HomeMy WebLinkAboutFile Documents.204 S Galena St.0030-2022-BCOM (12) CONSTRUCTION MANAGEMENT PLAN GUCCI - ASPEN 204 S Galena Street. Aspen, CO 81611 Prepared by: Ferrante Koberling Construction Inc. 2360 Eastman Ave. Ste 112 Oxnard, CA 93030 CONTACT DESIGNATION: Owner: GUCCI Contact: Michelle Carrieri Phone: 646.634.9651 Site Supervisor: Michael Ferrante Phone: 323.206.1663 Safety Officer: TBD Traffic control Officer: TBD Erosion Control Rep: N/A City of Aspen: 970.920.5000 Aspen Fire Department: 970.925.5532 Aspen Police Department: 970.920.5400 RFTA:970.925.8484 School District: 970.925.3760 Aspen Hospital: 970.925.1120 Emergency: 911 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 TBD 10/05/202210/31/2022 Table of Contents 1.0 General 1.1 Applicability ………………………………………………………………………………………………… 1.2 CMP Submission Certification ………………………………………………………………………….. 2.0 Project Location……………………………………………………………….……………………………… 2.1 Disturbance Area …………………………………………………………….……………………………… 2.2 Location ………………………………………………………………………………………………………. 2.3 Description …………………………………………………………………………………………………… 3.0 Project Documentation ……………………………………………………….……………………………… 3.1 Permits …………………………………………………………………………..…………………………… 3.2 Public Notification ………………………………………………………………..………………………….. 3.3 Project Sign ……………………………………………………………………….…………………………. 3.4 Contact Designation ………………………………………………………………………………………… 4.0 Project Implementation ……………………………………………………………………………………… 4.1 Dates of Construction ………………………………………………………………………….…...…………. 4.2 Hours of Construction ………………………………………………………………………………………. 4.3 Sequence of Construction ……………………………………………………………….…………………. 4.4 Neighboring Properties ………………………………………………………….………………………….. 4.5 Project Fencing ………………………………………………………………..…………………………….. 5.0 Site and Right of Way Management ………………………………………..……………………………… 5.1 Right of way management plan ……………………………………………...…………………………….. 5.2 Emergency Vehicle Ordinance ………………………………………...…….…………………………….. 5.3 Construction Parking Details ………………………………………………...…………………………….. 5.4 Staging Areas …………………………………………………………………...…………………………… 5.5 Right of Way Limitations ………………………………………………………...………………………….. 5.6 Site Plan ……………………………………………………………………………...………………………. 5.7 Waste Management ………………………………………………………………………………………… 6.0 Traffic Control …………………………………………………………………………….…………………… 6.1 General …………………………………………………………………………………..…………………… 6.2 Haul Routes ……………………………………………………………………………….…………………. 6.3 Delivery Requirements ……………………………………………………………………………………… 7.0 Pedestrian Protection ………………………………………………………………………...……………… 7.1 General ……………………………………………………………………………………………………… 8.0 Sediment and Erosion Control ……………………………………………………………………..……… 9.0 Fugitive Dust Control …………………………………………………………………………………..…….. 10.0 Emissions ………………………………………………………………………………………………...…... 11.0 Noise Suppression …………………………………………………………………………………………. Appendix A – Project Location ………………………………………………………..………………………….7 Appendix B – Project Sign ………………………………………………………………………………………..8 Appendix C – Schedule……………………………………………………………………………………………9 Appendix D – Site Plan …………………………………………………………………………………………..10 Appendix E – City of Aspen Haul Route ……………………………………………………………………….11 Appendix F – Noise Control Acceptance …………………………………………………………………..12-15 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022 1.0 GENERAL 1.1 APPLICABILITY This CMP is being submitted to comply with City of Aspen regulations of commercial development which disturb 1000 SF or greater or require demolition, improvement, or renovation (interior and/or exterior) of 400 SF or greater within any twelve-month period. 1.2 CMP SUBMISSION CERTIFICATION The Ferrante Koberling has completed the City of Aspen online CMP certification class. A copy of the CMP certificate is provided with this submission. 