HomeMy WebLinkAboutresolution.council.002-91
.
-
.
RESOLUTION ! ;L
(SERIES 1991)
RESOLUTION OF THE CITY COUNCIL OF ASPEN, COLORADO APPROVING THE
ASPEN MEADOWS CONCEPTUAL SPA PLAN AND ESTABLISHING
REQUIREMENTS FOR FINAL SPA PLAN SUBMISSION
WHEREAS, the Aspen City council, in order to establish meaningful
goals for the development of the Aspen Meadows, required that a
Master Plan be developed by the Meadows Consortium (comprised of
the Aspen Institute, Music Associates of Aspen, Aspen Center for
Physics, International Design Conference in Aspen, and Savanah
Limited Partnership); and
WHEREAS, on September 24, 1990 the Aspen Meadows Master Plan was
endorsed by the City Council with Resolution #42 (Series 1990);
and
WHEREAS, on October 16, 1990 the Aspen Planning and Zoning
commission adopted the Aspen Meadows Master Plan as an amendment
to the Aspen Area Comprehensive Plan by Resolution # 90-14; and
WHEREAS, at a regular meeting on November 20, 1990 the Aspen
Planning and Zoning commission heard presentations by the
Consortium representatives, found that the Conceptual SPA Plan
was consistent with the Master Plan and Conceptual SPA standards,
and forwarded a recommendation to the City Council for approval
with conditions; and
WHEREAS, at a duly noticed public hearing on December 10, the
City Council heard presentations by the Consortium
representatives, opened public comments, then continued the
public hearing to December 17; and
WHEREAS, on December 17, the city Council continued the public
hearing, then closed the public hearing. The Council then
discussed the specific conditions recommended by the Planning
Commission, and continued the discussions to December 20; and
WHEREAS, on December 20, 1990, the city Council approved the
Conceptual SPA Plan with conditions, as amended, by a vote of
4-1.
NOW THEREFORE BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
ASPEN, COLORADO:
Section 1:
The city Council finds that the Conceptual Development Plan for
the Aspen Meadows Property is consistent with the adopted Meadows
Master Plan.
1
.~
.
-
.
Section 2:
The Council finds the Conceptual application to be in compliance
with Sec. 7-804 (E) of the Aspen Land Use Code (revision date
August 1989), Review Standards for Development in a specially
Planned Area (SPA). Specifically, the Council makes the
following findings for the SPA Review Standards:
1. Whether the proposed development is compatible with or
enhances the mix of development in the immediate vicinity of
the parcel in terms of land use, density, height, bulk,
architecture, landscaping and open space. The Conceptual
Plan is consistent with the Meadows Master Plan and
preserves the academic and cultural character of the Meadows
property while being compatible with development in the
immediate vicinity. The Conceptual Plan provides for an
acceptable increase in density, while preserving important
open space. Specif ics about architecture and landscaping
will be addressed at Final Development Plan, with the
adopted Meadows Master Plan and HPC review providing the
applicant with adequate guidance.
2. Whether su:fficient public facilities and roads exist to
service the proposed development. The Conceptual Plan
provides adequate public facilities and roads to adequately
serve the development.
3 .
Whether the parcel proposed for development is generally
suitable for development, considering the slope, ground
instability and the possibility of mud flow, rock falls,
avalanche dangers and flood hazards. The Conceptual Plan
proposes development on land which is suitable for
development. Riparian areas, flood plains, and steep slopes
are not being proposed for development.
Whether the proposed development creatively employs land
planning techniques to preserve significant view planes,
avoid adverse environmental impacts and provide open space,
trails and similar amenities for the users of the project
and the public at large. The Conceptual Plan has endeavored
to preserve significant open space areas, as well as
environmentally sensitive areas through clustering of nel'i
development. The Conceptual Plan also provides a publ ic
trail network through the site in order to enhance the city-
wide trail system. These efforts are consistent with the
Meadows Master Plan and its vision for the property.
4.
5.
Whether the proposed development is in compliance with the
Aspen Area Comprehensive Plan. The Conceptual Plan is in
compliance with the Meadows Master Plan which was adopted as
an element of the Aspen Area Comprehensive Plan.
2
.~
.
e
.
Whether the proposed development will require the expendi-
ture of excessive public funds to provide public facilities
for the parcel, or the surrounding neighborhood. The
Conceptual Plan provides for adequate public facilities for
the proposed development without adversely effecting the
surrounding neighborhood. The provision of these publ ic
facilities is at the expense of the applicant and will be
detailed in the Final Development Plan.
7. Whether proposed development on slopes in excess of twenty
percent (20%) meet the slope reduction and density
requirements of Sec. 7-903(B) (2) (b). The Conceptual Plan is
in compliance with this standard because this property has
no underlying zoning, therefore, the property has no density
requirement to reduce.
6.
8.
Whether there are sufficient
proposed development. The
residential Growth Management
Development Plan approval.
