A RESOLUTION APPROVING A PROFESSIONAL SERVICES AGREEMENT AMENDMENT
BETWEEN MCLAUGHLIN WATER ENGINEERS AND THE CITY OF ASPEN, COLORADO,
FOR PROFESSIONAL SERVICES RELATING TO RELOCATION OF WATER
TRANSMISSION MAIN AT CASTLEIMAROON CREEK ROAD INTERSECTION, AND
AUTHORIZING THE WATER DIRECTOR TO EXECUTE SAID AGREEMENT AMENDMENT
ON BEHALF OF THE CITY OF ASPEN, COLORADO.
WHEREAS, the Aspen City Council approved an engineering services agreernent with
McLaughlin Water Engineers; and
WHEREAS, there has been submitted to the City Council a professional services agreement
amendment between McLaughlin Water Engineers, and the City of Aspen, a true and accurate copy
of the task authorization is attached hereto as Exhibit "A";
NOW, THEREFORE, BE.IT RESOLVED BY THE COUNCIL OF THE CITY OF ASPEN,
COLORADO:
That the City Council of the Cit~ of Aspen hereby approves that professional services
agreement amendment to authorize engineering services for "Project 1, Maroon Creek Road"
between McLaughlin Water Engineers, and the City of Aspen, a copy of which is annexed hereto and
incorporated herein, and does hereby authorize the Water Director of the City of Aspen to execute
said task athorization as an amendment to the existing agreement on behalf of the City of Aspen.
/3
INTRODUCED, READ AND ADOPTED by the City Council of the City of Aspen on the
daY~998.
JOhns.t:M!t~
. I, Kathryn S. Koch, duly appointed and acting City Clerk do certify that the foregoing is a
tiue and accurate copy of that resolution adopted by the City Council of the City of Aspen, Colorado,
at a meeting held on the day hereinabove stated.
r".
~.
i~
MWE
McLAUGHLIN WATER ENGINEERS, ltd,
210 AAABC ASPEN, COLORADO 816] 1
970-925-1920 970-925-1974 tax mweaspen@rofnet
MEMORANDUM
TO: Phil O. - City of Aspen Water Department
FROM: Dean D. - MWE Aspen
DATE: June 25, 1998
RE: Proposal for Consulting Engineering Services - Highway 82\LightRail\Pedestrian
Bypass Waterline Realignment and Improvement Projects.
As per you request I am attaching our proposal for the Highway 82\LightRaillPedestrian
Underpass Waterline Realignment and Improvement Projects. We have grouped all five projects
into one estimate, We have attempted to cover all the proposed work in our Scope of Services,
however final Highway alignment changes and other factors may require changing the Scope to
accommodate the required work.
If you have any questions, please feel free to call me at any time.
Thanks
Dean D
o
EXHffiIT "A"
SCOPE:
HIGHW A Y82\LIGHT RAIL\PEDESTRlAN UNDERPASS
WATERLINE REALIGNMENT AND IMPROVEMENT PROJECTS
This project consists of perfomring consulting engineering work for design services for realignment
of existing waterlines dealing with the installation of Highway 82 improvements, light rail train
appurtenances, and pedestrian underpasses along Highway 82 from Maroon Creek Road to the Aspen
Airport Business Center. The design and construction phases needed will include preparation of base
mapping, line design and construction specifications, construction inspection, Record Drawings, and
easements preparation for the five separate projects included in this proposal
PROJECTS:
1, Maroon Creek Road Intersection: The proposed improvements may require relocation of
existing 12 and lO-inch waterlines, relocation of existing valves, addition of a Pressure
Reducing Vault, and other line improvements stemming from the installation of the
Roundabout, light rail station and tracks, pedestrian underpass and bridge, and other work
~
2. Truscott Place Entrance and New Maroon Creek Bridge: The existing 16 and 1 O-inch main
water lines will need to be realigned to work with the new pedestrian underpass, The
construction of a new Maroon Creek bridge would allow the installation of an additional 12-
inch water line to feed the entire water system on the North side of the bridge, 12-inch line
extension and bridge crossing.
3. Highway 82 Four Lane Improvements. Several existing water lines, valves, fire hydrants,
and other water system improvements are located in the existing and proposed roadways that
need to be removed, capped, or relocated.
