HomeMy WebLinkAboutresolution.apz.009-05RESOLUTION NO. 9
(SERIES OF 2005)
A RESOLUTION OF THE CITY OF ASPEN PLANNING AND ZONING
COMMISSION RECOMMENDING CITY COUNCIL APPROVE A
CONCEPTUAL PLANNED UNIT DEVELOPMENT AND A CONCEPTUAL
TIMESHARE FOR THE LODGE AT ASPEN MOUNTAIN, LEGALLY
DESCRIBED AS BLOCK 6 EAMES ADDITION AND LOTS 7-20, BLOCK 11 OF
THE EAMES ADDITION AND A SMALL METES AND BOUNDS TRIANGULAR
SHAPED AREA, CITY OF ASPEN, PITKIN COUNTY, COLORADO.
Parcel ID:
2735-131-23-001 (Mine Dump Apartments)
2735-131-13-001 (Parcel with the Single-Family Residence)
WHEREAS, the Community Development Department received an application
from the Aspen Land Fund II, LLC, represented by Sunny Vann of Vann Associates for a
Conceptual Planned Unit Development and Conceptual Timeshare; and,
WHEREAS, the original application submitted (dated October 1, 2003) proposed
a 204,500 square foot, 121-unit, mixed use, hotel/fractional ownership project consisting
of 76 hotel rooms, 29 fractional units, 4 condominium units, 12 affordable housing units,
commercial and ancillary space and a total of 156 spaces in two, sub-grade parking
garages; and,
WHEREAS, the Community Development Department received referral
comments from the Aspen Consolidated Sanitation District, City Engineering, Building
Department, Fire, Streets, Housing, Environmental Health, Parks and Water Departments
as a result of the Development Review Committee meeting; and,
WHEREAS, said referral agencies and the Aspen Community Development
Department reviewed the proposed Conceptual PUD and Conceptual Timeshare and
recommended approval with conditions; and,
WHEREAS, during a regular meeting on Mamh 2, 2004, the Planning and
Zoning Commission recommended that City Council deny, by a three to one (3-1) vote,
the Conceptual PUD and Conceptual Timeshare request for the Lodge at Aspen
Mountain; and,
WHEREAS, the Applicant submitted an amended application on December 22,
2004, for reconsideration by the Planning and Zoning Commission; and,
WHEREAS, pursuant to Section 26.445 of the Land Use Code, Conceptual PUD
approval may be granted by the City Council at a duly noticed public hearing after
considering recommendations by the Planning and Zoning Commission, the Community
Development Director, and relevant referral agencies; and,
WHEREAS, pursuant to Section 26.590 of the Land Use Code, Conceptual
Timeshare approval may be granted by the City Council at a duly noticed public heating
after considering recommendations by the Planning and Zoning Commission, the
Community Development Director, and relevant referral agencies; and,
WHEREAS, the City of Aspen / Pitkin County Housing Authority forwarded a
unanimous recommendation of approval to City Council to approve the proposed
affordable housing mitigation and replacement units for the project at their meeting held
on November 19, 2003; and,
WHEREAS, Conceptual PUD and Conceptual Timeshare review by the Planning
and Zoning Commission requires a public hearing and this application was reviewed at a
public hearing where the recommendations of the Community Development Director and
comments from the public were heard; and,
WHEREAS, during a regular meeting on February 15, 2005, the Planning and
Zoning Commission opened a duly noticed public heating to consider the amended
project and continued the public hearing to February 22, 2005; and,
WHEREAS, during a regular meeting on February 22, 2005, the Planning and
Zoning Commission opened a duly noticed public hearing to consider the amended
project and continued the public hearing to March 29, 2005, where the Commission
discussed the proposal and continued the hearing to April 5, 2005; and,
WHEREAS, during a regular meeting on April 5, 2005, the Planning and Zoning
Commission opened a dul~, noticed public hearing to consider the amended project and
continued the public hearing to April 12, 2005; and,
WHEREAS, during a special meeting on April 12, 2005, the Planning and
Zoning Commission opened a duly noticed public hearing to consider the South Aspen
Street Winter Maintenance Plan and continued the public heating on the Lodge at Aspen
Conceptual PUD and Timeshare to May 10, 2005; and,
WHEREAS, during a special meeting on May 10, 2005, the Planning and Zoning
Commission opened a duly noticed public hearing to consider the amended project and
continued the public hearing on the Lodge at Aspen Conceptual PUD and Timeshare to
June 14, 2005; and,
WHEREAS, during a special meeting on June 14, 2005, the Planning and Zoning
Commission opened a duly noticed public hearing to consider the amended project and
continued the public hearing on the Lodge at Aspen Conceptual PUD and Timeshare to
June 21, 2005; and,
WHEREAS, during a regular meeting on June 21, 2005, the Planning and Zoning
Commission opened a duly noticed public hearing to consider the amended project and
continued the public hearing on the Lodge at Aspen Conceptual PUD and Timeshare to
July 5, 2005; and,
WHEREAS, during a regular meeting on July 5, 2005, the Planning and Zoning
Commission approved Resolution No. 9, Series of 2005, by a four to one (4-1) vote,
recommending that City Council approve the amended Conceptual PUD and Conceptual
Timeshare application, with the findings and conditions listed herein; and,
WHEREAS, Conceptual PUD and Conceptual Timeshare approval shall only
grant the ability for the Applicant to submit a Final PUD and Timeshare Application and
the proposed development is further subject to Final PUD review, Timeshare,
Subdivision, Growth Management Quota System, Special Review, Condominiumization,
8040 Greenline approval pursuant to the Municipal Code; and,
WHEREAS, The Commission finds that the development review standards for a
Conceptual PUD and Conceptual Timeshare plan are met by the revised proposal,
provided that the conditions established herein are complied with.