GMQS allotments for the
applicant shall receive
allotment prior to Final
Section 3:
The City Council approves the Aspen Meadows Conceptual SPA Plan
with the following conditions:
Prior to submission for Final Development Review:
1. The applicant shall submit a construction schedule.
2. The visual impact (height and linear appearance) of the
underground parking lot at the tennis courts shall be reduced as
much as possible. A detailed parking plan shall be provided
indicating any existing parking to be removed and any proposed
parking at the Meadows.
3. Those elements listed in the Master Plan must receive
Conceptual and Final approval by the Historic Preservation
committee (HPC) unless the HPC determines that final approval is
not necessary prior to Final SPA submission.
4. A Subdivision Plat in full compliance with Section 7-1004 D.l
and D.2 shall be submitted which describes the specific parcels
to be held in separate ownership, including the Conservation Area
to be purchased by the city.
5. Trail easements on the Meadows property must be dedicated on
the Subdivision Plat consistent with the Meado\'is Master Plan.
The trail accessing the west Meadows area from Seventh at North
shall follow the boundary of the racetrack open space as shown on
the Master Plan.
6. All utilities shall be underground.
Easement needs of each
3
.
e
.
utility shall be addressed at Final submission. Major utilities
mU5t sign off on final submission.
7. The applicant shall investigate with the Engineering
Department how to comply with drainage and runoff issues and be
prepared to specify mitigation in the final application and grant
all easements as required.
B. Seventh street shall be the primary access for two way traffic
into and out of the Meadows.
9. Costs associated with the Seventh Street expansions or
alterations shall be borne by the applicant.
10. Trails and bikeways shall be implemented in compliance with
the adopted Pedestrian and Bikeway Plan. The pedestrian trail
along the old Meadows road alignment shall be reconfigured to
conform to design standards set forth in this plan.
11. A fugitive dust control plan must be approved by state and
County agencies prior to issuance of any excavation or building
permits.
12. Food service facilities shall comply with all state and local
environmental health codes.
13. Energy efficient measures shall be a priority throughout the
Meadows property.
14. Housing mitigation for the 23.69 low income employees shall
be provided through cash-in-lieu for 16.69 employees as well as
on-site housing for seven employees, deed restricted to low
income.
15. The affordable housing units must be deed restricted
the Housing Authority's requirements for size, type,
income, and occupancy standards.
meeting
asset,
16. Condominiumization fees shall be paid for the eight existing
3 bedroom townhomes totaling $64,240, payable before plats are
filed.
17. New residential units must receive GMQS allotments prior to
Final SPA approval.
lB. The following areas shall be rezoned to a new zone district
called OS-Open Space: the 25 acre parcel currently zoned C-
Conservation (with consent of the applicant), the Racetrack, Sage
Meadow, Anderson Park, and the Tent Meadow, as designated in the
Master Plan. Upon further review, some historic use of the
parcel may indicate a slightly different approach to zoning
(SPA) .
4
.~
.
e
.
19. The Rehearsal Hall shall be located to
Tent and shall be screened along the
boundary with a vegetative buffer.
20. A detailed description of the use program for the Rehearsal
Hall shall be provided. This must address seasonal use, daily
use, use by outside entities, public performances, etc.
the east of the Music
eastern MAA property
21. A fire
concert with
submission.
suppression/protection plan must be developed in
the Fire Marshall's Office and included in the Final
23. The applicant shall commit to making necessary corrections to
the Sanitation District trunk line as mentioned in the referral
letter.
24. A detailed transportation plan shall be submitted with the
Final Plan application. The bus loading area and its interface
with pedestrian access ways must be addressed. The
transportation plan shall also provide specific details on items
mentioned in the Master Plan: vehicle size regulations, small
non-diesel buses, Rio Grande shuttle, paid parking, residential
parking permits, lodge 1 imousine, and which possibly includes
paving the M.A.A. parking lot. In addition the transportation
plan shall evaluate the effectiveness of less underground parking
and a better transit system throughout the property.
25. The proposed building envelope for the Health Club expansion
shall be shown on the Final SPA Plan. The building shall not be
expanded any further to the north. When designing the new road
in front of the club, the trees and pond shall be kept or
relocated.
26. Impacts of construction and development on the Meadows
property to wildlife and native vegetation should be addressed at
the final development plan and appropriate mitigation measures
placed on the final approval.
27. A digitized copy of the Subdivision plat is requested by the
Engineering Department prior to recordation.
Dated:
c;? <<-~- ~ 1
c:</ ' 199;.
~~~
William L. Stirling, Mayor
I, Kathryn S. Koch, duly appointed and acting City Clerk do
5
~
.
e
.
certify that the foregoing is a true and accurate copy of that
resolution adopted by the City Council of the City of Aspen,
Colorado at a meeting held ~.a.L {;I'" /;1 , 19~.
~h~~'~~k
,-
jtkvj/meadows.ccreso
6
.4