4. Stage Road\Owl Creek Road\Buttermilk Roadway improvements and pedestrian
underpass: Several water mains including a 16 and 8-inch waterlines, will need to be realigned
to work with the new improvements.
5. Airport and Airport Business Center intersections and pedestrian underpass: Roadway and
underpass improvements will require realignment of 18-inch and 8-inch water lines and other
appurtenances.
~
r"'
Base Maps
Prior to the design for the line realignments and relocations, base maps will be generated using
existing GIS mapping from the City of Aspen. The City's mapping does not show existing utilities
accurately enough to be able to use them for design purposes. MWE reconunends that utility
companies, telephone, gas, tv, sewer, water, and electrical, be contacted and have utilities be located
in the field for as built conditions. The asbuilt locates will be added to the mapping provided by the
City to create base maps for design purposes, This work will include reviewing existing as built
drawings, contacting utilities, site visits, field locating utilities, and transferring asbuilts to the base
maps for design. These maps will also need to incorporate the proposed Highway 82 improvements,
pedestrian underpass locations and road designs. We have assumed that the City of Aspen and
Colorado State Department Highways will be providing drawings capable of being used by Autocad
R 14.
Desi!!n Phase
r"'
The design phase will include taking the base maps compiled above and designing relocated water
facilities to meet proposed highway designs and field conditions, The design will require drawings
to be drafted for the line relocations, including alignment and all other work to be completed as part
of the Highway 82 work. It is assumed that MWE will use existing City of Aspen pipeline details,
installation, and material specifications for this project, MWE will provide the drawings at
approximately I" = 20-feet horizontal, 1"= 2-foot vertical on 24" x 36" reproducible mylars to the
city plus electronic files in DXF format. MWE will also provide preliminary design of the line
replacements including 50% and 90% design level for review by the City of Aspen. Weare assuming
that lines will be relocated within existing easements or ROW's,
Construction Phase
This work will includes Construction Observation and Record drawing preparation, The record
drawings will require drawings to be drafted for the replacements detailing alignment and all other
work completed as part of the water line extension, MWE will provide the as-built drawing on 24"
X 36" reproducible mylar( s) to the City, plus the electronic file in DXF format, All survey and legal
work is to be performed by the City of Aspen and should include an alignment survey, preparation
of legal descriptions, plotting easements and ROW on construction plans and recording of the
easement. New easements will only be required ifrealigrunent design requires the new aligrunent to
be outside the existing easement or ROW. Surveying will be required to verifY both horizontal and
vertical control with the existing system and the City's GIS system and new base monument layout.
To insure that the installation of the water line extension will be installed according to City of Aspen
and MWE drawings and specifications, MWE will provide inspection services. MWE will make daily
site visits to the project to review the contractor progress, installation methods, materials, and other
pertinent installation requirements. MWE will monitor tests and certifY that the water line meets
design and specified quality requirements,
~
r'
I""""
/""'"'..
For ease of billing and other cost purposes all five projects are lumped into one cost estimate,
Estimated Costs
1. Maroon Creek Road
Base Maps and Prelim Work
Design Phase
Construction Phase
Surveying and Easements **
$1,070.00
$7,700.00
$4,500.00
By others
SUBTOTAL
$13.270.00
2. Truscott Place Entrance
Base Maps and Prelim Work
Design Phase
Construction Phase
Surveying and Easements **
$],070.00
$]2,500,00
$6,400,00
By others
SUBTOTAL
$19.970.00
3. Hwv 82 4 Lane Improvements
Base Maps and Prelim Work
Design Phase
Construction Phase
Surveying and Easements **
$600.00
$1,700,00
$500,00
By others
SUBTOTAL
$2.800.00
r
r'.,
~,
4. Stae-e Road\Owl Creek\B-milk
Base Maps and Prelim Work
Design Phase
Construction Phase
Surveying and Easements **
$800.00
$3,100.00
$1,000,00
By others
SUBTOTAL
$4.900.00
5. Aspen Airport and Business Center
Base Maps and Prelim Work
Design Phase
Construction Phase
Surveying and Easements **
$1,340.00
$4,100,00
$1,000.00
By others
SUBTOTAL
$6.440.00
TOTAL PROJECT ESTIMATED COSTS
$47.380.00