2.0 PROJECT LOCATION 2.1 DISTURBANCE AREA The total disturbance area is 5,444 SF and the bu ilding size is 8,817 SF. 2.2 LOCATION Please see Appendix – A 2.3 DESCRIPTION Building Scope of Work The scope of work includes the construction of a new retail store within the demised leased line. Interior renovation including demolition of existing interior non-load bearing partitions, new walls and partitions, new lighting, ceiling, mechanical, electrical, plumbing, and new scheduled finishes. New millwork retail display units, drapery, shelving. New storage units/offices, pantry in the back of house and cellar level. Exterior scope of work to include new proposed glazed storefront windows, and new proposed recessed storefront entry. Demolition Scope of Work The scope of demolition work includes interior finishes, paneling, and millwork removal. Demolition of drywall (All studs and existing building structure to remain, untouched). Remove insulation within partitions. HVAC branch ductwork to removed. Light fixtures to be removed. Plumbing fixtures to be removed. 3.0 PROJECT DOCUMENTATION 3.1 PERMITS Demolition, mechanical, electrical, plu mbing, fire life safety and building. Permit #’s TBD 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 Sachse Construction 10/05/202210/31/2022 3.2 PUBLIC NOTIFICATION Neighbors within 300 feet of the construction site will be notified via mail no later than 10 days prior to the start of construction. Notification will include project description and a schedule. Project update notifications will be sent to neighbors on a monthly basis. 3.3 PROJECT SIGN 18” x 24” Poster will be posted in a readable location from the street or driveway. See Appendix B. 3.4 CONTACT DESIGNATION Please see cover page. 4.0 PROJECT IMPLEMENTATION 4.1 DATES OF CONSTRUCTION Start Date: 08.15.2022 End Date : 01.24.2022 4.2 HOURS OF CONSTRUCTION Monday – Friday: 7:30am – 5:30pm Saturday: 9am – 5pm No Work Sunday No work Thanksgiving day No work New Years Day No exterior work during Christmas week and Holiday Season. 4.3 SEQUENCE (PHASING) OF CONSTRUCTION Please see Appendix C for Rough Schedule 4.4 NEIGHBORING PROPERTIES No excavation will be done. Project will have a barricade in place to assist with the noise control and ensure public safety. During the initial start date, we will introduce ourselves with adjacent businesses and leave our contact information. We plan to work with the other businesses to assure we know about any events, sales they may have and to work accordingly to not disrupt any business activities. 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 11.14.2022 6.23.2023 10/05/202210/31/2022 4.5 PROJECT FENCING Project will have a barricade set up approved by the Engineering Department to assure public safety. 5.0 SITE AND RIGHT OF WAY MANAGEMENT 5.1 RIGHT OF WAY MANAGEMENT PLAN N/A 5.2 EMERGENCY VEHICLE ORDINANCE 35 All vehicles belonging to the construction project will maintain continuous emergency vehicle access. 5.3 CONSTRUCTION PARKING DETAILS Carpool Program – We will enforce all subcontractors to limit the number of vehicles per trade. Employees of the same company will be required to carpool together with an minimum of 2 people per vehicle. 5.4 STAGING AREAS All staging will be done within the space. 5.5 RIGHT OF WAY LIMITATIONS N/A 5.6 SITE PLAN Please see Appendix D for Site Plan. All job material storage, waste management containers, portable restroom will be stored within site. 5.7 WASTE MANAGEMENT A Waste Management Plan will be submitted prior to demolition. We will comply with City of Aspen’s regulations. During interior demo, waste containers will be placed inside space and removed daily from 7am – 10:30am. 