HomeMy WebLinkAboutresolution.hpc.037-2005RESOLUTION OF THE ASPEN HISTORIC PRESERVATION COMMISSION (HPC)
APPROVING AN APPLICATION FOR MAJOR DEVELOPMENT (FINAL) FOR THE
PROPERTY LOCATED AT 990 GIBSON AVENUE, UNIT 2, ALPINE ACRES
CONDOMINIUM, CITY AND TOWNSITE OF ASPEN, COLORADO
RESOLUTION NO. 37, SERIES OF 2005
PARCEL ID: 2737-074-10-002
WHEREAS, the applicants, Steven and Sharon Van Meter, represented by Warren Palmer, have
requested Major Development (Final) for the property located at 990 Gibson Avenue, Unit 2,
Alpine Acres Condominium, City and Townsite of Aspen, Colorado; and
WHEREAS, Section 26.415.070 of the Municipal Code states that "no building or structure
shall be erected, constructed, enlarged, altered, repaired, relocated or improved involving a
designated historic property or district until plans or sufficient information have been submitted
to the Community Development Director and approved in accordance with the procedures
established for their revie~v;" and
WHEREAS, for Final Major Development Review, the HPC must review the application, a staff
analysis report and the evidence presented at a hearing to determine the project's conformance
with the City of Aspen Historic Preservation Design Guidelines per Section 26.415.070.D.3.b.2
and 3 of the Municipal Code and other applicable Code Sections. The HPC may approve,
disapprove, approve with conditions or continue the application to obtain additional information
necessary to make a decision to approve or deny; and
WHEREAS, Amy Guthrie, in her staff report dated September 28, 2005, performed an analysis
of the application based on the standards, found that the review standards and the "City of Aspen
Historic Preservation Design Guidelines have been met, and recommended approval; and
WHEREAS, at their regular meeting on September 28, 2005, the Historic Preservation
Commission considered the application, found the application was consistent with the review
standards and "City of Aspen Historic Preservation Design Guidelines" and approved the
application by a vote of 6 to 0.
NOW, THEREFORE, BE IT RESOLVED:
That HPC hereby recommends Major Development (Final) for the property located at 990
Gibson Avenue, Unit 2, Alpine Acres Condominium, City and Townsite of Aspen, Colorado
with the following conditions:
1. There shall be no deviations from the exterior elevations as approved without first being
reviewed and approved by HPC staffand monitor, or the full board.
2. The conditions of approval will be required to be printed on the cover sheet of the
building permit plan set and all other prints made for the purpose of construction.
3. The applicant shall be required to provide the contractor with copies of the HPC
resolution applicable to this project. The contractor must submit a letter addressed to
10/27/2005 12:401
SILVIA DAVIS PITKIN COUNTY 00 R 11,00 D 0.00
HPC staff as part of the building permit application indicating that all conditions of
appro,~al are known and understood and must meet with the Historic Preservation Officer
prior to applying for the building permit.
The General Contractor and/or Superintendent shall be required to obtain a specialty
license in historic preservation prior to receiving a building permit.
APPROVED BY THE COMMISSION at its regular meeting on the 28th day of September
2005.
Approved as to Form:
David-Hoefer, Assistant Clty Attorney
Approved as to content:
HISTORIC PRESERVATION COMMISSION
air
Kathy Strit/gland, Chief Deputy Clerl~ \