City of Aspen Engineering Department
City Hall
www.jvajva.com
130 S. Galena
Aspen, CO 81601
RE: 905 Hopkins Avenue Residence
Comment Response Letter
JVA Job No. 3382c
the rece
Dear Engineering Department: submittE
1. Max Q shall be calculated for the inlet. Then, show that the inlet has capacity to intercept flow shows tl
the dryv
with a .50 clogging factor per section 4.7.3 in the City of Aspen URMP. Please c
for each
JVA Response:A figure has been added to the end of the drainage letter showing the max on pg 2;
and that the inlet has capacity with a .50 do::in:factor. drainagc
trench d
• i - . - •. . - • ' e, a, con -c • e' - : . e • a' a:e - o area dre
the property or 2. the drainage system within the ROW, without negatively impacting neighbors. 4"x4" fits
Conveyance to curb and gutter in roadway must be shown. If the project team elects to tie into
the neighboring properties on-site curb, a drainage easement would be required. Another option
to explore is the re-grading of the alley. Please include
discussion of
JVA Response: The drainage pan has been extended beyond the driveway aloe proposed curb in
to capture flows from the alley and convey them into the existing curb and gut, drainage report for
the wall. 909 E Hopkins.
By routing the stormwater from the alley across the property line to the neighboring
properties curb and gutter we are matching the intended previous design. According to
page 2 of the drainage report for the previous development done by Timberline
Engineering, LLC. "drainage from offsite and adjacent properties will be deflected at the
property lines using mountable curb &gutter (spill type)... ".
e. e c -. • - . e- .s .. o •i - . • so -• s e e . '•n .c
info: Provide e;
the transfc
Ron Christian Easement
Electric Superintendent be 11'xl8
(970) 274-2492 clearance
ron.christian@cityofaspen.com side of the
transform
On next •lanset please call out transformer type and clearances from structures and p operty of clearan
line : front.
JVA Response:After a conversation between the MEP designer and Ron Christia , - .
transformer has been relocated, and a note has been added to reference COA Electrdcl 18/2 0 2 2
BOULDER FORT COLLINS WINTER PARK GLENWOOD SPRINGS DENVER ASPEN
BUILDING DEPARTMENT
Provide spot 905 Hopkins Avenue Residence
elevations at the 01/12/2022
location where the 2 of 2
overflow path will
cross the sidewalk to
4. Overflow p ensure that drainage will successfully reach the curb and gutter in the
roadway. Addi will successfully s not linear and therefore would impact the neighboring
property a; sh cross the sidewalk to path that does not rely on neighboring property.
meet the curb and
JVA Re gutter. een revised to route water to a new overflow path that
does not impact the neighboring property. The overflow path line has been updated to
reflect this more accurately.
5. Include City of Aspen Water Detail Sheet in planset.
JVA Response: The City of Aspen Water Detail Sheet has been included in this plan set as
sheet C1.1.
Sincerely,
NA, INCORPORATED
By:
J.R. S g,Senior Project Project Manager
RECEIVED
O1/18/2022
ASPEN
BUILDING DEPARTMENT
0056-2021 -BRES_909 E Hopkins_Engineering Comments2
40.Drainage Report.909 E Hopkins (905 Lot 2).2021.10.06.pdf(1)
® Subject: Dev Rev
- Page: 22 Max Q shall be calculated for the inlet. Then, show
Author: carlym that the inlet has capacity to intercept flow with a
Unit: Count .50 clogging factor per section 4.7.3 in the City of
Ff. File Name: 40.Drainage Report.909 E Hopkins (905 Lot Aspen URMP.
2).2021.10.06.pdf
90.Civil Plans.909 E Hopkins (905 Lot 2).2021.10.06.pdf(4)
Subject: Dev Rev-___ Page: [2] C1.0 GRADING, DRAINAGE,AND UTILITY PLAN Show that water in the valley pan at the driveway
Author: carlym connects to either:
Unit: Count 1.the drainage system on the property
File Name: 90.Civil Plans.909 E Hopkins(905 Lot or
2).2021.10.06.pdf 2.the drainage system within the ROW,without
negatively impacting neighbors. Coneveyence to
curb and gutter in roadway must be shown.
If the project team elects to tie into the neighboring
properties on-site curb, a drainage easement
would be required.
Another option to explore is the re-grading of the
alley.
, Subject: Dev Rev
,gym' _` % % Page: [2] C1.0 GRADING, DRAINAGE,AND UTILITY PLAN Please schedule a meeting with Ron Christian to
] = ;'FRI Author: carlym discuss the proposed transformer.
4' --, Unit: Count
s_ Contact info:
File Name: 90.Civil Plans.909 E Hopkins(905 Lot
2).2021.10.06.pdf Ron Christian
Electric Superintendent
(970)274-2492
ron.christian@cityofaspen.com
On next planset, please call out transformer type
and clearances from structures and property lines.
4 Subject: Dev Rev
w „ - , \::/ Page: [2] C1.0 GRADING, DRAINAGE,AND UTILITY PLAN Overflow path must show that drainage will
Author: carlym successfully reach the curb and gutter in the
Unit: Count
roadway.
,r' File Name: 90.Civil Plans.909 E Hopkins(905 Lot 2).2021.10.06.pdf Additionally, drainage pattern is not linear and
therefore would impact the neighboring property as
shown. Please show drainage path that does not
rely on neighboring property.
Subject: Dev Rev
Page: [3] CD1.0 SITE DETAILS Include City of Aspen Water Detail Sheet in
I Author: carlym planset.
Unit: Count
File Name: 90.Civil Plans.909 E Hopkins(905 Lot
2).2021.10.06.pdf
RECEIVED
01/18/2O22
ASPEN