NOTICE OF EXEMPTION AND AUTHORIZATION TO APPLY FOR LAND USE/
BUILDING PERMITS DURING THE EFFECTIVE TERM OF ORDINANCE#27,
SERIES OF 2021 AND ORDINANCE #6, SERIES OF 2022
Property Address: 735 E Bleeker St Aspen, CO 81611
Parcel ID Number: 2737 07 360 006
Property Owner: David Beckwith
Representative/email: vkr@reidarchitects.com
Scope of Work (Provide narrative here and a separate pdf which is a succinct and
clear set of supporting documents, to be attached to this form as Exhibit A, such as
Letters of Completeness, Resolutions, Development Orders, Land Use Case
numbers, Building Permit numbers etc. If the representation being made is that the
work does not involve dimensional changes prohibited by the moratorium provide
existing and proposed calculations, floor Plans and and elevations to be attached:
construction of an exterior stair,no change to building envelope. Work is located in an approved building envelope,drawings attached.
Due to the circumstances noted below, the above referenced project as defined by
the Scope of Work is exempt from the application of Ordinance #27, Series of 2021
and Ordinance #6, Series of 2022, and is authorized to pursue a land use review
and/or building permit review during the effective terms of Ordinance #27, Series of
2021 and Ordinance #6, Series of 2022, ordinances which generally place a
moratorium on residential development. This authorization does not guarantee
issuance of a building permit or approval of any land use application. The applicant
must submit complete information and pursue all authorized approvals in a timely
fashion, adhering to all deadlines for submission, terms of Vested Rights,
response times required to maintain an active building permit, and all other Land Use
Code and Building Code requirements in effect as of December 8, 2021. Any
amendments and or additional approvals not addressed or identified in the
application, may be subject to Ordinance #27, Series of 2021 or Ordinance #6 Series
of 2022. RECEIVED
The project described above is permitted to proceed with land use review becgo121/2022
(check all that apply):
ASPEN
BUILDING DEPARTMENT
o A land use application for a Development Order or Notice of Approval was
submitted to the Community Development Department prior to final passage of
the ordinance on December 8, 2021, and was subsequently deemed to be
complete by the Community Development Department Director.
❑ The land use application is seeking a Development Order or Notice of Approval
for a project consisting of 100°/0 Affordable Housing as that term is defined at
§26.104.100 of the Aspen Municipal Code, or as may be deemed necessary for
the issuance of Certificates of Affordable Housing for a 100% Affordable Housing
project, or as determined by the Community Development Director.
❑ The land use application involves Voluntary AspenModern designation
processes that meet the requirements of Section 26.415.025.0 and
26.415.030.
❑ The land use application or administrative request may be necessary to issue
exempt building permits as described below, and as determined by the
Community Development Director.
The project described above is permitted to submit for building permit review
because (check all that apply):
❑ A building permit application was submitted to the Community Development
Department prior to final passage of the ordinance on December 8, 2021, and
was subsequently deemed to be complete by the Chief Building Official.
o It is a building permit for a project that will not increase the gross square
footage of development, Net leasable area, or Net livable area of any building
and does not meet the definition of demolition.
o It is a building permit for a project that will not increase the Height of any
building. This includes additions to or replacement of mechanical equipment or
energy efficiency systems pursuant to height exemptions as set forth at
§26.575.020 of the Aspen Municipal Code, or as determined by the Community
Development Director.
❑ It is a building permit for commercial and lodge development as stand-alone
uses on a parcel or property.
❑ The project has received or is eligible to receive a Development Order or
Notice of Approval on the effective date of this ordinance.
❑ It is a building permit for 100% affordable housing projects as that term is
defined at §26.104.100 of the Aspen Municipal Code.
❑ It is a building permit for demolition or repair of non-habitable structures.
Issued on June 10 , 2022 , this certificate is valid through the
effective date of Ordinance #27, Series of 2021 and Ordinance #6, Series of 2022, or
any Ordinance which supersedes a provision of these ordinances in a manner which
is relevant to the Scope of Work. A copy of this certificate is required when applying
for any land use review or building permit. This Notice is not a Development Order
or Administrative Determination that is subject to appeal.
47 3 w - Planning Director, for
Phillip Supino
Community Development Director
Disclaimer: This exemption is given based on the information provided by the applicant. If changes are
made, or the scope,after a more detailed review, is found to be subject to Ordinance 27, 20210at IVED
Ordinance #6, Series of 2022, the exemption may be revoked. ,PE
Exhibit A: Floor plans and elevations representing scope of work
06/21/2022
ASPEN
BUILDING DEPARTMENT
Exhibit A
NOTICE OF APPROVAL
FOR A CITY OF ASPEN ADMINISTRATIVE EXEMPTION OF STREAM MARGIN
REVIEW FOR STAIRWAY CONSTRUCTION, ON THE PROPERTY COMMONLY
DESCRIBED AS 735 E. BLEEKER,LEGALLY DESCRIBED AS UNIT 735,
CREEKTREE CONDOMINIUMS,ACCORDING TO THE MAP THEREOF
RECORDED SEPTEMBER 30, 1981,IN BOOK 12 OF MAPS AT PAGES 20 AND FIRST
AMENDMENT THERETO RECORDED AUGUST 12, 1992,IN PLAT BOOK 29 AT
PAGE 56 AND ACCORDING TO THE CONDOMINIUM DECLARATION THEREOF
RECORDED IN BOOK 416 AT PAGE 354 OF SUCH RECORDS,AS AMENDED.