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022 6.0 TRAFFIC CONTROL 6.1 GENERAL N/A 6.2 HAUL ROUTES Project will use City of Aspen’s designated routes for any Hauls, if applicable. See Appendix E 6.3 DELIVERY REQUIREMENTS No more than (1) delivery to be on site at a time. The delivery hours to be from 7:30am to 10:00am. 7.0 PEDESTRIAN PROTECTION 7.1 GENERAL A barricade will be placed on proposed site to ensure pedestrian safety. See Appendix F for barricade spec. 8.0 SEDIMENT AND EROSION CONTROL – N/A 9.0 FUGITIVE DUST CONTROL – N/A 10.0 EMISSIONS – N/A 11.0 NOISE SUPPRESSION 11.1 General Please see Appendix G with initials of acceptance. 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022 APPENDIX – A PROJECT LOCATION 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022 APPENDIX – B PROJECT SIGN PROJECT: GUCCI Build Out ADDRESS: 204 s Galena Street – Space A Aspen, CO 81611 PERMIT NUMBER:_____________ CONTACTOR: Ferrante Koberling Construction, Inc. Michael Ferrante (323) 206-1663 mferrante@ferrantekoberling.com EMERGENCY CONTACT: Michael Ferrante Cell: (323) 206-1663 Interior Remodel (demo, new FF&E, flooring, lighting) Gucci Ferrante Koberling Listing Agent: ________________________________ Website/Contact: ______________________________ PICTURE WILL BE INSERTED HERE 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 Tony Mazzotta (313) 549-9544 Sachse Construction 10/05/202210/31/2022 ID Task Name Duration Start Finish 1 Pre‐Construction 85 days Mon 7/18/22 Mon 11/14/22 2 Bid Submission 1 day Mon 7/18/22 Mon 7/18/22 3 First review call 1 day Mon 7/25/22 Mon 7/25/22 4 Final Bid Proposal 1 day Tue 8/2/22 Tue 8/2/22 5 Award Sachse 1 day Wed 8/10/22 Wed 8/10/22 6 Award Trades / submittals 15 days Thu 8/11/22 Wed 8/31/22 7 Receive Permit 1 day Thu 10/27/22 Thu 10/27/22 8 Mobilization 1 day Mon 11/14/22 Mon 11/14/22 9 PROJECT DURATION 150 days Mon 11/14/22 Mon 6/19/23 10 LL Precon 1 day Mon 11/14/22 Mon 11/14/22 11 CONSTRUCTION START 1 day Mon 11/14/22 Mon 11/14/22 12 Install Barricade 6 days Mon 11/14/22 Mon 11/21/22 13 Demo Work (start while barricade going up)10 days Wed 11/30/22 Tue 12/13/22 14 Clean and make ready for Millwork visit 1 day Wed 12/14/22 Wed 12/14/22 15 Submittals from all trades due 20 days Mon 10/31/22 Tue 11/29/22 16 Floor Survey 2 days Thu 12/15/22 Fri 12/16/22 17 Floor Infill and Overlay and curb 8 days Mon 12/19/22 Tue 1/3/23 18 Layout Walls 3 days Wed 1/4/23 Fri 1/6/23 19 Layout review with MILLWORKER  Architect / Owner 1 day Mon 1/9/23 Mon 1/9/23 20 Final drawings issued by MILLWORKER 5 days Tue 1/10/23 Mon 1/16/23 21 Layout SALES walls based on MILLWORKER dimensions 2 days Tue 1/17/23 Wed 1/18/23 22 Core for under slab elec. and plumbing 3 days Tue 1/10/23 Thu 1/12/23 23 Interior wall framing ‐ Level 1 BOH (non‐sales)3 days Tue 1/10/23 Thu 1/12/23 24 Interior wall framing (sales)6 days Tue 1/17/23 Tue 1/24/23 25 Storefront framing / Structural Steel / dumbwaiter rough 7 days Fri 1/20/23 Mon 1/30/23 26 Rough Electrical (overhead and in‐wall)15 days Wed 1/4/23 Tue 1/24/23 27 Rough Plumbing 3 days Wed 1/25/23 Fri 1/27/23 28 Rough HVAC 10 days Wed 1/25/23 Tue 2/7/23 29 Rough Sprinkler 3 days Wed 2/8/23 Fri 2/10/23 30 Rough Speakers and Security Cables 2 days Mon 2/13/23 Tue 2/14/23 31 Install of interior Blocking (millworker to review)2 days Mon 2/13/23 Tue 2/14/23 32 Light Fixtures delivered 1 day Wed 1/25/23 Wed 1/25/23 33 Set Light Troughs 7 days Mon 2/13/23 Tue 2/21/23 11/14 1/25 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Galena Street Aspen, CO Page 1 Bid Schedule issued Mid-Nov Start 10/05/202210/31/2022 ID Task Name Duration Start Finish 34 Ceiling Framing 7 days Wed 2/22/23 Thu 3/2/23 35 Inspections 2 days Fri 3/3/23 Mon 3/6/23 36 Architect / Owner Visit ‐ 2nd Visit 1 day Tue 3/7/23 Tue 3/7/23 37 Drywall interior walls and ceilings 5 days Tue 3/7/23 Mon 3/13/23 38 Tape, Mud, Finish Drywall walls 7 days Tue 3/14/23 Wed 3/22/23 39 Doors and frames 1 day Thu 3/23/23 Thu 3/23/23 40 Paint walls and ceiling 3 days Fri 3/24/23 Tue 3/28/23 41 Final Electrical 8 days Wed 3/29/23 Fri 4/7/23 42 Final Plumbing 3 days Wed 3/29/23 Fri 3/31/23 43 