Page: 1
Author: pjm
File Name: 40.WaterEasement.701Gibson.20220308.pdf
Fill in the easement agreement
so I can send to Water
Department & COA Attorney for
signatures as well.
40.WaterEasement.701Gibson.20220308.pdf (4)
Page: 1
Author: pjm
File Name: 40.WaterEasement.701Gibson.20220308.pdf
Comments on the water main
easement will not hold up
issuance of the permit, these
comments need to be addressed
prior to CO/LOC for the project -
however finalizing this asap is
recommended.
Page: 4
Author: pjm
File Name: 40.WaterEasement.701Gibson.20220308.pdf
Easement needs to be signed by
property owner for finalize the
document.
Page: 8
Author: pjm
File Name: 40.WaterEasement.701Gibson.20220308.pdf
This is the final easement,
remove draft.
Page: 3
Author: pjm
File Name: 90.Civil.701Gibson.20220322.pdf
Impacts to trees? Parks needs to
approve the location of the inlet
box.
90.Civil.701Gibson.20220322.pdf (3)
ENT AGREEMENT
ered into this _____ day of _________, 2022,
a Colorado municipal corporation and home
ress is 701 Gibson Avenue, Aspen, CO 81611
ls
e City of Aspen municipal water distribution
distribution system uses a waterline uses a
tor’s property known as 701 Gibson Avenue,
Fill in the easement
agreement so I can
send to Water
Department & COA
Attorney for
signatures as well.
EN
T AGREEMENT
into this _____ day of _________, 2022,
olorado municipal corporation and home
Comments on the water main easement
will not hold up issuance of the permit,
these comments need to be addressed
prior to CO/LOC for the project -
however finalizing this asap is
recommended.
Water Director
APPROVED AS TO FORM:
_____________________________
Aspen City Attorney
GRANTOR:
TRUE ROMANCE LLC, a Colorado limited
liability company
By:
Name:
Title:
Address: 701 Gibson Avenue, Aspen, CO 81611
[acknowledgements follow]
Easement needs to
be signed by property
owner for finalize the
document.
EXHIBIT C
ater Department Easement Agreement
missible Encroachments EXHIBIT
DRAFT R3
Sunday, March 6, 2022
ments in the 25’ Utility Easement. Water Department will not be responsible for
cess/repairs or replacement, it is the owner’s responsibility to replace infrastructure
This is the final
easement, remove
draft.
X:
1
2
.
5
+
/
-
Impacts to trees?
Parks needs to
approve the location
of the inlet box.
A callout has been added to sheet C.2.001 to get approval
from the parks department and for the city forester to be
present during installation of the curb inlet.
Comment Responses by High Country Engineering, Inc. are in red text below.
07/12/2022
Page: 3
Author: pjm
File Name: 90.Civil.701Gibson.20220322.pdf
Inlet box needs to be accessible
for cleaning. Are there
constraints on cleaning this
inlet?
Page: 3
Author: pjm
File Name: 90.Civil.701Gibson.20220322.pdf
THis sheet needs to be updated
in the plan set & the drainage
report narrative/calculations
need to be updated with the new
design. Include the variance in
the next round of submittal
DE
N
;
E,+/
-
2%
EX
:
1
2
.
5
+
/
-
Inlet box needs to be
accessible for
cleaning. Are there
constraints on
cleaning this inlet?
PROJECT NO.
2201051.00
PP-01
C.2.001
DA
R
I
CI
T
Y
O
F
A
70
1
G
I
B
S
O
N
15
-
I
N
C
TO
C
I
T
Y
O
F
A
S
PL
A
N
THis sheet needs to
be updated in the
plan set & the
drainage report
narrative/calculations
need to be updated
with the new design.
Include the variance
in the next round of
submittal
There are no foreseen accessibility constraints. The curb inlet
and catch basin are the typical COA structures. The inlet and
basin are also setback from the road, so access will be further
from vehicle traffic than a typical curb inlet layout.
The plan set and drainage report has been updated and a
variance request has been prepared and will be included in
submittal.
07/12/2022