COUNTY OF PITKIN, STATE OF COLORADO.
Parcel ID No. 2737-07-36-0006
APPLICANT: David Beckwith
85 Gloria Circle
Menlo Park, CA 94025
REPRESENTATIVE: Suzannah Reid,Reid Architects, Inc.
412 N. Mill St.
Aspen, CO 82611
SUBJECT& SITE OF APPROVAL:
The subject property is located within the Medium-Density (R-6) zone district and is improved
with a duplex dwelling. A large portion of the property is located one hundred feet or less (as
measured horizontally) from the high-water line of the Roaring Fork River. This is considered an
Environmentally Sensitive Area and is subject to heightened review pursuant to Land Use Code
Section 26.435.040,Stream Margin Review
SUMMARY:
The Applicant requests approval for Stream Margin Review to construct an exterior staircase that
connects the ground floor to a second-floor deck.
The proposed location of the staircase and a portion of the residence are located within the 100-
year flood plain(FEMA Flood Zone"AE") of the Roaring Fork River. While the staircase will be
located closer to the Roaring Fork River than the existing dwelling, the footprint of the staircase
will be maintained within the building envelope established pursuant to the First Amended Plat of
the Creek Tree Subdivision (Book 37,Page 54).
The footprint of the staircase will measure approximately thirty-three square feet, which falls
within the allowable area for exterior decks. The staircase requires a single steel post on a concrete
sonotube to support the upper landing as well as a three-foot wide concrete foundation under the
existing patio area to support the base of the stair. Existing grade and landscaping will not be impacted. RECEIVED
Page btri$21/2022
ASPEN
BUILDING DEPARTMENT
STAFF EVALUATION:
The project and associated improvements are limited to the existing building envelope pursuant to
the First Amendment Plat of the Creek Tree Subdivision(Book 37,Page 54).
The Engineering Department and the City's Flood Administrator have reviewed the application,
pursuant to Section 11.1.1 of the FEMA Guidance for Flood Risk Analysis and Mapping published
December 2020. The footprint of the staircase is represented at thirty-three square feet, which is
not anticipated to impact the base flood elevation. A condition of approval requires the stairway
to be constructed with open risers to allow for water flow. No changes to existing grade are
permitted. All trees and landscaping improvements will not be impacted.
Upon review of the application, Community Development staff determined that a large portion of
an existing patio was constructed outside of the approved building envelope without proper review
or approval from the City. A condition of approval requires the patio and related improvements to
be removed prior to building permit issuance.
Staff finds that the applicant's request meets the requirements for the Stream Margin Review,
subject to the conditions of approval set forth in this document.
Q II / 733 :ifi■
• C. II
C Bleckc .�::::.
PI I
> tp I I S iown for rc(crcncc on :•■� % ■:
•{.;biriirammerniei, fir. 1;tip
••''••`- Building Footprint
Second Floor ■�► .: .......:... .•r. ... (Conditioned Area)
■fir.:. .:...ti.......:...:.. : r
vowr
Deck Footprint I NI
_�■. ...■:■..:.■:..■: rrti.■
■■■■■ ■■ ■■ ■■■■■■■■■ ■■ main entry /
NEEME Mai
A 7■�{•i:'■ i:::• i■:•i i R.•■:•■:::::•:::•■ '
■�••::•�:f;•U.■■■:■.;;•:•••::■■■:■■4 'zlie,/
11- .=-10;..,
I ■■■■■■.
7■■■■■■■■■■■■ : : t?7 c
• ! ip.r. At-. • ,.. • . • • • • • , ,Grade All,Patio
• • • • • • • • • • • • •
Approved Staircase .:': ':::':':.:.• 0., ,,
Footprint 7 j ��4/All Sr,
I '4< 414' Y„N?:. . x
6-
`. Building Setback Line t j
7. �, (Building Envelope) Q a/
Figure 1: Existing Improvements&Proposed Location of Stairwell
RECEIVED
Page jgf1/2022
ASPEN
BUILDING DEPARTMENT
DECISION:
The Community Development Director finds the request for Exemption from Stream
Margin Review at 1411 Crystal Lake Road is consistent with the allowances in Land Use
Code Section 26.435.040.0 and hereby APPROVES Stream Margin Review subject to the
following conditions:
1. The existing patio and related improvements shall be removed from all areas outside
of the established building envelope prior to the issuance of a building permit.
2. The stairway shall maintain open treads to meet Base Flood Elevation requirements.
The footprint of the stairway shall remain within the established building envelope.
3. A Construction Management Plan shall be included with the building permit. The
plan shall clarify construction methods. Construction shall not impact the existing
river slope,native vegetation, or the river.
4. All Federal and State permitting requirements for construction within the 100-year
flood plain shall be followed.
5. All other zoning requirements not listed in this document shall be met.
APPROVED BY:
P ' S ,AICP Date
Comm ty Development Director
Attachments:
Exhibit A—Review Criteria(Not Recorded)
Exhibit B—Application(Not Recorded)
II
REC Iv'Fr
Page IY6V21/2022
•
ASPEN
BUILDING DEPARTMENT