff finds this criterion to not be met.
Exhibit A
Planned Development – Project Review
3
3. The project is compatible with or enhances the cohesiveness or distinctive identity of the
neighborhood and surrounding development patterns, including the scale and massing of
nearby historical or cultural resources.
Staff Findings: The surrounding neighborhood is comprised of a small lodge and multi-
family residential units. In this sense the proposed uses are compatible with the identity of
the neighborhood. However, the scale of the development, proposed as a single building,
does not complement the development pattern of the neighborhood. Staff recommends the
building be divided into separate structures to support less massing and scale, as well as
to provide additional access points through the site. Staff finds this criterion to not be met.
4. The number of off-street parking spaces shall be established based on the probable number
of cars to be operated by those using the proposed development and the nature of the
proposed uses. The availability of public transit and other transportation facilities,
including those for pedestrian access and/or the commitment to utilize automobile
disincentive techniques in the proposed development, and the potential for joint use of
common parking may be considered when establishing a parking requirement.
Staff Findings: The applicant is proposing 61 off-street parking spaces in a sub-grade
garage accessed from South Aspen St. As a note: the Lift One Lodge has requirements to
maintain four parking spaces at the end of South Aspen St. that may not be removed by
Gorsuch Haus.
The applicant is proposing to add a public transit stop that has been reviewed by the City’s
Engineering Dept. The bus stop is part of the MMLOS improvements required for the
project.
Staff finds this criterion to be met.
5. The Project Review approval, at City Council’s discretion, may include specific allowances
for dimensional flexibility between Project Review and Detailed Review. Changes shall
be subject to the amendment procedures of Section 26.445.110 – Amendments.
Staff Findings: The applicant is not requesting any allowances for dimensional flexibility
at this time. Staff finds this criterion to be not applicable.
E. Design Standards. The design of the proposed development is compatible with the
context and visual character of the area. In meeting this standard, the following criteria shall be
used:
1. The design complies with applicable design standards, including those outlined in Chapter
26.410, Residential Design Standards, Chapter 26.412, Commercial Design Standards,
and Chapter 26.415, Historic Preservation.
Staff Findings: The proposed development is subject to Chapter 26.412, Commercial
Design Standards. The design does not provide a human scale for the project and provides
building massing above the Wheeler View Plane and views through the property are not
provided. Staff does not find the applicant to effectively meet the design standards related
to public amenity or utility location, and find that the trash/recycling area proposed will
Exhibit A
Planned Development – Project Review
4
require a Special Review approval by the Environmental Health Dept. Staff finds this
criterion to not be met.
2. The proposed materials are compatible with those called for in any applicable design
standards, as well as those typically seen in the immediate vicinity. Exterior materials are
finalized during Detailed Review, but review boards may set forth certain expectations or
conditions related to architectural character and exterior materials during Project Review.
Staff Findings: The applicant is proposing to construct the building from stone, wood, and
metal with zinc and green roofs. These materials are compatible with those seen in the
immediate vicinity, which include wood, metal and stone. Staff finds this criterion to be
met.
F. Pedestrian, bicycle & transit facilities. The development improves pedestrian, bicycle,
and transit facilities. These facilities and improvements shall be prioritized over vehicular
facilities and improvements. Any vehicular access points, or curb cuts, minimize impacts on
existing or proposed pedestrian, bicycle, and transit facilities. The City may require specific
designs, mitigation techniques, and implementation timelines be defined as part of the Detailed
Review and documented within a Development Agreement.
Staff Findings: In response to the required Traffic Impact Analysis the applicant is proposing a
new bus stop with lighting and bench seating at the northern edge of the pedestrian walkway at
the front of the site; however, there is no actual vehicle proposed for this stop that is city run,
rather a shuttle van is proposed. The applicant is also proposing the addition of bicycle parking
across from the bus stop. Additional information is needed to evaluate the shuttle option to verify
it is a legitimate option. Staff finds this criterion not to be met.
G. Engineering Design Standards. There has been accurate identification of engineering
design and mitigation techniques necessary for development of the project to comply with the
applicable requirements of Municipal Code Title 29 – Engineering Design Standards and the City
of Aspen Urban Runoff Management Plan (URMP). The City Engineer may require specific
designs, mitigation techniques, and implementation timelines be defined as part of the Detailed
Review and documented within a Development Agreement.
Staff Findings: Staff Findings: Currently, the engineering department has noted that the proposal
does not meet certain standards such as the required width of the cul-de-sac and other design
features of the cul-de-sac including the transit stop and the need for sidewalks. The drainage
proposed does not currently work with other drainage plans along the S. Aspen Street corridor.
Staff does not find this criterion met.
H. Public Infrastructure and Facilities. The proposed Planned Development shall upgrade
public infrastructure and facilities necessary to serve the project. Improvements shall be at the
sole costs of the developer. The City Engineer may require specific designs, mitigation techniques,
and implementation timelines be defined as part of the Detailed Review and documented within a
Development Agreement.
Staff Findings: The applicant has been working with the Engineering Dept. to provide
improvements to the site that will upgrade the public infrastructure and facilities in this area. The
Exhibit A
Planned Development – Project Review
5
Engineering Dept. has required the applicant to work with adjacent One Aspen project to provide
a joint drainage plan that will serve both properties. Further requirements from Engineering are
listed as part of Exhibit H – Referral Agency Comments. Staff finds this criterion to be
conditionally met.
I. Access and Circulation. The proposed development shall have perpetual unobstructed
legal vehicular access to a public way. A proposed Planned Development shall not eliminate or
obstruct legal access from a public way to an adjacent property. All streets in a Planned
Development retained under private ownership shall be dedicated to public use to ensure adequate
public and emergency access. Security/privacy gates across access points and driveways are
prohibited.
Staff Findings: The only access way to this site is via S. Aspen St, which is a public roadway. The
applicant is proposing to terminate S. Aspen St. in a cul-de-sac, which will also be used as a turn-
around for dropping people off to the site, as well as the bus drop-off/loading area. With these
uses the cul-de-sac will not remain unobstructed.
The applicant is also proposing a perpetual vehicular easement across Lot 3 to provide access to
Lot 4. However, this corridor will also serve as ski return to Lift One Park. This may prove to be
a conflict of different uses.
Staff finds this criterion to not be met.