HomeMy WebLinkAboutresolution.council.037-95 RESOLUTION NO. ~--
(SERIES OF 1995)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
ASPEN, COLORADO APPROVING CONCEPTUAL
PLANNED UNIT DEVELOPMENT REVIEW FOR THE
PARKS AND GOLF DEPARTMENT MAINTENANCE FACILITY AND OFFICE,
ASPEN, COLORADO
WHEREAS, the Aspen Parks and Golf Department has submitted
a Planned Unit Development review application to expand their
office and maintenance facility at the Golf Course; and
WHEREAS, the Department requested a four step review process
to ensure that their design proposals would be found acceptable
before full architectural drawings were developed; and
WHEREAS, the Planning and Zoning Commission did review the
conceptual proposal at their May 2, 1995 public meeting; and
WHEREAS, the Commission found that the proposal was a
necessary expansion and that the conceptual proposal was the least
impactive to the surrounding neighborhood, users of the golf course
and Highway 82; and
WHEREAS, the Commission amended the conditions of approval,
identified those items that must be included in the fina~ PUD
application and recommend to Council conceptual PUD approval; and
WHEREAS, the Aspen City Council has reviewed the conceptual
application at a duly public noticed meeting; and
WHEREAS, Council has considered the conditions of approval as
amended by the Commission and the Commission's recommendation.
NOW THEREFORE BE IT RESOLVED by the Aspen City Council that it does
hereby approve the conceptual PUD development proposal for the
expansion of the Parks and Golf office and maintenance facility
with the following conditions:
1. A final architectural plan with elevations of all proposed
buildings including identification of building materials shall be
included in the submitted final PUD application.
2. A detailed lighting plan and landscape plan shall be included
in the final PUD application.
3. A housing mitigation plan shall be provided to mitigate 1.8
employees in the submitted final PUD application.
4. A storm drainage plan shall be included in the submitted final
PUD application.
5. A conceptual sidewalk/curb/gutter and paving plan shall be
developed with the Engineering Department and submitted for review
during final PUD review.
6. A revised site plan shall be included in the final PUD
application and shall include:
a. trash/recycle area and bike storage/racks;
b. on-site parking spaces; and
c. relocated 15th Tee and berm near the Tee.
7. Oil and sand separators shall be installed where vehicles are
serviced and stored. All chemical/fertilizer storage must be
designed to prevent leakage into the public sewer system.
8. The four inch sewer service line shall be replaced.
9. The project shall install an approved automatic sprinkler
system.
10. The application for final PUD review shall include the
following items:
a. detail description of building material
b. detailed landscape plan
c. a percentage break-out of golf use and parks use of the
facility
d. analysis of equipment and depreciation costs
e. elevations of the proposed building including heights
f. employee mitigation plan
11. Ail material representations made by the applicant in the
application and during public meetings with the Planning and Zoning
Commission shall be adhered to and considered conditions of
approval, unless otherwise amended by other conditions.
APPROVED by the Council at a regularly scheduled meeting June 12,
BY:
John Bennett, Mayor
I, Kathryn S. Koch, duly appointed and acting City Clerk do certify
that the foregoing is a true and accurate copy of that resolution
adopted by the City Council of the City of Aspen, Colorado at a
meeting held ~ /3 , 1995.
/
Kathryn S. Koch, city Clerk