Final HVAC 7 days Wed 3/29/23 Thu 4/6/23 44 Final Sprinklers 2 days Wed 3/29/23 Thu 3/30/23 45 Floor Prep 2 days Wed 3/29/23 Thu 3/30/23 46 Delivery of Gucci floor material (need time acclimate)1 day Thu 3/16/23 Thu 3/16/23 47 Floor Layout 2 days Fri 3/31/23 Mon 4/3/23 48 Install wood border 5 days Tue 4/4/23 Mon 4/10/23 49 Install Marble Carpet 7 days Tue 4/11/23 Wed 4/19/23 50 Install wood flooring 7 days Thu 4/20/23 Fri 4/28/23 51 White Box Completion 1 day Fri 4/28/23 Fri 4/28/23 52 Complete FOH Stone Restroom 10 days Mon 5/1/23 Fri 5/12/23 53 Millwork Delivery 2 days Fri 4/28/23 Mon 5/1/23 54 Millwork Install                                                                               28 days Tue 5/2/23 Thu 6/8/23 55 Paint Wood Floor 7 days Fri 5/26/23 Mon 6/5/23 56 UL Inspection 1 day Fri 6/9/23 Fri 6/9/23 57 GC portion ‐ Storefront rework 76 days Tue 1/31/23 Tue 5/16/23 58 Install storefront substrate / densglass 7 days Tue 1/31/23 Wed 2/8/23 59 Insert Stone sills 5 days Tue 3/7/23 Mon 3/13/23 60 Storefront framing 4 days Tue 4/18/23 Fri 4/21/23 61 Cladding 6 days Mon 4/24/23 Mon 5/1/23 62 Set Glass 4 days Mon 5/8/23 Thu 5/11/23 63 Doors and Frames 3 days Fri 5/12/23 Tue 5/16/23 64 BOH (Cellar Level)90 days Wed 1/11/23 Tue 5/16/23 65 Framing 2 days Wed 1/11/23 Thu 1/12/23 66 Inwall / Overhead electrical 10 days Fri 1/13/23 Thu 1/26/23 67 HVAC rough ductwork 4 days Fri 1/27/23 Wed 2/1/23 3/16 4/28 6/9 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Galena Street Aspen, CO Page 2 Bid Schedule issued Mid-Nov Start 10/05/202210/31/2022 ID Task Name Duration Start Finish 68 Rough plumbing 3 days Thu 2/2/23 Mon 2/6/23 69 Suppression 2 days Thu 2/2/23 Fri 2/3/23 70 Drywall ‐ hang / tape and finish 6 days Mon 2/6/23 Mon 2/13/23 71 Prime walls 2 days Tue 2/14/23 Wed 2/15/23 72 Doors and frames 1 day Thu 2/16/23 Thu 2/16/23 73 ACT Ceiling grid 4 days Fri 2/17/23 Wed 2/22/23 74 Finish Electrical / Lights / HVAC 12 days Thu 2/16/23 Fri 3/3/23 75 Complete Dumbwaiter 3 days Tue 4/18/23 Thu 4/20/23 76 Paint 2 days Fri 4/21/23 Mon 4/24/23 77 Open grid inspection 1 day Tue 4/25/23 Tue 4/25/23 78 ACT Ceiling pads 2 days Wed 4/26/23 Thu 4/27/23 79 VCT Flooring 2 days Fri 4/28/23 Mon 5/1/23 80 Millwork 5 days Tue 5/2/23 Mon 5/8/23 81 Finish Plumbing _ Canteen and Restroom 6 days Tue 5/9/23 Tue 5/16/23 82 Shelving Street Level 4 days Wed 5/17/23 Mon 5/22/23 83 Storefront Signage 3 days Tue 6/6/23 Thu 6/8/23 84 Touch up Paint walls and ceilings 4 days Tue 6/6/23 Fri 6/9/23 85 MIS EQUIPMENT INSTALL (owner vendor)4 days Tue 6/6/23 Fri 6/9/23 86 Security Install 4 days Tue 6/6/23 Fri 6/9/23 87 Test & Balance 1 day Mon 3/6/23 Mon 3/6/23 88 Construction Clean 1 day Fri 6/9/23 Fri 6/9/23 89 Final Inspections 3 days Thu 6/8/23 Mon 6/12/23 90 Punch List walk through 1 day Mon 6/12/23 Mon 6/12/23 91 Complete punch list 5 days Mon 6/12/23 Fri 6/16/23 92 Final Cleaning 1 day Mon 6/19/23 Mon 6/19/23 93 Store Turn Over 1 day Mon 6/19/23 Mon 6/19/23 94 Barricade Removal 4 days Tue 6/20/23 Fri 6/23/23 95 Merchandise / Store set up 4 days Mon 6/19/23 Thu 6/22/23 96 Store Opens 1 day Fri 6/23/23 Fri 6/23/23 97 98 99 6/23 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Critical Critical Split Progress Manual Progress Galena Street Aspen, CO Page 3 Bid Schedule issued Mid-Nov Start 10/05/202210/31/2022 APPENDIX D – SITE PLAN 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022 APPENDIX E – CITY OF ASPEN HAUL ROUTE 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022 APPENDIX F – NOISE CONTROL ACCEPTANCE 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022 APPENDIX F – CONTINUED 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022 APPENDIX F – CONTINUED 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022 APPNEDIX F – CONTINUED 08/08/2022 Sachse Construction 3663 Woodward Ave. Suite #500 Detroit, MI 48201 10/05/202210/31/2022