TO: Bruce Gillis, Ac~ing Chairman, Aspen Planning
and Zoning Commission
FROM: Dave Ellis, City Engineer
RE: Bay Street Estate Subdivision -Preliminary Plat
DATE: July 10,1973
1) The major problem of the area is the inadequate
existing right-of-way. Dedication of land to
provide for a 60' wide right-of-way will be
required; this will amount to a strip approxi-
mately 20' in width along the frontage.
2) The subdivider should be required to enter into
a covenant running with the land to join any
future storm drainage district or street im-
provement district,' including paving, sidewalks,
and curb and gutter.
3) The building design and/or site plan should
incorporate the capability for storm water
retention.
4) The landscaping plan should essentially be the
protection of existing trees and shrubs. This
can be provided for on the landscaping notes
included on the plat.
5) Aspen Metropolitan Sanitation District must
be assured an easement for the existing sewer
if they do not already have one. This would
apply to any other existing utilities.