Loading...
HomeMy WebLinkAboutFile Documents.1405 Red Butte Dr.0088-2022-BCHO (3)OBSERVATION REPORT Project Name:1405 Red Butte Drive Report #:01 Date:July 13, 2022 Site Time:10:30 AM Weather:Sunny Temperature:45 F Observed By:Tim Strickland, PE Accompanied:Nikolai Valdmanis, Don Stuber, Tarryn Link No items listed herein shall be interpreted as inspections or warranties of any kind. All items noted need to be verified, checked, and addressed by the project superintendent or project manager. 1.We visited the site on the morning of July 13 to observe the existing framing in order to understand the existing load path in order to design headers for the revised windows associated with the remodel. Prior to our visit, the interior finishes had been removed up to the ceiling of the second level. The state of the structure at the time of our visit is shown in Image 1 on the following page. 2.The following items were observed during this site visit: 2.1.The floor joists below the original second floor restroom had been significantly compromised. We noted one joist with no end support. Two remediation options are available, depending on whether the existing floor penetration is required to remain: ●If the penetration is to remain, provide a full depth 2x header to support the unsupported end of the existing joist shown in Image 2. The joist end and both ends of the header shall be supported by Simpson LUS210 joist hangers. Sister one additional 2x10 to each of the adjacent joists receiving the joist header. ●If the penetration is to be abandoned, sister a full length 2x10 to the existing joist, ensuring that both ends of the new joist are fully supported by the 2x4 wall at each end. See Image 2 - Action Required:YES 2.2.The floor joists below the original second floor restroom had been significantly compromised. We noted one joist that appeared to have been spliced, but the splice is inadequate for the loads imposed. Provide a new full length 2x10 joist to the existing joist, ensuring that both ends of the new joist are fully supported by the 2x4 wall at each end. See Image 3 - Action Required:YES 2.3.We observed the existing framing and have provided a header schedule for use by the contractor when enlarging existing openings to match the dimensions provided in the architectural drawings. Refer to attached schedule SDS-1 Action Required: NO 2225 E. MURRAY HOLLADAY RD., SUITE 110 ::SALT LAKE CITY, UTAH 84117 ::801.274.3950 ::structuralds.com 11/29/2022 OBSERVATION PHOTOGRAPHS IMAGE 1 - State of the structure during our 7/13 visit. Interior finishes removed and structure exposed IMAGE 2 - Unsupported floor joist. Refer to Item 2.1 for repair options 2225 E. MURRAY HOLLADAY RD., SUITE 110 ::SALT LAKE CITY, UTAH 84117 ::801.274.3950 ::structuralds.com 11/29/2022 IMAGE 3 - Insufficient joist splice. Sister new joist at this location per Item 2.2 IMAGE 4 - Overview of compromised floor framing below Level 2 bathroom. Items 2.1 and 2.2 are visible. 2225 E. MURRAY HOLLADAY RD., SUITE 110 ::SALT LAKE CITY, UTAH 84117 ::801.274.3950 ::structuralds.com 11/29/2022 OPEN OPEN WOOD HEADER CONC FND BELOW WOOD WALL GROUND LEVEL FLOOR / ROOF LEVEL WOOD HEADER NOTES: 1. SEE WOOD HEADER SCHEDULE FOR HEADER SIZE, AND NUMBER OF KING + TRIM STUDS. TYPICAL WOOD WALL ELEVATION DOUBLE 2X STUD AT END OF WALL MIN, TYP UNO STUD BLOCKING SILL ANCHOR PER SCHEDULE TOP PLATE KING STUDS TRIMMERS MAX SPAN MAX SPAN WALL BLOCKING THIRD-HT WALL BLOCKING MID-HT STUD SPACING SILL PLATE WOOD HEADER SCHEDULE MARK COMMENTSKING STUDSHEADERMAX SPAN NOTES: 1. SEE GENERAL STRUCTURAL NOTES FOR ALL OTHER REQUIREMENTS. 2. HDR 3 IS ONLY TO BE USED AT FULL HEIGHT WINDOW AT MAIN ENTRY AT BASE OF STAIRS AND IS NOT TO BE USED FOR ANY OTHER WINDOW OR DOOR OPENING. TRIM STUDS HDR-1 (2) 2x8 No. 1 3'-0" (2) 2x4 No. 1 (1) 2x4 HDR-2 (2) 11.7/8" LVL 6'-0" (4) 2x4 No. 1 (1) 2x4 HDR-3 (4) 2x8 No. 1 6'-6" (3) 2x8 No. 1 (1) 2x8 WALL STUDS TO BE 2x8. PROVIDE 5/8" DIA. X 6" TITEN HD ANCHORS AT 24" O.C. Scale: AS INDICATED Project No.: Date Status 2225 E. MURRAY HOLLADAY RD., SUITE 110 SALT LAKE CITY, UTAH 84117 801.274.3950 structuralds.com Supplemental Structural Sketch SHEET: SDS-1 1405 Red Butte HEADER SCHEDULE 22034 07/20/2022 CD July 20, 2022 11/29/2022