THE CITY OF ASPEN CITY OF ASPEN ENGINEERING DEPARTMENT
SUFFICIENCY REVIEW REQUIREMENTS
If the project will increase impervious area(this includes enlarging a driveway, adding hard surface
patios, increasing the footprint of the house, etc.), disturb>200SF of exterior area(this includes
grading, even if a structure or hard surface isn't added), or add or repair snowmelt then an
engineering review will be required as part of the Building Permit or Landscape and Grading Permit
Application review process. All permit applications that must receive an engineering review are
required to schedule and participate in a Pre-Application Meeting with the Development Engineer.
The sufficiency checklist below and any necessary supporting documents should be completed prior
to this meeting, as they will be reviewed during the meeting. The Development Engineer's
signature on this checklist is required in order to submit a Building Permit Application.
Project Address: 211 W Hopkins Ave, Aspen CO
Project Common Location/Common Name: Pan Abode
Parcel ID Number: 2753512463003
Owner and Phone Number: Matt Joblon and Vaughan Capital Partners LP 508-344-2557
Contact and Phone Number and e-mail address: Jennifer Ramsey Jennifer.rmsey@rowlandbroughton.com
1. How much land will be disturbed? acres= 2000 sq.ft.
If one acre or more is disturbed, a CDPHE Construction General Permit is required.
Yes,Notice of Coverage has been included in the CMP.
No, A statement that Notice of Coverage is not required has been included in the CMP.
2. How much impervious area will be disturbed? 0 sq.ft. Added? 1000 sq.ft.
3. What is the estimated total impervious area of the site (not just the addition)? 1000 sq.ft.
4. What type of permit is being sought(Building or Landscape/Grading)? Building
5. What sub-basin(see Secion 1.5 of URMP)is the project located within? Aspen
6. What level of project is this—Minor or Major? Major
In general,the project is considered"Minor"if 200— 1000 sq ft of disturbance/work and"Major"
if > 1000 sq ft of disturbance/work.
RECEIVED
Revised 11-30-14
05/21/2021
ASPEN
BUILDING DEPARTMENT
The following information is required for the engineer's review. Please indicate if these documents
have been completed and are attached. If any of these documents are not applicable,please provide
an explanation in the space provided.
Included N/A
7. Minor Grading and Drainage Plan and Report
8. Major Grading and Drainage Plan and Report El
9. Compliant City of Aspen Survey ✓
10. Soils Report U I FT
11. Excavation Stabilization Plan U
12. Construction Management Plan (CMP)
TO BE SUBMITTED WITH FIRST COMMENT RESPONSES
13. Pu• c mprovemen equiremen s
14. Floodplain Development Requirements (n a
15. Mudflow Analysis FT El
I hereby declare the engineering information submitted in this sufficiency review for this
project is sufficient for City of Aspen Building Permit Application submittal.
Digitally signed by Jennifer Ramsey
Jennifer Ramsey DN US, 05/07/2021
E=jenn fifer.ramsey@ rowland broughton.com,
0="Rowland+groughton",CN=Jennifer Ramsey
Date:2021.05.07 21:44:07-06'00'
Applicant's Signature Date
City of Aspen Development Engineer's Signature Date