HomeMy WebLinkAboutresolution.council.042-02 RESOLUTION #
(Series of 2002)
A RESOLUTION APPROVING A CHANGE ORDER BETWEEN THE CITY
OF ASPEN, COLORADO, AND STANEK CONSTRUCTORS, 1NC., FOR THE
TERMS AND CONDITIONS FOR MODIFICATIONS TO THE EAST AND
WEST FILTER PLANTS AND AUTHORIZING THE CITY MANAGER TO
EXECUTE SAID CHANGE ORDER.
WHEREAS, Resolution 2001-71 had been approved on July 9, 2001, a
change order has been submitted between the City of Aspen, Colorado, and Stanek
Constructors, Inc., a copy of which is annexed hereto and made a part thereof.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF ASPEN, COLORADO:
Section 1
That the City Council of the city of Aspen hereby approves this change
order between the City of Aspen, Colorado, and regarding, a copy of which is
annexed hereto and incorporated herein, and does hereby authorize the City
Manager of the City of Aspen to execute said change order on behalf of the City of
Aspen.
Dated: ~ ~&c4~f~.
d./ '
I, Kathryn S. Koch, duly appointed and acting City Clerk do certify that the
foregoing is a true and accurate copy of that resolution adopted by the City
Council of the city of Aspen, Colorado, at a meeting held, t2002
~' ' S. Koch, City Cl~rk
CHANGE ORDER
City of Aspen Water Department No. i
PROJECT: City of Aspen Filter Modifications DATE OF ISSUANCE:
OWNER: City of Aspen
CONTRACTOR: Stanek Constructors OWNER's Project No. 2001-033
17301 WEST COLFAX AVE SUITE 401
GOLDEN, Colorado 80401
303-980-8233
ENGINEER: McLaughlin Water Engineers, Ltd.
ENGINEER'S Project No. 73.005.027
You are directed to make the following changes in the Contract Documents.
Description: Replacement of Sluice Gates, Addition of Flour/de Room, and other items, See attached description
sheet
Purpose of Change Order: WTP Improvements
Attachments: (List documents supporting change) CO fi 1 Work Summary, Cost SUmmary and Breakd6wn
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIME:
Original Contract Price: $ I34,000 Original Contract Time: 90 days to 12/15/0I
days or date
Previous Change Order No Net Change from previous
to No. Change Orders
0
None days
Contra~t Price prior to Contract Time prior to
tbds Change Order. this Change Order
$ $I34.000 90 Days- 12/15/01
.days or date
Net Increase (decrease) Net Increase (decrease)
of this Change Order of this Change Order
$ $99,000 210
days
Contract Price witti ali Contract T/me with all
approved Change Orders approved Change Orders
$ $233.000 June 30, 2002
days or date
ECOMMh~NDE'D:
(-"/Enter ("/ ~ ," Owr~er Contractor