Project: 1215 Snowbunny Ln, Unit B
Permit # 0063-2022-BRES
22 September 2022
Change Order 01 – Summary
Change order 01 is a structural clarification to replace insufficient existing roof framing. The existing
interior volume remains unchanged. Ceilings heights are not impacted, and the overall area remains the
same.
New parallel chord trusses will replace existing dimensional lumber roof framing. The height of the
building will increase approximately 12”-18” as a result. Final heights will be determined through the
design-build-engineering process by the roof truss manufacturer. We are submitting the worst case
(18”) scenario should we need a 24” tall truss.
Included with the change order submittal are the following drawings:
1. Structural engineering drawings
2. Calculations for both height and demolition area
3. Architectural elevations showing the height increase
Bryan May, AIA
Bryan May Architecture + Interiors
09/26/2022