NOW, THEREFORE BE IT RESOLVED that the Planning and Zoning Commission
recommends that the City Council approve the revised Conceptual Planned Unit
Development and Conceptual Timeshare application for the Lodge at Aspen Mountain
allowing a 185,000 square foot, 104-unit, mixed use, hotel/fractional ownership project
consisting of 82 hotel rooms, 22 fractional units, 4 condominium units, 12 affordable
housing units, commercial and ancillary space and a total of 156 parking spaces in two,
sub-grade parking garages, subject to the conditions established herein.
Section 1: Final PUD Application
The Final PUD application shall be generally consistent with the conceptual proposal and
shall include the following:
1. An application for Final PUD, Final Timeshare, Subdivision, Rezoning, Special
Review for Parking, Growth Management Quota System, 8040 Greenline Review,
Subdivision, Timeshare, Condominiumization. A pre-application conference with a
mmnber of the Community Development Department is required prior to submitting
an application.
Delineation of all dimensional provisions to become requirements of the PUD.
A proposed subdivision plat, PUD plans, subdivision/PUD Agreement and other
submittal requirements specified in Section 26.445.06003).
A construction plan describing timing of construction components, areas of
disturbance, contractor parking, and a physical plan for maintaining adequate
access, including emergency access, to land uses remaining active during
construction. The construction plan shall indicate that all construction hauling
shall occur on South Aspen Street.
A detailed phasing plan that describes overall timing of specific project phases,
including the off-site improvements and describing construction affects on the
neighboring properties.
A detailed street design plan that includes provisions for slteet signage, pavement
markings and pedestrian facilities. South Aspen Street adjacent to the Lodge at
Aspen Mountain shall be increased in width so that the back of curb is located on the
property line adjacent to South Aspen Street. Juan and Garmisch Streets adjacent to
the Lodge at Aspen Mountain shall be increased in width to twenty-six (26) feet.
Proposed public sidewalk easements shall be included in the final PUD plans along
Garmisch and Juan Streets where public sidewalks are proposed to be constructed in
conjunction with the development proposal.
8. A complete storm water management plan that includes a drainage plan and report
performed by a licensed Engineer within the state of Colorado.
Section 2: Juan Street Air Space Riehts
As part of the final PUD application the Applicant shall submit a document outlining the
terms of the use of the public air space over the Juan Street right-of-way for the private
bridge. Said document will be reviewed as part of the final PUD application with the intent
that it would serve as an agreement between the Applicant and the City for the use of the
right-of-way.
Section 3: Dean Avenue Improvements
The final PUD application shall contain a detailed landscape and improvements plan for
the Dean Avenue Right-of-way abutting the Lodge at Aspen Mountain property that is
consistent with the Dean Street pedestrian improvements plan that Staff has initiated.
Section 4: Fire Access and Mitigation
The bridge over Juan Street shall be at least sixteen and a half feet above Juan Street to
allow for fire trucks to pass beneath it. The Applicant shall also submit a plan for
fighting fires within the project's parking garages at the time of building permit.
Section 5: Outdoor Lighting and Street Lights
The Applicant shall provide a detailed exterior lighting plan at time of final PUD application
submittal. The exterior lighting plan shall include street lighting fixtures proposed in the
adjacent right-of-ways as is required pursuant to Land Use Code Section
26.580.020(B)(1)(w), Street lights.
Section 6: Air Quality
The Applicant shall submit a PM-10 mitigation plan as part of the final PUD submission
that includes air quality mitigation measures recommended by the City of Aspen
Environmental Health Department.
Section 7: South Aspen Street
The Applicant shall provide the City with annual funding for an additional seasonal
employee in the Streets Department during the winter and spring months to do increased
snow plowing, snow hauling on South Aspen Street throughout the construction process and
as long as the hotel is in operation. The Applicant shall provide a detailed plan outlining a
funding amount estimate, timing of payment, method of payment for the additional Streets
Department Staffperson as part of the final PUD application. In the event that City Council
deems it appropriate to snowmelt South Aspen Street in relation to development of other
properties accessed fi.om South Aspen Street, the Applicant shall join any future
improvements district formed to improve South Aspen Street and shall study the possibility
of reserving space on the property suitable to house thc mechanical equipment needed to
snowmelt thc street between Conceptual approval and Final PUD submittal.
Section 8:
The Applicant shall submit a detailed employee housing mitigation plan as part of their
Growth Management application that shall be applied for prior to or in conjunction with the
Final PUD application.
Section 9:
This Resolution shall not effect any existing litigation and shall not operate as an
abatement of any action or proceeding now pending under or by virtue of the ordinances
repealed or amended as herein provided, and the same shall be conducted and concluded
under such prior ordinances.
Section 10:
If any section, subsection, sentence, clause, phrase, or portion of this Resolution is for
any reason held invalid or unconstitutional in a court of competent jurisdiction, such
portion shall be deemed a separate, distinct and independent provision and shall not affect
the validity of the remaining portions thereof.
APPROVED by the Commission by a four to one (4-1) vote at a regular meeting on July
5, 2005.
APPROVED AS TO FORM:
DaSd Hoefer, Asst. City ~[ttomey
ATTEST:
~ackie Lothian, Deputy City Clerk
PLANNING AND ZONING
C(~MMISSION:
Jasmine Tygre, Chair ~/Q~